PMI Project Management Principles 
A Point of Reference 
(based on the 5th Edition PMBOK® Guide) 
By Tom Tiede
2 
Agenda 
This material will cover the following project management topics: 
• What is PMI and the PMP? 
• Why PMI Project Management Principles are 
Useful to Know 
• A Few Basic PMI Definitions 
• Five Process Groups 
o Initiating 
o Planning 
o Executing 
o Monitoring and Controlling 
o Closing 
• Ten Knowledge Areas 
o Integration 
o Scope 
o Time 
o Cost 
o Quality 
o Human Resources 
o Communication 
o Risk 
o Procurement 
o Stakeholders 
• Project Management Terms, such as: 
o Triple Constraint 
o Project Charter 
o Project Management Plan 
o Work Breakdown Structure (WBS) 
o Predecessor Relationships 
o Earned Value Management 
o Gold Plating 
o Responsibilities Assignment Matrix 
o Forming, Storming, Norming, Performing, 
Adjourning 
o Communication Noise 
o Risk Probability and Impact Matrix 
o Contract Type 
o Stakeholder Power vs. Interest Grid 
• Code of Ethics and Professional Conduct 
o Honor 
o Responsibility 
o Respect 
o Fairness 
o Honesty
3 
What is PMI and the PMP? 
The Project Management Institute (PMI) is the world’s largest 
membership association for the advocacy of Project and Program 
management. 
• Over 400,000 current members across 180 countries 
• Over 600,000 PMI certification holders 
• Their most widely recognized certification is the PMP (Project Management 
Professional). The PMP credential recognizes your: 
o Experience, 
o Education, and 
o Competency to lead and manage projects 
• Earning the PMP credential requires: 
o A bachelor’s degree and 4,500 hours of documented project management experience, or a 
secondary degree and 7,500 hours of documented project management experience 
o 35 hours of certified project management training 
o Passing the certification exam 
• Regardless of your inclination to pursue PMP certification, PMI project management 
principles apply to your role as a project leader or stakeholder 
The purpose of this material is to share a few PMI project management 
principles that apply to your role as a project leader or stakeholder
4 
Why Is This Useful to Know? 
Leveraging prescribed PMI project management principles reduces the 
risk and impact of costly project omissions, changes, and errors. 
Project 
Initiation 
Cost of Resolving Project Omissions, Changes, or Errors 
Project 
Planning 
Project 
Execution 
Project 
Closure 
(Illustrative) 
The PMI approach places great emphasis on project initiation and planning when 
requirements are clearly defined and agreed upon and the full scope of the project is planned
5 
Let’s Start with a Few PMI Definitions 
• PMBOK ® - the Project Management Book of Knowledge 
from which PMI defines terms, standards, and good practices 
• Portfolio – Projects, programs, and operations managed as 
a group to achieve strategic objectives 
• Program - A group of projects and program activities 
managed in a coordinated way 
• Project – a temporary endeavor undertaken to create a 
unique product, service, or result 
• Project Management – the application of knowledge, 
skills, tools, and techniques to project management activities 
to meet project requirements 
• Project Manager – the person authorized by the 
performing organization to direct the team accountable for 
realizing project objectives 
• Project Stakeholder – includes all project team members 
and anyone impacted by or impacting the project 
• Triple Constraint – the foundation of project management 
is balancing scope, time, and cost. Quality is at the center of 
the triple constraint 
Portfolio 
Programs 
Projects 
A few basic definitions: 
Time Cost 
Quality 
Scope
6 
Project Management Process Groups 
Initiating Planning Executing 
Monitoring 
& 
Controlling 
Closing 
A process group is a logical grouping of activities, inputs, tools, 
techniques, and outputs required for any type of project. 
Define a new project or 
new phase, identify 
stakeholders, and 
obtain authorization 
“Authorize the Work” 
Develop an integrated 
project management 
plan to attain project 
objectives 
“Plan the Work” 
Complete the work and 
satisfy project 
objectives 
“Work the Plan” 
Track and review 
project progress and 
performance; manage 
variance and change 
“Control the Plan” 
Finalize all activities 
and formally close the 
project or phase 
“End the Work” 
• Project Charter 
• Stakeholder Register 
• Project Mgt. Plans & 
Related Documents 
- Scope 
- Requirements 
- Schedule 
- Cost 
- Quality 
- Human Resources 
- Communication 
- Risk 
- Procurement 
- Change 
- Stakeholders 
• Project Deliverables 
• Work Performance 
Data 
• Team Performance 
Assessments 
• Project 
Communications (e.g. 
status reports) 
• Selected Suppliers & 
Agreements 
• Change Requests 
• Issue Log 
• Change Logs 
• Approved Change 
Requests 
• Work Performance 
Information 
• Schedule Forecasts 
• Cost Forecasts 
• Updates to Project 
Plan 
• Quality Control 
Measurements 
• Verified Deliverable 
• Accepted Deliverables 
• Final Product, 
Service, or Result 
(i.e. purpose of 
project) 
• Closed Procurement 
(e.g. formal signature 
of acceptance) 
Process 
Groups 
Activities 
Key 
Outputs
7 
Applying Project Management Process Groups 
The five process groups overlap and follow a basic cycle of “plan, do, 
check, act” until project closure. 
Process Group Overlap 
Time 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Initiating 
Planning Executing 
Monitoring & 
Controlling 
Change 
? 
Complete 
? 
Yes Yes 
Closing 
No 
No 
“Plan, Do, Check, Act”
8 
Knowledge Areas 
A project manager is responsible for applying and managing the following 
ten knowledge areas: 
Identify, define, combine, unify and coordinate activities within the Project Management Process 
Groups Integration 
Ensure the project includes all work required Scope to complete the project successfully 
Time Manage the timely completion of the project 
Manage the planning, estimating, budgeting, financing, funding, monitoring, and controlling of 
cost to enable the project to be completed within the approved budget Cost 
Determine quality policies , objectives, and responsibilities so that the project will satisfy the needs 
for which it was undertaken Quality 
Organize, manage, and lead the project team, including the identification of roles, responsibilities, 
required skills, and reporting relationships Human Resources 
Ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, 
management, control, monitoring and disposition of project information Communication 
Identify and assess risks, plan responses, and control risk to increase the likelihood and impact of 
positive events and decrease the likelihood and impact of negative events on the project Risk 
Purchase or acquire and control products, services, or results needed from outside the project 
team Procurement 
Identify people, groups, or organizations that could impact or be impacted by the project; analyze 
expectations, and develop strategies to engage stakeholders in decisions and activities Stakeholders
9 
Knowledge Areas & Process Groups 
Activity within each knowledge area is applied based on the appropriate 
process group. 
Process Groups 
Knowledge Areas 
(Below) 
Initiating Planning Executing 
Monitoring & 
Controlling 
Closing 
Integration Applicable Applicable Applicable Applicable Applicable 
Scope Applicable Applicable 
Time Applicable Applicable 
Cost Applicable Applicable 
Quality Applicable Applicable Applicable 
Human Resources Applicable Applicable 
Communication Applicable Applicable Applicable 
Risk Applicable Applicable 
Procurement Applicable Applicable Applicable Applicable 
Stakeholders Applicable Applicable Applicable Applicable 
Each shaded intersection has defined activities, inputs, 
tools & techniques, and outputs
10 
1. Integration Management - Process Activities 
Integration management connects all of the knowledge areas together 
from beginning (project initiation) to end (project closure). 
Change Requests 
Develop 
Project Charter 
Develop 
Project Mgt. Plan 
Project Mgt. Plan 
Direct & Manage 
Project Work 
Monitor & Control 
Project Work 
Updates 
Reports 
Change Requests 
Perform 
Integrated Change 
Control 
Updates 
Change Log 
Approved Change 
Requests 
Close 
Project or Phase 
Final Product 
Service, or Results 
Project SOW 
Business Case 
Agreements 
Approved 
Project Documents, 
Work Performance 
Change Requests 
Project Charter 
Deliverables, & 
Data 
Project Management 
Plan Updates 
Develop a document that formally 
authorizes the project 
Define, prepare, 
coordinate and 
integrate all 
subsidiary plans into 
a comprehensive 
plan 
Lead and perform the work to 
accomplish project objectives 
Track, review, and report progress 
to meet performance objectives 
Review all change requests, 
approve changes, and manage 
changes to deliverables and the 
project management plan 
Finalize all activities across all 
Process Groups to formally 
complete the project or phase 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
Project Charter 
A project charter formally authorizes the project and the project manager 
to apply resources to project activities. Per PMI, without a charter, there 
is no project. 
11 
• A typical charter will identify: 
o Business need or justification 
o Scope (high level) 
o Objectives (such as the intended product, service, or result) 
o Requirements (high level) 
