SlideShare uma empresa Scribd logo
1 de 59
SLIDE 1
AN INTRODUCTION TO
POWER SYSTEM FAULT ANALYSIS
SLIDE 2
INTRODUCTION
A fault calculation is the analysis of the power system electrical behaviour under fault
conditions, with particular reference to the effects on the system currents and voltages.
Accurate fault calculations are essential for proper system design. The analysis of fault
conditions and their effects on the power system is of particular relevance to such
conditions as:
a. the choice of a suitable power system arrangement, with particular reference to
the configuration of the transmission or distribution network.
b. the determination of the required load and short-circuit ratings of the power
system plant.
c. the determination of the breaking capacity required of the power system
switchgear and fusegear.
d. the design and application of equipment for the control and protection of the
power system.
e. the operation of the system, with particular reference to security of supply and
economic considerations.
f. the investigation of unsatisfactory performance of the power system or of
individual items of power system plant.
SLIDE 3
Types of Fault
In the context of electrical fault calculations, a power system fault may
be defined as any condition or abnormality of the system which
involves the electrical failure of primary equipment, i.e. generators,
transformers, busbars, overhead lines and cables and all other items
of plant which operate at power system voltage.
Electrical failure generally implies one of two conditions or types of
failure (sometimes both), namely insulation failure resulting in a
short-circuit condition or a conducting path failure resulting in an
open-circuit condition, the former being by far the more common type
of failure.
SLIDE 4
a) Short-circuited phases
Faults of this type are caused by insulation failure between phase conductors or between phase
conductors and earth, or both. Figure 1 gives details of the various short-circuited-phase faults.
Figure 1: Short-circuited-phase faults
The three-phase fault, which may or may not be to earth, is the only balanced short-circuit
condition and is the one used as the standard in determining the system fault levels or ratings.
SLIDE 5
b) Open-circuited phases
Faults of this type, see Figure 2, result in the failure of one or more phases to conduct.
The more common causes of this type of fault are joint failures on overhead lines and cables, and
the failure of circuit-breakers or isolators to close properly. Both the single-phase and the two-
phase conditions are of particular interest because they tend to produce unbalance of the power
system currents and voltages with the consequent risk of damage to rotating plant.
Figure 2: Open-circuited phase faults
SLIDE 6
c) Simultaneous faults
A simultaneous fault condition, or a multiple fault condition, is
defined as the simultaneous presence of two or more faults which may
be of similar or dissimilar types and may be at the same or different
points in the power system.
The most common simultaneous fault condition is undoubtedly the
double-circuit overhead line fault in which a common cause, i.e.
lightning or clashing conductors, results in a fault on each of the two
circuits concerned.
Another simultaneous fault condition is known as the cross-country
earth-fault, in which a single-phase to earth fault at one point occurs
coincidentally with a second such fault on another phase at some other
point in the system.
SLIDE 7
d) Winding faults
This type of fault, which can occur in machine or transformer windings, is detailed in Figure 3, and
consists mainly of short circuits, from one phase to earth, or from phase to phase, or from one point
to another on the same phase winding. The last fault condition is known as the short-circuited
turns fault. This condition can pose special problems from a protection point of view because the
current in the shorted turns can be very large, while that in the remainder of the winding may be
quite small.
The open-circuited winding condition is quite rare in practice and is usually the result of damage to
the winding as a consequence of a preceding winding short circuit at or near the point of fault.
Open circuits in transformers may also occur as a result of failure of tap-changing equipment.
Phase-to-earth fault Phase-to-phase fault
Short-circuited turns Open-circuited winding
Figure 3. Winding faults
SLIDE 8
Factors Affecting Fault Severity
The severity of a power system fault condition may be assessed in terms of the
disturbance produced and the fault damage caused, the magnitude of the fault
current and its duration being of particular interest, especially in relation to the
design and application of the power system protection. The main factors which
affect the severity of a fault are:
a) Source conditions
These relate to the amount and location of all connected generation equipment -
including the ties or interconnections with other systems, the two extremes of
minimum and maximum connected plant being of particular interest. The
minimum and maximum plant conditions are normally those corresponding to the
conditions of minimum and maximum connected load.
SLIDE 9
b) Power system configuration
This is determined by the items of plant, i.e. generators, transformers, overhead lines
and cable circuits, etc., assumed to be in service for the particular condition being
investigated and by other such factors as may have a bearing on the make-up of the
equivalent circuit of the system. The system configuration may change during the
course of a fault with consequent changes in the magnitude and distribution of the
fault currents. Typical causes of the above changes being the sequential tripping of
the circuit-breakers at the two ends of the faulted transmission line and the sequential
clearance of multiple fault conditions.
SLIDE 10
c) Neutral earthing
Faults which involve the flow of earth current, i.e. phase faults to earth,
may be influenced considerably by the system neutral earthing
arrangements, particularly by the number of neutral earthing points and
the presence or absence of neutral earthing impedance. The power system
may be single-point or multiple-point earthed and such earthing may be
direct, i.e. solid earthing, or via a neutral impedance. The 132kV, 275kV
and the 400kV systems employ direct multiple earthing while the 66kV and
below generally employ single-point, sometimes multiple, resistance
earthing.
SLIDE 11
d) Nature and type of fault
From what has been said already, it is evident that the type and
location of a fault will have a significant effect on the magnitude
and distribution of the system fault currents. Likewise, the effect of
a given fault condition may be considerably modified by the
simultaneous presence of one or more other fault conditions, for
example, the combination of a short circuit and an open-circuited
phase condition.
SLIDE 12
The wide range of possible system fault conditions and the many
factors which influence them result in a wide range of possible
fault severity, ranging from very low levels up to the maximum
level possible for the system. It is of value to consider a standard
fault condition when discussing systems and the three-phase fault
level may be expressed in amperes but it is usually expressed in
MVA, corresponding to the rated system voltage and the current
for a symmetrical three-phase fault. This three-phase fault level
normally determines the required short-circuit rating of the power
system switchgear. A factor which may also have to be taken into
account is the maximum value of the one-phase to earth fault
current which, in a solidly earthed system, may exceed the
maximum three-phase fault current.
SLIDE 13
Methods of Fault Calculation
♦ The information normally required from a fault calculation is that
which gives the values of the currents and voltages at stated points in
the power system when a given fault condition is imposed on the system.
♦ A fault calculation is therefore, essentially a matter of network
analysis and can be achieved by a number of methods, i.e. mesh- current or
nodal-voltage methods, network reduction techniques or simulation using a
network analyser.
♦ The choice of method depends on the size and complexity of the
circuit model and the availability of computing facilities.
SLIDE 14
Methods of Fault Calculation
♦ An essential part of power system analysis and fault calculation is
that which concerns the determination of the equivalent system
network for the system operating conditions and the fault
conditions under consideration.
♦ As stated earlier, faults can be subdivided into either balanced
(symmetrical) or unbalanced (unsymmetrical) fault conditions,
this latter case being analysed, traditionally, by the method of
symmetrical components.
♦ Both classes of fault are analysed by reducing the power system,
with its fault condition, to an equivalent single-phase network.
SLIDE 15
Balanced Faults
The balanced fault is often the severest and is the simplest to determine. Hence, this
is the one normally used to determine the 'duty' of the system switchgear and busbars
Fault Calculation Procedure
The analysis of a 3-phase balanced fault condition consists, in general, of three parts:
a. the system with its fault condition is represented by its positive sequence
network,
b. the network is solved in terms of per-unit quantities,
c. the resulting per-unit quantities are converted to actual values.
Component Representation
Overhead lines and cables are normally represented by their series impedance on the
basis that the shunt impedance is high. Transformers and synchronous machines are
normally represented by their reactances as the resistance values are relatively small.
Load impedances are normally much larger than the other network impedances and
hence, they are normally neglected in fault calculations.
SLIDE 16
THREE PHASE FAULTS
The following example is presented to illustrate the methods employed for the
case which induces positive sequence components only. The system shown
represents a power station connected to the grid, together with its auxiliary
systems. The principle circuit and plant parameters are given in Table 1.
SLIDE 17
G2/3
G
Inf bus
Bus 1
T2/T3
G1
∆
∆
T1
T4
T5
M2
03BBus 203A
M1
T6 T7
M3 M4
L L
MCC2 Bus 3 Bus 4 MCC1
∆
∆
∆
∆ ∆
A fault is assumed to
occur first on busbar
MCC1 and secondly on
busbar MCC2. The fault
level quoted on Bus 1 is
2500 MVA.
Example
SLIDE 18
G2/3 71 MVA, X = 263 pu on 100 MVA
T2/T3 71 MVA, Xl = 009pu
G (2500-147-71)MVA
G1 147 MVA, Xd
= 1867 pu
T1 150 MVA, Xl
= 013 pu
T4 16 MVA, Xl
= 01 pu
T5 16 MVA, Xl
= 009 pu
T6 2 MVA, Xl
= 006 pu
T7 4 MVA, Xl
- 006 pu
M1 88 MVA
M2 806 MVA
M3 1247 MVA
M4 0977 MVA
SL 0918 MW, 09 p.f.
Table 1
SLIDE 19
grid infeed
100
2500 147 71( )− −
= ·438
Base 100 MVA
71 MVA
generation
2·63 (given)
100 09
71
127
× ⋅
= ⋅
147 MVA
generator
100 1 867
147
1 27
× ⋅
= ⋅
100 13
150
08
× ⋅
= ⋅
100 1
16
625
× ⋅
= ⋅
03B 03A
100 09
16
5625
× ⋅
= ⋅
MCC2 MCC1
100 06
2
3
× ⋅
=
100 06
4
1 5
× ⋅
= ⋅
N.B. 2x2 MVA Transformers
in parallel
3
1
2
Normalised system reactances on
equivalent circuit
SLIDE 20
Using the Star Delta Transform to simplify the above circuit
SLIDE 21
SLIDE 22
SLIDE 23
The resolution of the problem into sequence components results in considerable
simplification of all problems involving asymmetry such as that introduced by short-
circuiting conductors of a system either together or to earth, singly or in pairs, or by
the open circuiting of a conductor. The resolution of the problem into sequence
components has the further advantage in that it isolates the quantities into
components which represent a better criteria of the controlling factor or factors in
certain phenomena.
Consider the following system of vectors shown below.
SLIDE 24
A graphic vectorial representation is not tractable when dealing with complex practical
systems. Consider the vector equations in which , are written in terms of the
positive, negative and zero sequence components .
(1)
SLIDE 25
Rewriting equation (1), and for convenience neglecting the bar denoting vector quantities
Va = Va1 + Va2 + Va0
Vb = λ2
Va1 + λVa2 + Va0 (2)
Vc = λVa1 + λ2
Va2 + Va0
and Va0, Va1 and Va2 may now be written as V0, V1 and V2
where λ is an operator which moves a vector 120° anticlockwise, i.e.
λ = 0.5 + 0.886j
λ2
= - 0.5 – 0.886j (3)
λ3
= 1
Other useful identities in are given in the following Table 1.
Table 1
SLIDE 26
The transformation of phase quantities to sequence and reverse is given by
[Vph] = [T] [Vseq]
and [Vseq] = [T] -1
[Vph]
where [T] = (4)
and [T] -1
= (5)
SLIDE 27
SLIDE 28
For example, consider the network shown in the figure below
It follows that
[ ] [ ][ ]