o Risks (high level) 
o Assumptions and constraints 
o Stakeholders (primary) 
o Timing (anticipated) 
o Costs (anticipated) 
• The charter must be signed by someone who can invest authority for the project 
(typically senior management or a sponsor) 
Project Charter
The project management plan is the collection of all plans and related 
documents pertaining to planning, executing, monitoring, controlling, and 
closing the project. 
12 
Project Management Plan 
Procurement 
Project 
Communication 
Management 
Plan 
Change 
Scope 
Cost 
Process 
Improvement 
Stakeholders Risk 
Quality 
Schedule 
Configuration
2. Scope Management - Process Activities 
This area includes collecting requirements, defining scope, creating the 
work breakdown structure (WBS), and validating and controlling scope. 
Accepted Deliverables 
13 
Plan 
Scope Management 
Collect 
Requirements 
Define 
Scope 
Create 
WBS 
Validate 
Scope 
Control 
Scope 
Scope Baseline 
(Scope Baseline, WBS, 
WBS Dictionary) 
Updates 
Project Documents 
Workshops 
Interviews 
Benchmarking 
Context 
Diagrams 
Decomposition 
of Work 
Change Requests 
Inspection 
Project Scope 
Statement 
Reqs Documentation 
Reqs Traceability 
Matrix 
Scope Mgt;. Plan 
Reqs Mgt. Plan 
Change Requests 
Project Charter 
Project Scope is the work performed to deliver a product, service, 
or result that satisfies specified features and functions 
Determine, 
document, and 
manage 
stakeholder 
needs and 
requirements to 
meet objectives 
Create a plan that documents how 
the project scope will be defined, 
validated, and controlled 
Develop a 
detailed 
description of 
the project 
and product 
Subdivide project 
deliverables into 
smaller, more 
manageable 
components 
Gain formal 
acceptance of 
completed project 
deliverables 
Monitor 
status of the 
project scope 
and manage 
changes to 
the scope 
baseline 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply 
Scope
The WBS is the decomposition of the work to be performed. The output is 
called the Scope Baseline. 
14 
Work Breakdown Structure (WBS) 
Scope Baseline: 
• Scope Statement – description of project scope, major deliverables, assumptions, and 
constraints 
• WBS – hierarchical decomposition of the total scope of work 
• WBS Dictionary – provides details regarding the deliverables, activities, and scheduling 
information of each component of the WBS 
Project Title 
Deliverable 1 
Work 
Packages 
Deliverable 2 
Work 
Packages 
Control 
Account 
Planning 
Packages 
Work 
Packages 
Illustrative WBS 
Used when 
insufficient detail is 
available at the 
work package level 
Break down the 
work into the 
smallest level for 
which cost and time 
can be assessed and 
administered
15 
3. Time Management – Process Activities 
Time management includes all activity related to developing and 
managing the project schedule. 
Plan 
Schedule 
Management 
Define 
Activities 
Sequence 
Activities 
Estimate 
Activity Resources 
Estimate 
Activity Durations 
Develop 
Schedule 
Schedule Baseline 
Project Schedule 
Project Calendars 
Control 
Schedule 
Exp. Judgment 
Decomposition 
Rolling Wave 
Planning 
PDM 
Dependencies 
Leads/Lags 
Exp. Judgment 
Bottom Up 
PMIS 
Exp. Judgment 
Analogous 
Parametric 
3 Point 
Reserve Anal. 
Critical Path 
Compression 
Resource 
Optimization 
PMIS 
Project Schedule 
Network Diagrams 
Activity Resource 
Requirements 
RBS 
Activity Duration 
Estimates 
Schedule Mgt. Plan 
Activity List 
Milestone List 
Schedule Forecasts 
Project Charter 
Scope Baseline 
Establish the policies, 
procedures, and 
documentation for planning, 
developing, managing, 
executing, and controlling 
the project schedule 
Define and document specific 
actions to be performed to 
produce project deliverables 
Identify and document 
relationships among project 
activities 
Estimate the type and quantities of 
material, human resources, or suppliers 
required to perform each activity 
Estimate the number of work periods 
needed to complete individual activities 
with estimated resources 
Analyze activity sequences, durations, 
resource requirements, and schedule 
constraints to create the project schedule 
Monitor the 
status of project 
activities to 
update project 
progress and 
manage 
changes to the 
schedule 
baseline to 
achieve the plan 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
16 
Time (Schedule) Management Terms 
Below are a few of many terms project managers should know when 
developing and managing a project schedule. 
PMI Terms Descriptions 
3-Pt. Estimating Based on estimated Pessimistic (P), Optimistic (O), and Most Likely (M) durations 
Analogous Estimating High level, top down estimate based on similar projects (usually by a SME - subject matter expert) 
Bottom-Up Estimating Estimate at the lowest level of the WBS (level 3) and then roll up for the total project estimate 
Parametric Estimating Based on an existing, comparable parameter (e.g. $/ft. in the same neighborhood) 
Reserve Analysis Contingency (buffer based on known risk) & include in project budget or Managerial (buffer based on unknown risks) 
Rolling Wave Planning An iterative technique used when future details aren't known; near term is planned in detail; future is higher level 
Predecessor 
Relationships 
Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF) 
Default relationship; B cannot 
start until A is finished 
B cannot finish until A is 
finished 
B cannot start until A starts 
Rare, A starts before B 
finishes (e.g. when replacing 
an old system B with a new 
system A) 
A B 
A 
B 
A 
B 
A 
B 
Free Slack The latest an activity can start without delaying next activities 
Total Slack The latest an activity can start without delaying project finish date 
Float Often referred to as the same as Slack 
Lag Lag (a delay) = the successor must wait due to some delay after the predecessor is complete 
Lead Lead (an accelerant) = the successor can begin before the predecessor is complete 
Schedule Compression Crashing or fast tracking the schedule to adjust the schedule to align with the plan 
Fast Tracking Compression technique based on overlapping sequential activities (risky) 
Resource Leveling Adjusting peaks and valleys to create a level usage of resources 
Resource Smoothing Adjusting peaks and valleys to create a level usage of resources AND also accounts for individual resource limitations
4. Cost Management – Process Activities 
This area includes defining how project costs will be managed, estimating 
activity costs, determining the budget, and controlling costs. 
17 
Plan 
Cost Management 
Estimate 
Costs 
Determine 
Budget 
Cost Baseline 
Project Funding 
Requirements 
Control 
Costs 
Work Performance Info 
Cost Forecasts 
Change Requests 
Updates 
Analogous 
Parametric 
Bottom Up 
3 Point 
Reserve 
Exp. Judgment 
Aggregation 
Reserve 
Analysis 
Funding LImits 
Earned Value 
TCPI 
Forecasting 
PMIS 
Reserve Anal. 
Cost Mgt. Plan 
Activity Cost Estimates 
Basis of Estimates 
IRR 
NPV 
ROI 
Opportunity $ 
Payback 
Establish the 
policies, 
procedures, and 
documentation 
for planning, 
managing, 
expending, and 
controlling 
project costs 
Develop an approximation 
of the monetary resources 
needed to complete 
project activities 
Aggregate estimated costs of 
individual activities or work 
packages to establish an 
authorized cost baseline 
Monitor the status of the 
project to update project 
costs and manage changes to 
the cost baseline 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
18 
Earned Value Management (EVM) 
EVM is a means of measuring project cost and schedule vs. the plan. 
Earned Value (EV) = budgeted cost for work actually completed 
Time 
Dollars 
Cost Baseline (“S” Curve) 
Approved Time-Phased Budget 
BAC 
Budget at Completion (BAC) = total 
project budget 
Estimate to Complete (ETC) = cost to complete 
the project based on current spending efficiency 
ETC 
EAC 
Estimate at Completion (EAC) = 
current projected final cost based on 
current spending efficiency 
Variance at Completion (VAC) 
Cost Variance 
(CV) 
Cost Performance (CPI) = EV/AC 
Schedule Variance 
(SV) 
Schedule Performance (SPI) = EV/PV 
Planned Value (PV) = budgeted cost for work scheduled 
Actual Cost (AC) 
at point in time 
AC 
PV 
EV 
Point in Time
19 
5. Quality Management – Process Activities 
Quality management includes identifying quality requirements and 
standards, auditing requirements and control measurements, assessing 
quality performance, and recommending changes, when needed. 
Plan 
Quality 
Management 
Perform 
Quality Assurance 
Control 
Quality 
Cost/Benefit 
Cost of Quality 
7 Basic Tools 
Benchmarking 
Sampling 
Quality Mgt. Plan 
Process Improvement 
Plan 
Quality Metrics 
Quality Checklists 
Quality Audits 
Controls 
Charts 
Process 
Analysis 
Updates 
Verified Deliverables 
QC Measures 
Validated Changes 
Measurements 
Identify quality requirements 
and/or standards for the 
project and its deliverables, 
and document how the project 
will demonstrate compliance 
Audit the quality requirements 
and the results from quality 
control measurements to ensure 
appropriate standards and 
operational definitions are used 
Monitor and record results of 
quality activities to assess 
performance and recommend 
necessary changes 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing
20 
Quality Management Philosophies and Principles 
PMI quality management principles are based on a few popular 