=










2
1
0
2
1
0
I
I
I
TZ
V
V
V
T
SLIDE 29
premultiplying equation (7) by [T] -1
the following sequence component equations are
obtained.
[ ] [ ][ ]










=










−
2
1
0
1
2
1
0
I
I
I
TZT
V
V
V
SLIDE 30
Evaluating the term [T]-1
[Z] [T] defines the sequence impedances
[T]-1 [Z] [T] (9)
SLIDE 31
N.B. The transformation diagonalises the impedance matrix, in which Z1 = Z2, i.e. positive
and negative sequence impedances are equal. The sequence currents are obtained
from:
(10)
Now consider the case where the circuit impedances are of the form
possible distribution for an electrical machine
SLIDE 32
(11)
resulting in sequence impedances of different values.
SLIDE 33
Example
An untransposed transmission line gives rise to 3 per cent negative sequence voltage.
Show approximately how this affects the magnitudes of the terminal voltages of the
generator supplying the system.
No zero sequences voltage; let V2 = 0⋅03 V1
Va = V1 + 0⋅03V1 = (1 + 0⋅03)V1
Vb = λ2
V1 + λ0⋅03V1 = (λ2
+ 0⋅03λ)V1
Vc = λV1 + λ2
0⋅03V1 = (λ + 0⋅03λ2
)V1
SLIDE 34
SLIDE 35
SLIDE 36
Components of voltage
VA = 0 and since the generator is only able to generate positive sequence components,
E0 = E2 = 0
Also, since IB = IC = 0, I0 = I2 = 0
021
1
1
ZZZ
E
I
++
=
SLIDE 37
The fault current If = IA = 3I1
where E is the generated phase voltage.
The equivalent circuit is given by
021
f
ZZZ
E3
I
++
=
SLIDE 38
Example
X1 = 0⋅2j pu
X2 = 0⋅1j pu
X0 = 0⋅05j pu
Consider an earth fault at B
Choose base of 75 MVA, VB = 33 kV
SLIDE 39
SLIDE 40
The next stage is to draw a sequence diagram. For the single phase to earth fault, the
positive, negative and zero sequence diagrams are connected in series.
SLIDE 41
= -j3·49 kA
The fault current may be reduced by increasing the impedance to the fault. Using the data
of the above example, consider the effect of earthing only one generator.
SLIDE 42
SLIDE 43
Consider placing an impedance in the earth path as shown in Figure 12.
Figure 12
N.B. Zero sequence components only flow in the earth path.
∴ Zero sequence network becomes
Figure 13
SLIDE 44
SLIDE 45
The sequence diagram becomes
I0 = I1 = I2
I1 = (0⋅621 - 1⋅19j)
If = 3 x (0⋅621 - 1⋅19j) x = 2⋅93(0⋅621 - 1⋅19j) kA
SLIDE 46
Too large a fault current can cause problems, nevertheless the
fault current must be sufficient to be detected by protection.
However, before proceeding further, the effect of the transformer
windings on the flow of zero sequence currents must be assessed.
SLIDE 47
Shown below are three connection diagrams for power transformers
Star / Star, primary and
secondary windings earthed
I0 will flow in primary and
secondary circuits
Star / Star, primary winding
earthed, secondary unearthed
I0 cannot flow in secondary circuit
Star / Delta, primary winding
earthed
I0 flows in primary and
circulated in the secondary
SLIDE 48
Shown below are the three equivalent circuits corresponding to the previous connection
diagrams for the power transformers.
SLIDE 49
Shown below is the equivalent circuit for a three-winding transformer
SLIDE 50
Returning to the example and considering only the zero sequence diagram
The zero sequence impedance has been increased by Z0(trans) and therefore, If will be less.
SLIDE 51
Consider the / transformer replaced by a Δ/ .
Zero sequence diagram:
The RN is now out of circuit for an end of line fault. However, its effect is seen for a fault
at the generator terminals. If will now rise as compared to previous case.
SLIDE 52
NONE OF CONFIGURATIONS AFFECT THE POSITIVE AND NEGATIVE SEQUENCE
NETWORKS
A further modification involves the inclusion of second transformer
The Zero sequence diagram becomes
SLIDE 53
PRACTICAL FAULT STUDIES
As previously stated, power systems are subject to excessive damage when high
magnitude currents are flowing due to system short circuit. The analysis so far
has been confined to steady-state conditions arising subsequent to fault incidence.
The initial transient condition has been neglected which, for many practical
situations, is considered to be satisfactory. However, the instant of initiation of the
short circuit relative to the voltage waveform, has a marked effect upon the
maximum peak value of the short-circuit current which may be important from
the point of view of fast acting fault clearance devices, i.e. does the circuit breaker
operate prior to the decay of the transient component of the current.
SLIDE 54
Consider the single phase equivalent circuit of a generator shown in Figure 26.
Figure 26
If S is suddenly closed, the equation representing the equivalent circuit on a single phase
basis is
(43)
The solution of which yields
(44)
where Z2
= r2
+ ω2
L2
and tan φ =
and (45)
SLIDE 55
The total current is obtained by adding the steady-state and the transient components.
SLIDE 56
In practice, the time variation of the short circuit current is dependent on the
actual characteristic of the generator. To a close approximation, the short
circuit current can be allocated to the following categories:
1. the continuous component
2. the transient component
3. the subtransient component
These categories are determined by the electromagnetic process that occurs
in the generator. For most fault studies, the representation and calculation of
the short circuit characteristics are based on a constant voltage and on the
assumption that the decay of the ac short-circuit current is due to an increase
in the generator reactances from
(1) the subtransient reactance Xd"
to (2) the transient reactance Xd'
and finally (3) the synchronous reactance Xd
SLIDE 57
Therefore, the fault current for the three conditions may be calculated as:
; ;
If this approximation is acceptable, then the analysis previously developed is applicable by
merely using the appropriate value of generator impedance. Otherwise, a full system
transient analysis is required which involves considerable computing time.
SLIDE 58
Synchronous and Induction Motor Loads
For a short-circuit period of T ≤ 0·2s, synchronous motors can be treated in
the same manner as synchronous generators. In a larger short-circuit
period, the machine is subjected to a speed drop and is then operating in an
assynchronous mode. High and low voltage motors similarly make a
contribution to the short-circuit current. However, due to differences in
their construction, this contribution decays very rapidly.
Short-circuit analysis is generally preceded by data collection and the
preparation of a one-line diagram, followed by the determination of the
exact objectives of the study. Table 2 gives an indication of parameter
values to be used under certain circumstances.
SLIDE 59
Table 2

Mais conteúdo relacionado

Mais procurados

DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYRaviraj solanki
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current ProtectionSARAVANAN A
 
Harmonics and mitigation techniques
Harmonics and mitigation techniquesHarmonics and mitigation techniques
Harmonics and mitigation techniquesrifat maryum
 
Distribution systems
Distribution systemsDistribution systems
Distribution systemsSURAJ PRASAD
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclVISHAL VERMA
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedureMustafa Ismail
 
Protective relay
Protective relay Protective relay
Protective relay Uday Wankar
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection michaeljmack
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformerROOPAL PANCHOLI
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault AnalysisSANTOSH GADEKAR
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical poweDarya khan
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSKarthik Bharadwaj
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationraiamitesh8
 

Mais procurados (20)

132 kv
132 kv132 kv
132 kv
 
DISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAYDISTANCE PROTECTION RELAY
DISTANCE PROTECTION RELAY
 
Relays
RelaysRelays
Relays
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
Harmonics and mitigation techniques
Harmonics and mitigation techniquesHarmonics and mitigation techniques
Harmonics and mitigation techniques
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
Basic short circuit calculation procedure
Basic short circuit calculation procedureBasic short circuit calculation procedure
Basic short circuit calculation procedure
 
Protective relay
Protective relay Protective relay
Protective relay
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
Hvdc notes
Hvdc notesHvdc notes
Hvdc notes
 
Transmission lines of Electrical powe
Transmission lines of Electrical poweTransmission lines of Electrical powe
Transmission lines of Electrical powe
 
Motor starter
Motor starterMotor starter
Motor starter
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTS
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 

Destaque

distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangementManjunath Ds
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2R.K. Mathuria
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Living Online
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohitMohit Awasthi
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesLiving Online
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...Vikram Rawani
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthingNitesh Dash
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Conceptsmvrkprasad
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthingDenuka
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION moiz89
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety Reliance
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safetyRock Wood
 

Destaque (20)

distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2
 
Earthing system
Earthing systemEarthing system
Earthing system
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...
 