philosophies. 
Quality Philosophies: 
• Total Quality Management (Deming) – 
proactive approach with statistical analysis 
• Zero Defects (Crosby) – Do it right the first time 
• Fitness for Use (Juran) – Satisfy customer 
needs 
• Continuous Improvement (Kaizen) – proactive 
approach to process improvement 
• Gold Plating – unacceptable practice of 
providing more than requested 
• Cost of Quality – cost of conforming is less than 
cost of non-conforming 
• Design of Experiments – isolate factors that 
influence results 
• 6 Sigma – strive for 99.9997% error free 
• ISO 9000 – document what you do; do what you 
document 
Quality Principles: 
• Define and satisfy customer needs 
• Prevent rather than inspect 
• Be proactive rather reactive 
• Validate project processes 
• Measure against approved 
standards 
• Continually improve 
• Take accountability
21 
Quality Management Tools and Terms 
Project managers should be familiar with common quality management 
tools and terms. 
Tools Description 
1. Cause and Effect Diagrams Fishbone (Ishikawa) diagram 
2. Flowcharts Basic flow chart or GERT diagram with feedback loop 
3. Checksheets Check list (e.g. pre-flight list to ensure you are "cockpit ready" before taking flight) 
4. Pareto Diagrams Cumulative histogram (e.g. 80/20 rule) 
5. Histograms Depiction of volume or frequency of occurrences of several events 
6. Control Charts Depiction of process output over time with UCL & LCL at 3 sigma from mean 
7. Scatter Diagrams Depicts pattern of results across two variables 
Terms Description 
Benchmarking Comparing actual or planned processes to comparable projects to identify best practices 
Design of Experiments Variable based analysis (freeze all variables but one and assess outcome) 
Statistical Sampling Using a % of the population and extrapolating the results within an acceptable confidence level 
Quality Audits Identify best practices; identify gaps; share best practices; offer assistance to improve; highlight lessons learned 
Process Analysis Assess process, identify root causes, alleviate root causes 
Inspection Examination of work product and comparison to documented standards (e.g. reviews, audits) 
85/15 Rule 85% of quality relates to mgt.; 15% is worker related 
80/20 Rule 80% of problems come from 20% of the issues 
Rule of 7 Must have 7 consecutive data points above or below mean to consider process "out of control" 
Mean Time Before Failure MTBF, example quality metric 
Mean Time to Repair MTTR, example quality metric 
Grade vs. Quality Not the same; you can have a lower grade product with high quality and vice versa (e.g. automobile models) 
Upper Control Limit UCL = 3 sigma above mean (average) 
Lower Control Limit LCL = 3 sigma below mean (average) 
Upper Specification Limit USL is customer established and can be above or below UCL 
Lower Specification Limit USL is customer established and can be above or below LCL
6. Human Resource Management - Process Activities 
Human resource management consists of planning, acquiring, developing, 
and managing the project team. 
22 
Plan 
HR Management 
Acquire 
Project Team 
Develop 
Project Team 
Manage 
Project Team 
Change Requests 
Updates 
Org Charts 
Job Descriptions 
Org. Theory 
Pre- 
Assignment 
Acquisition 
Negotiation 
Training 
Team Building 
Ground Rules 
Recognition 
Rewards 
HR Mgt. Plan 
Project Staff 
Assignments 
Resource Calendars 
Team Performance 
Assessments 
Observations 
Conversations 
Conflict Mgt. 
Performance 
Appraisals 
Define roles, 
responsibilities, 
required skills, 
and reporting 
relationships 
Confirm availability 
and obtain the 
necessary team 
Improve competencies, 
team interaction, the 
team environment, and 
enhance project team 
performance 
Track team member 
performance, provide 
feedback, resolve issues, 
and manage changes to 
the team to optimize team 
performance 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
23 
Roles and Responsibilities 
Responsibility assignment matrix (RAM) charts such as a “RACI” let each 
team member know who is responsible for each activity and deliverable. 
RACI Person 
Activity Ann Ben Carlos Denny 
Develop Schedule A R I I 
Collect Requirements I A R C 
Develop Test Plan I A R C 
Develop Training Plan A C I R 
• (R) Responsible - those who do the work 
• (A) Accountable - The one who: 
o Is ultimately answerable for the completion of the deliverable 
o Delegates the work to those responsible 
o Approves the work that the responsible person provides 
• (C) Consulted – those whose opinions are sought (typically subject matter experts); typically this is a two 
way communication 
• (I) Informed – those who are kept up-to-date on progress; typically this is a one way communication
24 
Project Life Cycle - Team Building & Leadership Styles 
Project managers should be aware of typical team building dynamics and 
situational leadership styles across a project life cycle. 
Team Building: Forming Storming Norming Performing Adjourning 
Leadership Style: Directing Coaching Facilitating Supporting 
Initiating Closing 
Project Life Cycle 
Team Building Stages 
• Forming – creating the team 
• Storming – team chaos as people start 
working with one another 
• Norming – team behavior starts to 
normalize 
• Performing – team performs as a unit 
• Adjourning – team completes work 
and disbands 
Time 
Situational Leadership Styles 
• Directing – provide specific, clear 
instructions and closely supervise 
• Coaching – solicit input, offer rationale 
and examples 
• Facilitating –maintain team progress; 
delegate day-to-day control 
• Supporting – support and motivate 
the team to complete objectives
Conflict is inevitable. A project manager should be aware of typical 
sources of project conflict and recommended techniques to resolve them. 
25 
Conflict Management 
Sources of Conflict Conflict Resolution Techniques 
• Scheduling Priorities 
• Scarce Resources 
• Personal Work Styles 
• Methodology/Details 
• Cost/Budget 
• Personalities 
Recommended: 
1. Collaborate/Problem Solve 
2. Compromise/Reconcile 
3. Force/Direct 
Not Recommended: 
1. Smooth/Accommodate 
2. Withdraw/Avoid 
Higher 
Probability 
of Conflict 
Lower
26 
7. Communication Management - Process Activities 
Roughly 90% of a project manager’s job is communication. 
Plan 
Communication 
Management 
Communciation 
Mgt. Plan 
Manage 
Communications 
Project Communications 
Control 
Communications 
Req. Analysis 
Technology 
Models 
Methods 
Meetings 
Models 
Method 
Systems 
Reporting 
Exp. Judgment 
Systems 
Meetings 
Work Performance 
Information 
Change Requests 
Develop a 
communication 
approach based 
on stakeholder’s 
informational 
needs 
Create, collect, 
distribute, store, 
and retrieve 
information 
Monitor and control 
communication 
throughout the entire 
project life cycle 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
27 
Communication Management 
Project managers should be aware of the basics of effective 
communication across the broad stakeholder community. 
Transmit 
Communication Paths 
N N 
N 
N 
• # of Communication Paths 
equals [N x (N-1)]/2 
• N equals # of Stakeholders 
• Example: [4 x (4-1)]/2 = 6 
Communication Methods 
• Interactive – between two people 
• Push – send to specific recipients 
• Pull – recipient actively seeks information 
Communication Types 
• Active listening – receiver verifies correct 
interpretation 
• Effective listening – receiver observes visual 
and vocal cues 
• Feedback – sender receives feedback from 
receiver 
• Nonverbal - ~55% of communication (e.g. 
body and facial language) 
• Para-lingual – Voice characteristics 
Communication Model 
Sender/Encode Decode/Receiver 
Acknowledgement 
Response 
Noise 
Noise
28 
8. Risk Management – Process Activities 
Risks are possible events that could impact the project in a positive (an 
opportunity) or negative (a threat) way. 
Plan 
Risk Management 
Identify 
Risks 
Risk Register 
(Risks & Triggers) 
Perform 
Qualitative Analysis 
Perform 
Quantitative 
Analysis 
Plan 
Risk Response 
Control 
Risks 
Updates 
Updates 
Project Documents 
Risk Mgt. Plan 
Updates 
Updates 
Define how to 
conduct risk 
management 
activities 
Determine and document the 
characteristics of risk which 
may affect the project 
Prioritize risks for further analysis or 
action by assessing their probability of 
occurrence and impact 
Analyze the effect of 
identified risks on overall 
project objectives 
Develop options 
and actions to 
enhance 
opportunities and 
reduce threats to 
project objectives 
Implement risk response plans, track identified 
risks, monitor residual risks, identify new risks, 
and evaluate risk process effectiveness 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and 
techniques not depicted may apply
29 
Risk Probability and Impact Matrix 
A probability and impact matrix can be used to evaluate the impact of a 
risk and the probability of its occurrence. 
High 
Moderate 
Low Moderate 
High 
Probability of 
Occurrence 
Level of Impact 
Positive Risk Responses 
• Share – split the responsibility 
and benefit to maximize the 
opportunity 
• Exploit – take steps to ensure 
success 
• Enhance – improve the size of 
the risk event and impact 
• Accept – do nothing 
Negative Risk Responses 
• Avoid – get rid of the potential 
problem 
• Transfer – re-assign to another 
party 
• Mitigate – minimize the bad 
characteristics of the risk 
• Accept – do nothing 