400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit400kv sub-station-final-ppt-by-mohit
400kv sub-station-final-ppt-by-mohit
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety Rules
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthing
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Importance of industrial safety
Importance of industrial safetyImportance of industrial safety
Importance of industrial safety
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safety
 
Electrical safety new
Electrical safety newElectrical safety new
Electrical safety new
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safety
 
Substation overview
Substation overviewSubstation overview
Substation overview
 

Semelhante a File 1 power system fault analysis

283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.pptAshaLatha456489
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission linepamu17
 
Voltage support to grid under unbalance rodriguje
Voltage support to grid under unbalance rodrigujeVoltage support to grid under unbalance rodriguje
Voltage support to grid under unbalance rodrigujeDeepak Gehlot
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit iivenki249
 
Out of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersOut of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersAli Sepehri
 
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...Suganthi Thangaraj
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculationsRonald Santos
 
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdf
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdfH7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdf
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdfEMERSON EDUARDO RODRIGUES
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...IRJET Journal
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)ingcortez
 
Protection of Converter Dense Power Systems
Protection of Converter Dense Power Systems Protection of Converter Dense Power Systems
Protection of Converter Dense Power Systems Aditya Kumar Tripathy
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdfssuser564db8
 
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...Suganthi Thangaraj
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryHimmelstern
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryHimmelstern
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET Journal
 

Semelhante a File 1 power system fault analysis (20)

ECE610 IEEE
ECE610 IEEEECE610 IEEE
ECE610 IEEE
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
 
Schneider system grounding
Schneider   system groundingSchneider   system grounding
Schneider system grounding
 
Voltage support to grid under unbalance rodriguje
Voltage support to grid under unbalance rodrigujeVoltage support to grid under unbalance rodriguje
Voltage support to grid under unbalance rodriguje
 
Pq unit ii
Pq unit iiPq unit ii
Pq unit ii
 
Out of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit BreakersOut of phase current switching in High Voltage Circuit Breakers
Out of phase current switching in High Voltage Circuit Breakers
 
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
ENHANCING RELIABILITY BY RECONFIGURATION OF POWER DISTRIBUTION SYSTEMS CONSID...
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdf
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdfH7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdf
H7 SHORT-CIRCUIT EMERSON EDUARDO RODRIGUES.pdf
 
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
A Load Shedding Scheme Based On Frequency Response Model With Fast Voltage St...
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
Bp36398403
Bp36398403Bp36398403
Bp36398403
 
Protection of Converter Dense Power Systems
Protection of Converter Dense Power Systems Protection of Converter Dense Power Systems
Protection of Converter Dense Power Systems
 
lecture1423723756.pdf
lecture1423723756.pdflecture1423723756.pdf
lecture1423723756.pdf
 
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...
MITIGATION OF UNBALANCED FAULTS IN DISTRIBUTION SYSTEM USING FD-STATCOM WITH ...
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
 
Power Quality Enhancement in Power System Network using DSTACOM
Power Quality Enhancement in Power System Network using DSTACOMPower Quality Enhancement in Power System Network using DSTACOM
Power Quality Enhancement in Power System Network using DSTACOM
 
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion SystemIRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
IRJET- Low Volatge Ride through Solution for Wind Energy Conversion System
 

Último

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 

Último (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 

File 1 power system fault analysis

  • 1. SLIDE 1 AN INTRODUCTION TO POWER SYSTEM FAULT ANALYSIS
  • 2. SLIDE 2 INTRODUCTION A fault calculation is the analysis of the power system electrical behaviour under fault conditions, with particular reference to the effects on the system currents and voltages. Accurate fault calculations are essential for proper system design. The analysis of fault conditions and their effects on the power system is of particular relevance to such conditions as: a. the choice of a suitable power system arrangement, with particular reference to the configuration of the transmission or distribution network. b. the determination of the required load and short-circuit ratings of the power system plant. c. the determination of the breaking capacity required of the power system switchgear and fusegear. d. the design and application of equipment for the control and protection of the power system. e. the operation of the system, with particular reference to security of supply and economic considerations. f. the investigation of unsatisfactory performance of the power system or of individual items of power system plant.
  • 3. SLIDE 3 Types of Fault In the context of electrical fault calculations, a power system fault may be defined as any condition or abnormality of the system which involves the electrical failure of primary equipment, i.e. generators, transformers, busbars, overhead lines and cables and all other items of plant which operate at power system voltage. Electrical failure generally implies one of two conditions or types of failure (sometimes both), namely insulation failure resulting in a short-circuit condition or a conducting path failure resulting in an open-circuit condition, the former being by far the more common type of failure.
  • 4. SLIDE 4 a) Short-circuited phases Faults of this type are caused by insulation failure between phase conductors or between phase conductors and earth, or both. Figure 1 gives details of the various short-circuited-phase faults. Figure 1: Short-circuited-phase faults The three-phase fault, which may or may not be to earth, is the only balanced short-circuit condition and is the one used as the standard in determining the system fault levels or ratings.
  • 5. SLIDE 5 b) Open-circuited phases Faults of this type, see Figure 2, result in the failure of one or more phases to conduct. The more common causes of this type of fault are joint failures on overhead lines and cables, and the failure of circuit-breakers or isolators to close properly. Both the single-phase and the two- phase conditions are of particular interest because they tend to produce unbalance of the power system currents and voltages with the consequent risk of damage to rotating plant. Figure 2: Open-circuited phase faults
  • 6. SLIDE 6 c) Simultaneous faults A simultaneous fault condition, or a multiple fault condition, is defined as the simultaneous presence of two or more faults which may be of similar or dissimilar types and may be at the same or different points in the power system. The most common simultaneous fault condition is undoubtedly the double-circuit overhead line fault in which a common cause, i.e. lightning or clashing conductors, results in a fault on each of the two circuits concerned. Another simultaneous fault condition is known as the cross-country earth-fault, in which a single-phase to earth fault at one point occurs coincidentally with a second such fault on another phase at some other point in the system.
  • 7. SLIDE 7 d) Winding faults This type of fault, which can occur in machine or transformer windings, is detailed in Figure 3, and consists mainly of short circuits, from one phase to earth, or from phase to phase, or from one point to another on the same phase winding. The last fault condition is known as the short-circuited turns fault. This condition can pose special problems from a protection point of view because the current in the shorted turns can be very large, while that in the remainder of the winding may be quite small. The open-circuited winding condition is quite rare in practice and is usually the result of damage to the winding as a consequence of a preceding winding short circuit at or near the point of fault. Open circuits in transformers may also occur as a result of failure of tap-changing equipment. Phase-to-earth fault Phase-to-phase fault Short-circuited turns Open-circuited winding Figure 3. Winding faults
  • 8. SLIDE 8 Factors Affecting Fault Severity The severity of a power system fault condition may be assessed in terms of the disturbance produced and the fault damage caused, the magnitude of the fault current and its duration being of particular interest, especially in relation to the design and application of the power system protection. The main factors which affect the severity of a fault are: a) Source conditions These relate to the amount and location of all connected generation equipment - including the ties or interconnections with other systems, the two extremes of minimum and maximum connected plant being of particular interest. The minimum and maximum plant conditions are normally those corresponding to the conditions of minimum and maximum connected load.
  • 9. SLIDE 9 b) Power system configuration This is determined by the items of plant, i.e. generators, transformers, overhead lines and cable circuits, etc., assumed to be in service for the particular condition being investigated and by other such factors as may have a bearing on the make-up of the equivalent circuit of the system. The system configuration may change during the course of a fault with consequent changes in the magnitude and distribution of the fault currents. Typical causes of the above changes being the sequential tripping of the circuit-breakers at the two ends of the faulted transmission line and the sequential clearance of multiple fault conditions.
  • 10. SLIDE 10 c) Neutral earthing Faults which involve the flow of earth current, i.e. phase faults to earth, may be influenced considerably by the system neutral earthing arrangements, particularly by the number of neutral earthing points and the presence or absence of neutral earthing impedance. The power system may be single-point or multiple-point earthed and such earthing may be direct, i.e. solid earthing, or via a neutral impedance. The 132kV, 275kV and the 400kV systems employ direct multiple earthing while the 66kV and below generally employ single-point, sometimes multiple, resistance earthing.