Probability and Impact Matrix 
The higher the combined probability and impact of the risk 
event the greater the need to develop a risk response plan
30 
Risk Management 
Project managers should be aware of risk management terms. 
Risk Management Terms 
• Monte Carlo – simulation of possible outcomes 
• Risk Breakdown Structure – breakdown by category (e.g. internal, external, technology, 
organizational, etc.) 
• Risk Trigger – an indicator that an event “could” occur 
• SWOT Analysis – strengths, weaknesses, opportunities, and threats 
• Expected Monetary Value (EMV) – summation of probability x impact of alternative decisions (…not 
to be confused with EVM – earned value management) 
• Contingency Reserves – for known risks (include in budget and schedule) 
• Management Reserves – for unknown risks (excluded from baselines for budget and schedule) 
• Residual Risk – risk remaining after risk response 
• Secondary Risk – potential risk as a result of risk response 
• Workaround – “wing it” response when other risk response plans don’t work 
• Types of Risk Tolerance 
o Averse – Avoids risk 
o Seeker – Seeks risk 
o Neutral – Middle ground
31 
9. Procurement Management – Process Activities 
Procurement management includes planning, selecting, contracting, 
controlling, and closing outsourced products and services. 
Procurement 
Mgt. Plan 
Plan 
Procurement Mgt. 
Conduct 
Procurements 
Control 
Procurements 
Work Performance Info 
Updates 
Change Requests 
Close 
Procurements 
Procurement Mgt. Plan 
SOW 
RFPs 
Selection Criteria 
Make Buy Decision 
Selected Suppliers 
Agreements 
Resource Calendars 
Exp. Judgment 
Make Buy 
Analysis 
Exp. Judgment 
Bidder Conf. 
Ind. Estimates 
Advertising 
Seller Proposals 
Inspect/Audits 
Reporting 
A/P Systems 
Claims Admin. 
Records Mgt. 
Audits 
Negotiations 
Record Mgt. 
Closed Procurements 
OPA Udpates 
Document 
project 
procurement 
decisions, 
specify the 
approach, and 
identify 
potential sellers 
Obtain seller response, 
select a seller, and 
award a contract 
Manage procurement 
relationship, monitor contract 
performance, and make changes 
and corrections as appropriate 
Complete each project 
procurement, including 
finalizing open claims, 
updating records to 
reflect final results, and 
archiving information 
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
Note, additional inputs, outputs, tools and techniques not depicted may apply
32 
Contract Types 
Project managers should be aware of the benefits and risks of different 
contract types from a buyer’s perspective and a seller’s perspective. 
Buyer’s Risk 
Low High 
FFP FPIF FP EPA T&M PO CPFF CPIF CPAF CPPC 
Seller’s Risk 
High Low 
• (FFP) Firm Fixed Price – allows buyer to budget fixed price; requires seller to detail scope and accurately 
estimate price; very common 
• (FFIF) Fixed Price Incentive Fee – includes incentive to motivate seller to produce at greater speed 
• (FF EPA) Fixed Price Economic Price Adjustment – compensates for year to year economic changes 
• (T&M) Time and Materials – typically used for smaller initiatives 
• (PO) Purchase Order – typically used for commodity items 
• (CPFF) Cost Plus Fixed Fee – typically variable costs are cost-plus and predictable costs are fixed fee 
• (CPIF) Cost Plus Incentive Fee – actual costs plus incentive to motivate seller to produce at greater speed 
• (CPAF) Cost Plus Award Fee – actual costs plus award based on customer satisfaction with agreed criteria 
• (CPPC) Cost Plus Percent of Cost – actual cost plus % of actual; the higher the cost, the higher the fees
33 
Procurement Terms 
Project managers should be familiar with additional procurement terms 
in the table below: 
Terms Description 
Make or Buy Analysis Is it more practical to insource or outsource (based on a cost comparison between the two)? 
Bidder Conference Prior to bid submission, offers opportunities for prospective sellers to obtain requirements clarification from buyer 
Independent Estimates Used to validate proposal information 
Contract (CCOLA) Must have 5 Components: Capacity, Consideration, Offer, Legal Purpose, Acceptance 
Point of Total Assumption 
Point at which seller is responsible for all cost overruns; PTA = (Ceiling Price - Target Price)/Buyer Share + Target 
Cost 
Ceiling Price % of Target Cost (e.g. Ceiling = 140% of target cost) 
Target Cost Expected cost of work in the contract 
Target Price Equals Target Cost + Target Profit 
Share Ratio Ratio of split between buyer and seller of cost savings or overruns (e.g. 70/30) 
RFP Request for Proposal, typically used for higher priced, customized services or products 
RFQ Request for Quote, typically used for small dollar commodity type products 
IFB Invitation to Bid, used for government sealed bids (similar to RFP) 
Design Scope of Work (SOW) Buyer provides exact details; generally results in fixed price contract 
Functional Scope of Work (SOW) Buyer provides functionality needed; generally results in cost plus contract 
Sole Source Go direct to a supplier without any available competition (e.g. supplier holds the patent) 
Single Source Go direct to a supplier although competitors are available (e.g. "preferred supplier") 
Negotiation PMI prefers "win/win" negotiation approach 
Standard Terms & Conditions Typical common (non-negotiable) contract items with a tight range or parameters 
Special Provisions Typically added to account for changes to standard terms and conditions 
Claims Administration Means of administering contested changes or disagreements regarding compensation 
ADR Alternative dispute resolution (e.g. arbitration) used when claims cannot be negotiated between buyer and seller
Key: 
Initiating 
Planning 
Executing 
Monitoring & Controlling 
Closing 
34 
10. Stakeholder Management – Process Activities 
It is critical to project success to identify stakeholders, address their 
requirements, meet their expectations, and foster their engagement. 
Identify 
Stakeholders 
Plan 
Stakeholder 
Management 
Manage 
Stakeholder 
Engagement 
Stakeholder Register 
Stakeholder Mgt. Plan 
Issue Log 
Change Requests 
Updates 
Control 
Stakeholder 
Engagement 
Work Performance Info 
Change Requests 
Updates 
Exp. Judgment 
Stakeholder 
Analysis 
(Power/ 
Interest) 
Interpersonal 
Skills 
Management 
Skills 
Stakeholder 
Engagement Matrix 
(Unaware, Neutral, 
Resistance, Leading) 
Identify the people, 
groups, or 
organizations that 
could impact or be 
impacted by the 
decision, activity, or 
outcome of the 
project. 
Develop appropriate management 
strategies to effectively engage 
stakeholders throughout the project 
life cycle based on their needs and 
potential impact on project success 
Communicate and work with stakeholders to meet 
their needs and expectations, address issues as 
they occur, and foster appropriate stakeholder 
engagement throughout the project life cycle 
Monitor overall 
project stakeholder 
relationships and 
adjust strategies and 
plans for engaging 
stakeholders 
Note, additional inputs, outputs, tools and techniques not depicted may apply
35 
Stakeholder Power vs. Interest Grid 
All stakeholders are different and, therefore, need to be managed 
differently based on their relative authority (power) and level of concern 
(interest). 
Stakeholder 
Power vs. Interest Grid 
Keep Satisfied Manage Closely 
Monitor Keep Informed 
High 
Moderate 
Low Moderate 
High 
Power 
Interest
36 
PMI Code of Ethics and Professional Conduct 
All PMI members must agree to adhere to a high personal standard of 
ethical and professional behavior. 
Tenets of Code: 
1. Honor 
o Do what is right and honorable 
o Set high standards for yourself and aspire to meet those standards is all aspects of life 
2. Responsibility – Take ownership of: 
o The decisions you make or fail to make 
o The actions you take or fail to take 
o The consequences that result 
3. Respect 
o Show high regard for yourself, others, and the resources (e.g. people, money, reputation, 
safety) entrusted to you 
o Engender trust confidence, performance excellence, and mutual cooperation in an environment 
of diverse perspectives and views 
4. Fairness 
o Make decisions and act impartially and objectively 
o Conduct yourself in a way free from competing self interest, prejudice, and favoritism 
5. Honesty 
o Understand the truth 
o Act in a truthful manner both in your communication and in your conduct
37 
Summary 
This material covered the following project management topics: 
• What is PMI and the PMP? 
• Why PMI Project Management Principles are 
Useful to Know 
• A Few Basic PMI Definitions 
• Five Process Groups 
o Initiating 
o Planning 
o Executing 
o Monitoring and Controlling 
o Closing 
• Ten Knowledge Areas 
o Integration 
o Scope 
o Time 
o Cost 
o Quality 
o Human Resources 
o Communication 
o Risk 
o Procurement 
o Stakeholders 
• Project Management Terms, such as: 
o Triple Constraint 
o Project Charter 
o Project Management Plan 
o Work Breakdown Structure (WBS) 
o Predecessor Relationships 
o Earned Value Management 
o Gold Plating 
o Responsibilities Assignment Matrix 
o Forming, Storming, Norming, Performing, 
Adjourning 
o Communication Noise 
o Risk Probability and Impact Matrix 
o Contract Type 
o Stakeholder Power vs. Interest Grid 
• Code of Ethics and Professional Conduct 
o Honor 
o Responsibility 
o Respect 
o Fairness 
o Honesty 
Thank you for taking the time to review this material!

Mais conteúdo relacionado

Mais procurados

Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardJavid Hamdard
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process GroupsBhuWan Khadka
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsNishant Munjal
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Managementguest90bddb
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areasguestfe6ad
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaJoshua Render
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementMohamed Loey
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge AreasElizabeth Harrin FAPM
 

Mais procurados (20)

Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
project management
project managementproject management
project management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
The Project Management Plan in 20 steps
The Project Management Plan in 20 stepsThe Project Management Plan in 20 steps
The Project Management Plan in 20 steps
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
06. Project Management Process Groups
06. Project Management Process Groups06. Project Management Process Groups
06. Project Management Process Groups
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Introduce Project Management
Introduce Project ManagementIntroduce Project Management
Introduce Project Management
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 
Project Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge AreasProject Management Process Groups And Knowledge Areas
Project Management Process Groups And Knowledge Areas
 
Project management
Project managementProject management
Project management
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
PMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration ManagementPMP Lecture 4: Project Integration Management
PMP Lecture 4: Project Integration Management
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
10 Project Management Knowledge Areas
10 Project Management Knowledge Areas10 Project Management Knowledge Areas
10 Project Management Knowledge Areas
 

Destaque

Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishRicardo Viana Vargas
 
Henry fayols priciple of management- image ppt
Henry fayols priciple of management- image pptHenry fayols priciple of management- image ppt
Henry fayols priciple of management- image pptNajeeb Ahmed
 
Project on Principles of management-Business studies project work
Project on Principles of management-Business studies project workProject on Principles of management-Business studies project work
Project on Principles of management-Business studies project workRavi Singh
 
Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012EBY3081
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management Ahmad Maharma, PMP,RMP
 
Lean Scope Project Management
Lean Scope Project ManagementLean Scope Project Management
Lean Scope Project ManagementBill Brantley
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Project Management Scope Templates for SharePoint
Project Management Scope Templates for SharePointProject Management Scope Templates for SharePoint
Project Management Scope Templates for SharePointToby Elwin
 
Vision Mission Goals and Objectives for the School Library Media Center
Vision Mission Goals and Objectives for the School Library Media CenterVision Mission Goals and Objectives for the School Library Media Center
Vision Mission Goals and Objectives for the School Library Media CenterJohan Koren
 
Managing Virtual Project Teams
Managing Virtual Project TeamsManaging Virtual Project Teams
Managing Virtual Project TeamsShawn Grubb
 
Objectives of Project evaluation
Objectives of Project evaluationObjectives of Project evaluation
Objectives of Project evaluationRobina Nasir
 

Destaque (20)

Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
project management essentials
project management essentialsproject management essentials
project management essentials
 
Scrum Concepts
Scrum ConceptsScrum Concepts
Scrum Concepts
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
 
Henry fayols priciple of management- image ppt
Henry fayols priciple of management- image pptHenry fayols priciple of management- image ppt
Henry fayols priciple of management- image ppt
 
Project on Principles of management-Business studies project work
Project on Principles of management-Business studies project workProject on Principles of management-Business studies project work
Project on Principles of management-Business studies project work
 
Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012Seo goals & objectives 2 quarter 2012
Seo goals & objectives 2 quarter 2012
 
Project ATOM Goals And Objectives
Project ATOM Goals And ObjectivesProject ATOM Goals And Objectives
Project ATOM Goals And Objectives
 
Pmbok 4th edition chapter 5 - Project Scope Management
Pmbok 4th edition   chapter 5 - Project Scope Management Pmbok 4th edition   chapter 5 - Project Scope Management
Pmbok 4th edition chapter 5 - Project Scope Management
 
Lean Scope Project Management
Lean Scope Project ManagementLean Scope Project Management
Lean Scope Project Management
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Project Management Scope Templates for SharePoint
Project Management Scope Templates for SharePointProject Management Scope Templates for SharePoint
Project Management Scope Templates for SharePoint
 
Vision Mission Goals and Objectives for the School Library Media Center
Vision Mission Goals and Objectives for the School Library Media CenterVision Mission Goals and Objectives for the School Library Media Center
Vision Mission Goals and Objectives for the School Library Media Center
 
Managing Virtual Project Teams
Managing Virtual Project TeamsManaging Virtual Project Teams
Managing Virtual Project Teams
 
02 project scope management
02 project scope management02 project scope management
02 project scope management
 
Objectives of Project evaluation
Objectives of Project evaluationObjectives of Project evaluation
Objectives of Project evaluation
 
Defining clear project goals
Defining clear project goalsDefining clear project goals
Defining clear project goals
 

Semelhante a PMI Project Management Principles

pmi project management principles.pptx
pmi project management principles.pptxpmi project management principles.pptx
pmi project management principles.pptxssusere01f83
 
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalAMIT PAYAL
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...Chandrasen Sharma
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management Yesica Adicondro
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptxagathamarlinee
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Managementchaitanyakrsk
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI ApproachZaur Ahmadov, PMP
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 

Semelhante a PMI Project Management Principles (20)

pmi project management principles.pptx
pmi project management principles.pptxpmi project management principles.pptx
pmi project management principles.pptx
 
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit Payal
 
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
pmiprojectmanagementprinciples20141006-141006181426-conversion-gate01-convert...
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad Thalji
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
Basics in Project Management
Basics in Project ManagementBasics in Project Management
Basics in Project Management
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
Ibm projectmgmt-1
Ibm  projectmgmt-1Ibm  projectmgmt-1
Ibm projectmgmt-1
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
6396901
63969016396901
6396901
 
Making of Stakeholders Delight
Making of Stakeholders DelightMaking of Stakeholders Delight
Making of Stakeholders Delight
 

Último

Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...dsnow9802
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Designshakkardaddy
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Managementshakkardaddy
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Nagarjuna Reddy Aturi
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsCIToolkit
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONsivani14565220
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsCIToolkit
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfcoolsnoopy1
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisCIToolkit
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Conny Dethloff
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesMassimo Canducci
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsHannah Smith
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBusiness of Software Conference
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationPMIUKChapter
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teamsshakkardaddy
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 

Último (20)

Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Management
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data Insights
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdf
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram Analysis
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human Resources
 
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic TraitsDigital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
Digital PR Summit - Leadership Lessons: Myths, Mistakes, & Toxic Traits
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentation
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teams
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data Sets
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 