  • 11. SLIDE 11 d) Nature and type of fault From what has been said already, it is evident that the type and location of a fault will have a significant effect on the magnitude and distribution of the system fault currents. Likewise, the effect of a given fault condition may be considerably modified by the simultaneous presence of one or more other fault conditions, for example, the combination of a short circuit and an open-circuited phase condition.
  • 12. SLIDE 12 The wide range of possible system fault conditions and the many factors which influence them result in a wide range of possible fault severity, ranging from very low levels up to the maximum level possible for the system. It is of value to consider a standard fault condition when discussing systems and the three-phase fault level may be expressed in amperes but it is usually expressed in MVA, corresponding to the rated system voltage and the current for a symmetrical three-phase fault. This three-phase fault level normally determines the required short-circuit rating of the power system switchgear. A factor which may also have to be taken into account is the maximum value of the one-phase to earth fault current which, in a solidly earthed system, may exceed the maximum three-phase fault current.
  • 13. SLIDE 13 Methods of Fault Calculation ♦ The information normally required from a fault calculation is that which gives the values of the currents and voltages at stated points in the power system when a given fault condition is imposed on the system. ♦ A fault calculation is therefore, essentially a matter of network analysis and can be achieved by a number of methods, i.e. mesh- current or nodal-voltage methods, network reduction techniques or simulation using a network analyser. ♦ The choice of method depends on the size and complexity of the circuit model and the availability of computing facilities.
  • 14. SLIDE 14 Methods of Fault Calculation ♦ An essential part of power system analysis and fault calculation is that which concerns the determination of the equivalent system network for the system operating conditions and the fault conditions under consideration. ♦ As stated earlier, faults can be subdivided into either balanced (symmetrical) or unbalanced (unsymmetrical) fault conditions, this latter case being analysed, traditionally, by the method of symmetrical components. ♦ Both classes of fault are analysed by reducing the power system, with its fault condition, to an equivalent single-phase network.
  • 15. SLIDE 15 Balanced Faults The balanced fault is often the severest and is the simplest to determine. Hence, this is the one normally used to determine the 'duty' of the system switchgear and busbars Fault Calculation Procedure The analysis of a 3-phase balanced fault condition consists, in general, of three parts: a. the system with its fault condition is represented by its positive sequence network, b. the network is solved in terms of per-unit quantities, c. the resulting per-unit quantities are converted to actual values. Component Representation Overhead lines and cables are normally represented by their series impedance on the basis that the shunt impedance is high. Transformers and synchronous machines are normally represented by their reactances as the resistance values are relatively small. Load impedances are normally much larger than the other network impedances and hence, they are normally neglected in fault calculations.
  • 16. SLIDE 16 THREE PHASE FAULTS The following example is presented to illustrate the methods employed for the case which induces positive sequence components only. The system shown represents a power station connected to the grid, together with its auxiliary systems. The principle circuit and plant parameters are given in Table 1.
  • 17. SLIDE 17 G2/3 G Inf bus Bus 1 T2/T3 G1 ∆ ∆ T1 T4 T5 M2 03BBus 203A M1 T6 T7 M3 M4 L L MCC2 Bus 3 Bus 4 MCC1 ∆ ∆ ∆ ∆ ∆ A fault is assumed to occur first on busbar MCC1 and secondly on busbar MCC2. The fault level quoted on Bus 1 is 2500 MVA. Example
  • 18. SLIDE 18 G2/3 71 MVA, X = 263 pu on 100 MVA T2/T3 71 MVA, Xl = 009pu G (2500-147-71)MVA G1 147 MVA, Xd = 1867 pu T1 150 MVA, Xl = 013 pu T4 16 MVA, Xl = 01 pu T5 16 MVA, Xl = 009 pu T6 2 MVA, Xl = 006 pu T7 4 MVA, Xl - 006 pu M1 88 MVA M2 806 MVA M3 1247 MVA M4 0977 MVA SL 0918 MW, 09 p.f. Table 1
  • 19. SLIDE 19 grid infeed 100 2500 147 71( )− − = ·438 Base 100 MVA 71 MVA generation 2·63 (given) 100 09 71 127 × ⋅ = ⋅ 147 MVA generator 100 1 867 147 1 27 × ⋅ = ⋅ 100 13 150 08 × ⋅ = ⋅ 100 1 16 625 × ⋅ = ⋅ 03B 03A 100 09 16 5625 × ⋅ = ⋅ MCC2 MCC1 100 06 2 3 × ⋅ = 100 06 4 1 5 × ⋅ = ⋅ N.B. 2x2 MVA Transformers in parallel 3 1 2 Normalised system reactances on equivalent circuit
  • 20. SLIDE 20 Using the Star Delta Transform to simplify the above circuit
  • 23. SLIDE 23 The resolution of the problem into sequence components results in considerable simplification of all problems involving asymmetry such as that introduced by short- circuiting conductors of a system either together or to earth, singly or in pairs, or by the open circuiting of a conductor. The resolution of the problem into sequence components has the further advantage in that it isolates the quantities into components which represent a better criteria of the controlling factor or factors in certain phenomena. Consider the following system of vectors shown below.
  • 24. SLIDE 24 A graphic vectorial representation is not tractable when dealing with complex practical systems. Consider the vector equations in which , are written in terms of the positive, negative and zero sequence components . (1)
  • 25. SLIDE 25 Rewriting equation (1), and for convenience neglecting the bar denoting vector quantities Va = Va1 + Va2 + Va0 Vb = λ2 Va1 + λVa2 + Va0 (2) Vc = λVa1 + λ2 Va2 + Va0 and Va0, Va1 and Va2 may now be written as V0, V1 and V2 where λ is an operator which moves a vector 120° anticlockwise, i.e. λ = 0.5 + 0.886j λ2 = - 0.5 – 0.886j (3) λ3 = 1 Other useful identities in are given in the following Table 1. Table 1
  • 26. SLIDE 26 The transformation of phase quantities to sequence and reverse is given by [Vph] = [T] [Vseq] and [Vseq] = [T] -1 [Vph] where [T] = (4) and [T] -1 = (5)
  • 28. SLIDE 28 For example, consider the network shown in the figure below It follows that [ ] [ ][ ]           =           2 1 0 2 1 0 I I I TZ V V V T
  • 29. SLIDE 29 premultiplying equation (7) by [T] -1 the following sequence component equations are obtained. [ ] [ ][ ]           =           − 2 1 0 1 2 1 0 I I I TZT V V V