PMI Project Management Principles

  • 1. PMI Project Management Principles A Point of Reference (based on the 5th Edition PMBOK® Guide) By Tom Tiede
  • 2. 2 Agenda This material will cover the following project management topics: • What is PMI and the PMP? • Why PMI Project Management Principles are Useful to Know • A Few Basic PMI Definitions • Five Process Groups o Initiating o Planning o Executing o Monitoring and Controlling o Closing • Ten Knowledge Areas o Integration o Scope o Time o Cost o Quality o Human Resources o Communication o Risk o Procurement o Stakeholders • Project Management Terms, such as: o Triple Constraint o Project Charter o Project Management Plan o Work Breakdown Structure (WBS) o Predecessor Relationships o Earned Value Management o Gold Plating o Responsibilities Assignment Matrix o Forming, Storming, Norming, Performing, Adjourning o Communication Noise o Risk Probability and Impact Matrix o Contract Type o Stakeholder Power vs. Interest Grid • Code of Ethics and Professional Conduct o Honor o Responsibility o Respect o Fairness o Honesty
  • 3. 3 What is PMI and the PMP? The Project Management Institute (PMI) is the world’s largest membership association for the advocacy of Project and Program management. • Over 400,000 current members across 180 countries • Over 600,000 PMI certification holders • Their most widely recognized certification is the PMP (Project Management Professional). The PMP credential recognizes your: o Experience, o Education, and o Competency to lead and manage projects • Earning the PMP credential requires: o A bachelor’s degree and 4,500 hours of documented project management experience, or a secondary degree and 7,500 hours of documented project management experience o 35 hours of certified project management training o Passing the certification exam • Regardless of your inclination to pursue PMP certification, PMI project management principles apply to your role as a project leader or stakeholder The purpose of this material is to share a few PMI project management principles that apply to your role as a project leader or stakeholder
  • 4. 4 Why Is This Useful to Know? Leveraging prescribed PMI project management principles reduces the risk and impact of costly project omissions, changes, and errors. Project Initiation Cost of Resolving Project Omissions, Changes, or Errors Project Planning Project Execution Project Closure (Illustrative) The PMI approach places great emphasis on project initiation and planning when requirements are clearly defined and agreed upon and the full scope of the project is planned
  • 5. 5 Let’s Start with a Few PMI Definitions • PMBOK ® - the Project Management Book of Knowledge from which PMI defines terms, standards, and good practices • Portfolio – Projects, programs, and operations managed as a group to achieve strategic objectives • Program - A group of projects and program activities managed in a coordinated way • Project – a temporary endeavor undertaken to create a unique product, service, or result • Project Management – the application of knowledge, skills, tools, and techniques to project management activities to meet project requirements • Project Manager – the person authorized by the performing organization to direct the team accountable for realizing project objectives • Project Stakeholder – includes all project team members and anyone impacted by or impacting the project • Triple Constraint – the foundation of project management is balancing scope, time, and cost. Quality is at the center of the triple constraint Portfolio Programs Projects A few basic definitions: Time Cost Quality Scope
  • 6. 6 Project Management Process Groups Initiating Planning Executing Monitoring & Controlling Closing A process group is a logical grouping of activities, inputs, tools, techniques, and outputs required for any type of project. Define a new project or new phase, identify stakeholders, and obtain authorization “Authorize the Work” Develop an integrated project management plan to attain project objectives “Plan the Work” Complete the work and satisfy project objectives “Work the Plan” Track and review project progress and performance; manage variance and change “Control the Plan” Finalize all activities and formally close the project or phase “End the Work” • Project Charter • Stakeholder Register • Project Mgt. Plans & Related Documents - Scope - Requirements - Schedule - Cost - Quality - Human Resources - Communication - Risk - Procurement - Change - Stakeholders • Project Deliverables • Work Performance Data • Team Performance Assessments • Project Communications (e.g. status reports) • Selected Suppliers & Agreements • Change Requests • Issue Log • Change Logs • Approved Change Requests • Work Performance Information • Schedule Forecasts • Cost Forecasts • Updates to Project Plan • Quality Control Measurements • Verified Deliverable • Accepted Deliverables • Final Product, Service, or Result (i.e. purpose of project) • Closed Procurement (e.g. formal signature of acceptance) Process Groups Activities Key Outputs
  • 7. 7 Applying Project Management Process Groups The five process groups overlap and follow a basic cycle of “plan, do, check, act” until project closure. Process Group Overlap Time Initiating Planning Executing Monitoring & Controlling Closing Initiating Planning Executing Monitoring & Controlling Change ? Complete ? Yes Yes Closing No No “Plan, Do, Check, Act”
  • 8. 8 Knowledge Areas A project manager is responsible for applying and managing the following ten knowledge areas: Identify, define, combine, unify and coordinate activities within the Project Management Process Groups Integration Ensure the project includes all work required Scope to complete the project successfully Time Manage the timely completion of the project Manage the planning, estimating, budgeting, financing, funding, monitoring, and controlling of cost to enable the project to be completed within the approved budget Cost Determine quality policies , objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken Quality Organize, manage, and lead the project team, including the identification of roles, responsibilities, required skills, and reporting relationships Human Resources Ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring and disposition of project information Communication Identify and assess risks, plan responses, and control risk to increase the likelihood and impact of positive events and decrease the likelihood and impact of negative events on the project Risk Purchase or acquire and control products, services, or results needed from outside the project team Procurement Identify people, groups, or organizations that could impact or be impacted by the project; analyze expectations, and develop strategies to engage stakeholders in decisions and activities Stakeholders
  • 9. 9 Knowledge Areas & Process Groups Activity within each knowledge area is applied based on the appropriate process group. Process Groups Knowledge Areas (Below) Initiating Planning Executing Monitoring & Controlling Closing Integration Applicable Applicable Applicable Applicable Applicable Scope Applicable Applicable Time Applicable Applicable Cost Applicable Applicable Quality Applicable Applicable Applicable Human Resources Applicable Applicable Communication Applicable Applicable Applicable Risk Applicable Applicable Procurement Applicable Applicable Applicable Applicable Stakeholders Applicable Applicable Applicable Applicable Each shaded intersection has defined activities, inputs, tools & techniques, and outputs
  • 10. 10 1. Integration Management - Process Activities Integration management connects all of the knowledge areas together from beginning (project initiation) to end (project closure). Change Requests Develop Project Charter Develop Project Mgt. Plan Project Mgt. Plan Direct & Manage Project Work Monitor & Control Project Work Updates Reports Change Requests Perform Integrated Change Control Updates Change Log Approved Change Requests Close Project or Phase Final Product Service, or Results Project SOW Business Case Agreements Approved Project Documents, Work Performance Change Requests Project Charter Deliverables, & Data Project Management Plan Updates Develop a document that formally authorizes the project Define, prepare, coordinate and integrate all subsidiary plans into a comprehensive plan Lead and perform the work to accomplish project objectives Track, review, and report progress to meet performance objectives Review all change requests, approve changes, and manage changes to deliverables and the project management plan Finalize all activities across all Process Groups to formally complete the project or phase Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 11. Project Charter A project charter formally authorizes the project and the project manager to apply resources to project activities. Per PMI, without a charter, there is no project. 11 • A typical charter will identify: o Business need or justification o Scope (high level) o Objectives (such as the intended product, service, or result) o Requirements (high level) o Risks (high level) o Assumptions and constraints o Stakeholders (primary) o Timing (anticipated) o Costs (anticipated) • The charter must be signed by someone who can invest authority for the project (typically senior management or a sponsor) Project Charter
  • 12. The project management plan is the collection of all plans and related documents pertaining to planning, executing, monitoring, controlling, and closing the project. 12 Project Management Plan Procurement Project Communication Management Plan Change Scope Cost Process Improvement Stakeholders Risk Quality Schedule Configuration
  • 13. 2. Scope Management - Process Activities This area includes collecting requirements, defining scope, creating the work breakdown structure (WBS), and validating and controlling scope. Accepted Deliverables 13 Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope Scope Baseline (Scope Baseline, WBS, WBS Dictionary) Updates Project Documents Workshops Interviews Benchmarking Context Diagrams Decomposition of Work Change Requests Inspection Project Scope Statement Reqs Documentation Reqs Traceability Matrix Scope Mgt;. Plan Reqs Mgt. Plan Change Requests Project Charter Project Scope is the work performed to deliver a product, service, or result that satisfies specified features and functions Determine, document, and manage stakeholder needs and requirements to meet objectives Create a plan that documents how the project scope will be defined, validated, and controlled Develop a detailed description of the project and product Subdivide project deliverables into smaller, more manageable components Gain formal acceptance of completed project deliverables Monitor status of the project scope and manage changes to the scope baseline Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply Scope
  • 14. The WBS is the decomposition of the work to be performed. The output is called the Scope Baseline. 14 Work Breakdown Structure (WBS) Scope Baseline: • Scope Statement – description of project scope, major deliverables, assumptions, and constraints • WBS – hierarchical decomposition of the total scope of work • WBS Dictionary – provides details regarding the deliverables, activities, and scheduling information of each component of the WBS Project Title Deliverable 1 Work Packages Deliverable 2 Work Packages Control Account Planning Packages Work Packages Illustrative WBS Used when insufficient detail is available at the work package level Break down the work into the smallest level for which cost and time can be assessed and administered
  • 15. 15 3. Time Management – Process Activities Time management includes all activity related to developing and managing the project schedule. Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Schedule Baseline Project Schedule Project Calendars Control Schedule Exp. Judgment Decomposition Rolling Wave Planning PDM Dependencies Leads/Lags Exp. Judgment Bottom Up PMIS Exp. Judgment Analogous Parametric 3 Point Reserve Anal. Critical Path Compression Resource Optimization PMIS Project Schedule Network Diagrams Activity Resource Requirements RBS Activity Duration Estimates Schedule Mgt. Plan Activity List Milestone List Schedule Forecasts Project Charter Scope Baseline Establish the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule Define and document specific actions to be performed to produce project deliverables Identify and document relationships among project activities Estimate the type and quantities of material, human resources, or suppliers required to perform each activity Estimate the number of work periods needed to complete individual activities with estimated resources Analyze activity sequences, durations, resource requirements, and schedule constraints to create the project schedule Monitor the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 16. 16 Time (Schedule) Management Terms Below are a few of many terms project managers should know when developing and managing a project schedule. PMI Terms Descriptions 3-Pt. Estimating Based on estimated Pessimistic (P), Optimistic (O), and Most Likely (M) durations Analogous Estimating High level, top down estimate based on similar projects (usually by a SME - subject matter expert) Bottom-Up Estimating Estimate at the lowest level of the WBS (level 3) and then roll up for the total project estimate Parametric Estimating Based on an existing, comparable parameter (e.g. $/ft. in the same neighborhood) Reserve Analysis Contingency (buffer based on known risk) & include in project budget or Managerial (buffer based on unknown risks) Rolling Wave Planning An iterative technique used when future details aren't known; near term is planned in detail; future is higher level Predecessor Relationships Finish to Start (FS) Finish to Finish (FF) Start to Start (SS) Start to Finish (SF) Default relationship; B cannot start until A is finished B cannot finish until A is finished B cannot start until A starts Rare, A starts before B finishes (e.g. when replacing an old system B with a new system A) A B A B A B A B Free Slack The latest an activity can start without delaying next activities Total Slack The latest an activity can start without delaying project finish date Float Often referred to as the same as Slack Lag Lag (a delay) = the successor must wait due to some delay after the predecessor is complete Lead Lead (an accelerant) = the successor can begin before the predecessor is complete Schedule Compression Crashing or fast tracking the schedule to adjust the schedule to align with the plan Fast Tracking Compression technique based on overlapping sequential activities (risky) Resource Leveling Adjusting peaks and valleys to create a level usage of resources Resource Smoothing Adjusting peaks and valleys to create a level usage of resources AND also accounts for individual resource limitations
  • 17. 4. Cost Management – Process Activities This area includes defining how project costs will be managed, estimating activity costs, determining the budget, and controlling costs. 17 Plan Cost Management Estimate Costs Determine Budget Cost Baseline Project Funding Requirements Control Costs Work Performance Info Cost Forecasts Change Requests Updates Analogous Parametric Bottom Up 3 Point Reserve Exp. Judgment Aggregation Reserve Analysis Funding LImits Earned Value TCPI Forecasting PMIS Reserve Anal. Cost Mgt. Plan Activity Cost Estimates Basis of Estimates IRR NPV ROI Opportunity $ Payback Establish the policies, procedures, and documentation for planning, managing, expending, and controlling project costs Develop an approximation of the monetary resources needed to complete project activities Aggregate estimated costs of individual activities or work packages to establish an authorized cost baseline Monitor the status of the project to update project costs and manage changes to the cost baseline Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 18. 18 Earned Value Management (EVM) EVM is a means of measuring project cost and schedule vs. the plan. Earned Value (EV) = budgeted cost for work actually completed Time Dollars Cost Baseline (“S” Curve) Approved Time-Phased Budget BAC Budget at Completion (BAC) = total project budget Estimate to Complete (ETC) = cost to complete the project based on current spending efficiency ETC EAC Estimate at Completion (EAC) = current projected final cost based on current spending efficiency Variance at Completion (VAC) Cost Variance (CV) Cost Performance (CPI) = EV/AC Schedule Variance (SV) Schedule Performance (SPI) = EV/PV Planned Value (PV) = budgeted cost for work scheduled Actual Cost (AC) at point in time AC PV EV Point in Time
  • 19. 19 5. Quality Management – Process Activities Quality management includes identifying quality requirements and standards, auditing requirements and control measurements, assessing quality performance, and recommending changes, when needed. Plan Quality Management Perform Quality Assurance Control Quality Cost/Benefit Cost of Quality 7 Basic Tools Benchmarking Sampling Quality Mgt. Plan Process Improvement Plan Quality Metrics Quality Checklists Quality Audits Controls Charts Process Analysis Updates Verified Deliverables QC Measures Validated Changes Measurements Identify quality requirements and/or standards for the project and its deliverables, and document how the project will demonstrate compliance Audit the quality requirements and the results from quality control measurements to ensure appropriate standards and operational definitions are used Monitor and record results of quality activities to assess performance and recommend necessary changes Key: Initiating Planning Executing Monitoring & Controlling Closing
  • 20. 20 Quality Management Philosophies and Principles PMI quality management principles are based on a few popular philosophies. Quality Philosophies: • Total Quality Management (Deming) – proactive approach with statistical analysis • Zero Defects (Crosby) – Do it right the first time • Fitness for Use (Juran) – Satisfy customer needs • Continuous Improvement (Kaizen) – proactive approach to process improvement • Gold Plating – unacceptable practice of providing more than requested • Cost of Quality – cost of conforming is less than cost of non-conforming • Design of Experiments – isolate factors that influence results • 6 Sigma – strive for 99.9997% error free • ISO 9000 – document what you do; do what you document Quality Principles: • Define and satisfy customer needs • Prevent rather than inspect • Be proactive rather reactive • Validate project processes • Measure against approved standards • Continually improve • Take accountability
  • 21. 21 Quality Management Tools and Terms Project managers should be familiar with common quality management tools and terms. Tools Description 1. Cause and Effect Diagrams Fishbone (Ishikawa) diagram 2. Flowcharts Basic flow chart or GERT diagram with feedback loop 3. Checksheets Check list (e.g. pre-flight list to ensure you are "cockpit ready" before taking flight) 4. Pareto Diagrams Cumulative histogram (e.g. 80/20 rule) 5. Histograms Depiction of volume or frequency of occurrences of several events 6. Control Charts Depiction of process output over time with UCL & LCL at 3 sigma from mean 7. Scatter Diagrams Depicts pattern of results across two variables Terms Description Benchmarking Comparing actual or planned processes to comparable projects to identify best practices Design of Experiments Variable based analysis (freeze all variables but one and assess outcome) Statistical Sampling Using a % of the population and extrapolating the results within an acceptable confidence level Quality Audits Identify best practices; identify gaps; share best practices; offer assistance to improve; highlight lessons learned Process Analysis Assess process, identify root causes, alleviate root causes Inspection Examination of work product and comparison to documented standards (e.g. reviews, audits) 85/15 Rule 85% of quality relates to mgt.; 15% is worker related 80/20 Rule 80% of problems come from 20% of the issues Rule of 7 Must have 7 consecutive data points above or below mean to consider process "out of control" Mean Time Before Failure MTBF, example quality metric Mean Time to Repair MTTR, example quality metric Grade vs. Quality Not the same; you can have a lower grade product with high quality and vice versa (e.g. automobile models) Upper Control Limit UCL = 3 sigma above mean (average) Lower Control Limit LCL = 3 sigma below mean (average) Upper Specification Limit USL is customer established and can be above or below UCL Lower Specification Limit USL is customer established and can be above or below LCL
  • 22. 6. Human Resource Management - Process Activities Human resource management consists of planning, acquiring, developing, and managing the project team. 22 Plan HR Management Acquire Project Team Develop Project Team Manage Project Team Change Requests Updates Org Charts Job Descriptions Org. Theory Pre- Assignment Acquisition Negotiation Training Team Building Ground Rules Recognition Rewards HR Mgt. Plan Project Staff Assignments Resource Calendars Team Performance Assessments Observations Conversations Conflict Mgt. Performance Appraisals Define roles, responsibilities, required skills, and reporting relationships Confirm availability and obtain the necessary team Improve competencies, team interaction, the team environment, and enhance project team performance Track team member performance, provide feedback, resolve issues, and manage changes to the team to optimize team performance Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 23. 23 Roles and Responsibilities Responsibility assignment matrix (RAM) charts such as a “RACI” let each team member know who is responsible for each activity and deliverable. RACI Person Activity Ann Ben Carlos Denny Develop Schedule A R I I Collect Requirements I A R C Develop Test Plan I A R C Develop Training Plan A C I R • (R) Responsible - those who do the work • (A) Accountable - The one who: o Is ultimately answerable for the completion of the deliverable o Delegates the work to those responsible o Approves the work that the responsible person provides • (C) Consulted – those whose opinions are sought (typically subject matter experts); typically this is a two way communication • (I) Informed – those who are kept up-to-date on progress; typically this is a one way communication
  • 24. 24 Project Life Cycle - Team Building & Leadership Styles Project managers should be aware of typical team building dynamics and situational leadership styles across a project life cycle. Team Building: Forming Storming Norming Performing Adjourning Leadership Style: Directing Coaching Facilitating Supporting Initiating Closing Project Life Cycle Team Building Stages • Forming – creating the team • Storming – team chaos as people start working with one another • Norming – team behavior starts to normalize • Performing – team performs as a unit • Adjourning – team completes work and disbands Time Situational Leadership Styles • Directing – provide specific, clear instructions and closely supervise • Coaching – solicit input, offer rationale and examples • Facilitating –maintain team progress; delegate day-to-day control • Supporting – support and motivate the team to complete objectives
  • 25. Conflict is inevitable. A project manager should be aware of typical sources of project conflict and recommended techniques to resolve them. 25 Conflict Management Sources of Conflict Conflict Resolution Techniques • Scheduling Priorities • Scarce Resources • Personal Work Styles • Methodology/Details • Cost/Budget • Personalities Recommended: 1. Collaborate/Problem Solve 2. Compromise/Reconcile 3. Force/Direct Not Recommended: 1. Smooth/Accommodate 2. Withdraw/Avoid Higher Probability of Conflict Lower