  • 30. SLIDE 30 Evaluating the term [T]-1 [Z] [T] defines the sequence impedances [T]-1 [Z] [T] (9)
  • 31. SLIDE 31 N.B. The transformation diagonalises the impedance matrix, in which Z1 = Z2, i.e. positive and negative sequence impedances are equal. The sequence currents are obtained from: (10) Now consider the case where the circuit impedances are of the form possible distribution for an electrical machine
  • 32. SLIDE 32 (11) resulting in sequence impedances of different values.
  • 33. SLIDE 33 Example An untransposed transmission line gives rise to 3 per cent negative sequence voltage. Show approximately how this affects the magnitudes of the terminal voltages of the generator supplying the system. No zero sequences voltage; let V2 = 0⋅03 V1 Va = V1 + 0⋅03V1 = (1 + 0⋅03)V1 Vb = λ2 V1 + λ0⋅03V1 = (λ2 + 0⋅03λ)V1 Vc = λV1 + λ2 0⋅03V1 = (λ + 0⋅03λ2 )V1
  • 36. SLIDE 36 Components of voltage VA = 0 and since the generator is only able to generate positive sequence components, E0 = E2 = 0 Also, since IB = IC = 0, I0 = I2 = 0 021 1 1 ZZZ E I ++ =
  • 37. SLIDE 37 The fault current If = IA = 3I1 where E is the generated phase voltage. The equivalent circuit is given by 021 f ZZZ E3 I ++ =
  • 38. SLIDE 38 Example X1 = 0⋅2j pu X2 = 0⋅1j pu X0 = 0⋅05j pu Consider an earth fault at B Choose base of 75 MVA, VB = 33 kV
  • 40. SLIDE 40 The next stage is to draw a sequence diagram. For the single phase to earth fault, the positive, negative and zero sequence diagrams are connected in series.
  • 41. SLIDE 41 = -j3·49 kA The fault current may be reduced by increasing the impedance to the fault. Using the data of the above example, consider the effect of earthing only one generator.
  • 43. SLIDE 43 Consider placing an impedance in the earth path as shown in Figure 12. Figure 12 N.B. Zero sequence components only flow in the earth path. ∴ Zero sequence network becomes Figure 13
  • 45. SLIDE 45 The sequence diagram becomes I0 = I1 = I2 I1 = (0⋅621 - 1⋅19j) If = 3 x (0⋅621 - 1⋅19j) x = 2⋅93(0⋅621 - 1⋅19j) kA
  • 46. SLIDE 46 Too large a fault current can cause problems, nevertheless the fault current must be sufficient to be detected by protection. However, before proceeding further, the effect of the transformer windings on the flow of zero sequence currents must be assessed.
  • 47. SLIDE 47 Shown below are three connection diagrams for power transformers Star / Star, primary and secondary windings earthed I0 will flow in primary and secondary circuits Star / Star, primary winding earthed, secondary unearthed I0 cannot flow in secondary circuit Star / Delta, primary winding earthed I0 flows in primary and circulated in the secondary
  • 48. SLIDE 48 Shown below are the three equivalent circuits corresponding to the previous connection diagrams for the power transformers.
  • 49. SLIDE 49 Shown below is the equivalent circuit for a three-winding transformer
  • 50. SLIDE 50 Returning to the example and considering only the zero sequence diagram The zero sequence impedance has been increased by Z0(trans) and therefore, If will be less.
  • 51. SLIDE 51 Consider the / transformer replaced by a Δ/ . Zero sequence diagram: The RN is now out of circuit for an end of line fault. However, its effect is seen for a fault at the generator terminals. If will now rise as compared to previous case.
  • 52. SLIDE 52 NONE OF CONFIGURATIONS AFFECT THE POSITIVE AND NEGATIVE SEQUENCE NETWORKS A further modification involves the inclusion of second transformer The Zero sequence diagram becomes
  • 53. SLIDE 53 PRACTICAL FAULT STUDIES As previously stated, power systems are subject to excessive damage when high magnitude currents are flowing due to system short circuit. The analysis so far has been confined to steady-state conditions arising subsequent to fault incidence. The initial transient condition has been neglected which, for many practical situations, is considered to be satisfactory. However, the instant of initiation of the short circuit relative to the voltage waveform, has a marked effect upon the maximum peak value of the short-circuit current which may be important from the point of view of fast acting fault clearance devices, i.e. does the circuit breaker operate prior to the decay of the transient component of the current.
  • 54. SLIDE 54 Consider the single phase equivalent circuit of a generator shown in Figure 26. Figure 26 If S is suddenly closed, the equation representing the equivalent circuit on a single phase basis is (43) The solution of which yields (44) where Z2 = r2 + ω2 L2 and tan φ = and (45)
  • 55. SLIDE 55 The total current is obtained by adding the steady-state and the transient components.
  • 56. SLIDE 56 In practice, the time variation of the short circuit current is dependent on the actual characteristic of the generator. To a close approximation, the short circuit current can be allocated to the following categories: 1. the continuous component 2. the transient component 3. the subtransient component These categories are determined by the electromagnetic process that occurs in the generator. For most fault studies, the representation and calculation of the short circuit characteristics are based on a constant voltage and on the assumption that the decay of the ac short-circuit current is due to an increase in the generator reactances from (1) the subtransient reactance Xd" to (2) the transient reactance Xd' and finally (3) the synchronous reactance Xd
  • 57. SLIDE 57 Therefore, the fault current for the three conditions may be calculated as: ; ; If this approximation is acceptable, then the analysis previously developed is applicable by merely using the appropriate value of generator impedance. Otherwise, a full system transient analysis is required which involves considerable computing time.
  • 58. SLIDE 58 Synchronous and Induction Motor Loads For a short-circuit period of T ≤ 0·2s, synchronous motors can be treated in the same manner as synchronous generators. In a larger short-circuit period, the machine is subjected to a speed drop and is then operating in an assynchronous mode. High and low voltage motors similarly make a contribution to the short-circuit current. However, due to differences in their construction, this contribution decays very rapidly. Short-circuit analysis is generally preceded by data collection and the preparation of a one-line diagram, followed by the determination of the exact objectives of the study. Table 2 gives an indication of parameter values to be used under certain circumstances.