  • 26. 26 7. Communication Management - Process Activities Roughly 90% of a project manager’s job is communication. Plan Communication Management Communciation Mgt. Plan Manage Communications Project Communications Control Communications Req. Analysis Technology Models Methods Meetings Models Method Systems Reporting Exp. Judgment Systems Meetings Work Performance Information Change Requests Develop a communication approach based on stakeholder’s informational needs Create, collect, distribute, store, and retrieve information Monitor and control communication throughout the entire project life cycle Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 27. 27 Communication Management Project managers should be aware of the basics of effective communication across the broad stakeholder community. Transmit Communication Paths N N N N • # of Communication Paths equals [N x (N-1)]/2 • N equals # of Stakeholders • Example: [4 x (4-1)]/2 = 6 Communication Methods • Interactive – between two people • Push – send to specific recipients • Pull – recipient actively seeks information Communication Types • Active listening – receiver verifies correct interpretation • Effective listening – receiver observes visual and vocal cues • Feedback – sender receives feedback from receiver • Nonverbal - ~55% of communication (e.g. body and facial language) • Para-lingual – Voice characteristics Communication Model Sender/Encode Decode/Receiver Acknowledgement Response Noise Noise
  • 28. 28 8. Risk Management – Process Activities Risks are possible events that could impact the project in a positive (an opportunity) or negative (a threat) way. Plan Risk Management Identify Risks Risk Register (Risks & Triggers) Perform Qualitative Analysis Perform Quantitative Analysis Plan Risk Response Control Risks Updates Updates Project Documents Risk Mgt. Plan Updates Updates Define how to conduct risk management activities Determine and document the characteristics of risk which may affect the project Prioritize risks for further analysis or action by assessing their probability of occurrence and impact Analyze the effect of identified risks on overall project objectives Develop options and actions to enhance opportunities and reduce threats to project objectives Implement risk response plans, track identified risks, monitor residual risks, identify new risks, and evaluate risk process effectiveness Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 29. 29 Risk Probability and Impact Matrix A probability and impact matrix can be used to evaluate the impact of a risk and the probability of its occurrence. High Moderate Low Moderate High Probability of Occurrence Level of Impact Positive Risk Responses • Share – split the responsibility and benefit to maximize the opportunity • Exploit – take steps to ensure success • Enhance – improve the size of the risk event and impact • Accept – do nothing Negative Risk Responses • Avoid – get rid of the potential problem • Transfer – re-assign to another party • Mitigate – minimize the bad characteristics of the risk • Accept – do nothing Probability and Impact Matrix The higher the combined probability and impact of the risk event the greater the need to develop a risk response plan
  • 30. 30 Risk Management Project managers should be aware of risk management terms. Risk Management Terms • Monte Carlo – simulation of possible outcomes • Risk Breakdown Structure – breakdown by category (e.g. internal, external, technology, organizational, etc.) • Risk Trigger – an indicator that an event “could” occur • SWOT Analysis – strengths, weaknesses, opportunities, and threats • Expected Monetary Value (EMV) – summation of probability x impact of alternative decisions (…not to be confused with EVM – earned value management) • Contingency Reserves – for known risks (include in budget and schedule) • Management Reserves – for unknown risks (excluded from baselines for budget and schedule) • Residual Risk – risk remaining after risk response • Secondary Risk – potential risk as a result of risk response • Workaround – “wing it” response when other risk response plans don’t work • Types of Risk Tolerance o Averse – Avoids risk o Seeker – Seeks risk o Neutral – Middle ground
  • 31. 31 9. Procurement Management – Process Activities Procurement management includes planning, selecting, contracting, controlling, and closing outsourced products and services. Procurement Mgt. Plan Plan Procurement Mgt. Conduct Procurements Control Procurements Work Performance Info Updates Change Requests Close Procurements Procurement Mgt. Plan SOW RFPs Selection Criteria Make Buy Decision Selected Suppliers Agreements Resource Calendars Exp. Judgment Make Buy Analysis Exp. Judgment Bidder Conf. Ind. Estimates Advertising Seller Proposals Inspect/Audits Reporting A/P Systems Claims Admin. Records Mgt. Audits Negotiations Record Mgt. Closed Procurements OPA Udpates Document project procurement decisions, specify the approach, and identify potential sellers Obtain seller response, select a seller, and award a contract Manage procurement relationship, monitor contract performance, and make changes and corrections as appropriate Complete each project procurement, including finalizing open claims, updating records to reflect final results, and archiving information Key: Initiating Planning Executing Monitoring & Controlling Closing Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 32. 32 Contract Types Project managers should be aware of the benefits and risks of different contract types from a buyer’s perspective and a seller’s perspective. Buyer’s Risk Low High FFP FPIF FP EPA T&M PO CPFF CPIF CPAF CPPC Seller’s Risk High Low • (FFP) Firm Fixed Price – allows buyer to budget fixed price; requires seller to detail scope and accurately estimate price; very common • (FFIF) Fixed Price Incentive Fee – includes incentive to motivate seller to produce at greater speed • (FF EPA) Fixed Price Economic Price Adjustment – compensates for year to year economic changes • (T&M) Time and Materials – typically used for smaller initiatives • (PO) Purchase Order – typically used for commodity items • (CPFF) Cost Plus Fixed Fee – typically variable costs are cost-plus and predictable costs are fixed fee • (CPIF) Cost Plus Incentive Fee – actual costs plus incentive to motivate seller to produce at greater speed • (CPAF) Cost Plus Award Fee – actual costs plus award based on customer satisfaction with agreed criteria • (CPPC) Cost Plus Percent of Cost – actual cost plus % of actual; the higher the cost, the higher the fees
  • 33. 33 Procurement Terms Project managers should be familiar with additional procurement terms in the table below: Terms Description Make or Buy Analysis Is it more practical to insource or outsource (based on a cost comparison between the two)? Bidder Conference Prior to bid submission, offers opportunities for prospective sellers to obtain requirements clarification from buyer Independent Estimates Used to validate proposal information Contract (CCOLA) Must have 5 Components: Capacity, Consideration, Offer, Legal Purpose, Acceptance Point of Total Assumption Point at which seller is responsible for all cost overruns; PTA = (Ceiling Price - Target Price)/Buyer Share + Target Cost Ceiling Price % of Target Cost (e.g. Ceiling = 140% of target cost) Target Cost Expected cost of work in the contract Target Price Equals Target Cost + Target Profit Share Ratio Ratio of split between buyer and seller of cost savings or overruns (e.g. 70/30) RFP Request for Proposal, typically used for higher priced, customized services or products RFQ Request for Quote, typically used for small dollar commodity type products IFB Invitation to Bid, used for government sealed bids (similar to RFP) Design Scope of Work (SOW) Buyer provides exact details; generally results in fixed price contract Functional Scope of Work (SOW) Buyer provides functionality needed; generally results in cost plus contract Sole Source Go direct to a supplier without any available competition (e.g. supplier holds the patent) Single Source Go direct to a supplier although competitors are available (e.g. "preferred supplier") Negotiation PMI prefers "win/win" negotiation approach Standard Terms & Conditions Typical common (non-negotiable) contract items with a tight range or parameters Special Provisions Typically added to account for changes to standard terms and conditions Claims Administration Means of administering contested changes or disagreements regarding compensation ADR Alternative dispute resolution (e.g. arbitration) used when claims cannot be negotiated between buyer and seller
  • 34. Key: Initiating Planning Executing Monitoring & Controlling Closing 34 10. Stakeholder Management – Process Activities It is critical to project success to identify stakeholders, address their requirements, meet their expectations, and foster their engagement. Identify Stakeholders Plan Stakeholder Management Manage Stakeholder Engagement Stakeholder Register Stakeholder Mgt. Plan Issue Log Change Requests Updates Control Stakeholder Engagement Work Performance Info Change Requests Updates Exp. Judgment Stakeholder Analysis (Power/ Interest) Interpersonal Skills Management Skills Stakeholder Engagement Matrix (Unaware, Neutral, Resistance, Leading) Identify the people, groups, or organizations that could impact or be impacted by the decision, activity, or outcome of the project. Develop appropriate management strategies to effectively engage stakeholders throughout the project life cycle based on their needs and potential impact on project success Communicate and work with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholder engagement throughout the project life cycle Monitor overall project stakeholder relationships and adjust strategies and plans for engaging stakeholders Note, additional inputs, outputs, tools and techniques not depicted may apply
  • 35. 35 Stakeholder Power vs. Interest Grid All stakeholders are different and, therefore, need to be managed differently based on their relative authority (power) and level of concern (interest). Stakeholder Power vs. Interest Grid Keep Satisfied Manage Closely Monitor Keep Informed High Moderate Low Moderate High Power Interest
  • 36. 36 PMI Code of Ethics and Professional Conduct All PMI members must agree to adhere to a high personal standard of ethical and professional behavior. Tenets of Code: 1. Honor o Do what is right and honorable o Set high standards for yourself and aspire to meet those standards is all aspects of life 2. Responsibility – Take ownership of: o The decisions you make or fail to make o The actions you take or fail to take o The consequences that result 3. Respect o Show high regard for yourself, others, and the resources (e.g. people, money, reputation, safety) entrusted to you o Engender trust confidence, performance excellence, and mutual cooperation in an environment of diverse perspectives and views 4. Fairness o Make decisions and act impartially and objectively o Conduct yourself in a way free from competing self interest, prejudice, and favoritism 5. Honesty o Understand the truth o Act in a truthful manner both in your communication and in your conduct
  • 37. 37 Summary This material covered the following project management topics: • What is PMI and the PMP? • Why PMI Project Management Principles are Useful to Know • A Few Basic PMI Definitions • Five Process Groups o Initiating o Planning o Executing o Monitoring and Controlling o Closing • Ten Knowledge Areas o Integration o Scope o Time o Cost o Quality o Human Resources o Communication o Risk o Procurement o Stakeholders • Project Management Terms, such as: o Triple Constraint o Project Charter o Project Management Plan o Work Breakdown Structure (WBS) o Predecessor Relationships o Earned Value Management o Gold Plating o Responsibilities Assignment Matrix o Forming, Storming, Norming, Performing, Adjourning o Communication Noise o Risk Probability and Impact Matrix o Contract Type o Stakeholder Power vs. Interest Grid • Code of Ethics and Professional Conduct o Honor o Responsibility o Respect o Fairness o Honesty Thank you for taking the time to review this material!