Step by step configuration procedures for SAP MM module.. Screenshots, menu paths and descriptions provided
http://sapdocs.info/sap/materials-management-2/sap-mm-configuration-a-real-life-project-documentation/
2. Project Shield
configuration Document
Page 2 of 182
TABLE OF CONTENTS: Page No
1. Enterprise Structure – Definition: --------------------------------------------------------------------------07-27
1.1 Logistics – General
1.1.1 Define valuation level
1.1.2 Define, copy, delete, check plant
1.2 Materials Management
1.2.1 Maintain storage location
1.2.2 Maintain purchasing organization
2. Enterprise Structure – Assignment :-------------------------------------------------------------------------27-32
2.1 Logistics - General
2.1.1 Assign plant to company code
2.2 Materials Management
2.2.1 Assign purchasing organization to company code
2.2.2 Assign purchasing organization to plant
3. Logistics – General:-----------------------------------------------------------------------------------------------33-42
3.1 Material Master
3.1.1 Assign Screen Sequences to User/Material Type/Transaction/Industry Sector
3.2 Material Types
3.2.1 Define Attributes of Material Types
3.2.2 Define Number Ranges for Each Material Type
3.3 Settings for Key Fields
3.3.1 Define Material Groups
3.3.2 Define Divisions
3.4 Business Partner
3.4.1 Vendors - Define Account Groups and Field Selection (Vendor)
3.4.2 Vendors- Define Number Ranges for Vendor Master Records
4. Materials Management:
4.1 Purchasing----------------------------------------------------------------------------------------------------43-117
4.1.1 Environment Data
4.1.1.1 - Define Attributes of System Messages
4.1.1.2 Define Default Values for Buyers
4.1.2 Material Master
4.1.2.1 Define Shipping Instructions
4.1.2.2 Define Purchasing Value Keys
4.1.3 Vendor Master
4.1.3.1 Define Terms of Payment
4.1.3.2 Check Incoterms
4.1.4 Create Purchasing Groups
4.1.5 Purchasing Info Record
3. Project Shield
configuration Document
Page 3 of 182
4.1.5.1 Define Number Ranges
4.1.6 Quota Arrangement
4.1.6.1 Define Number Ranges
4.1.6.2 Define Quota Arrangement Usage
4.1.7 RFQ/Quotation
4.1.7.1 Define Document Types
4.1.7.2 Define Number Ranges
4.1.7.3 Release Procedure
4.1.8 Purchase Requisition
4.1.8.1 Define Document Types
4.1.8.2 Define Number Ranges
4.1.9 Purchase Order
4.1.9.1 Define Document Types
4.1.9.2 Define Number Ranges
4.1.9.3 Release Procedure
4.1.9.4 Set Tolerance Limits for Price Variance
4.1.9.5 Texts for Purchase Orders
4.1.9.6 Set up Stock Transport Order
4.1.9.7 Returns Order
4.1.10 Contract
4.1.10.1 Define Document Types
4.1.10.2 Define Number Ranges
4.1.10.3 Release Procedure
4.1.11 Scheduling Agreement
4.1.11.1 Define Document Types
4.1.11.2 Define Number Ranges
4.1.12 Conditions
4.1.12.1 Define Price Determination Process
4.1.12.1.1 Define Access Sequences
4.1.12.1.2 Define Condition Types
4.1.12.1.3 Define Calculation Schema
4.1.12.1.4 Define Schema Group
4.1.12.1.5 Define Schema Determination
4.1.12.1.6 Define Transaction/Event Keys
4.1.13 Account Assignment
4.1.13.1 Maintain Account Assignment Categories
4.1.14 Define Default Values for Document Type
4.1.15 Version Management
4.1.15.1 Set Up Version Management for Purchase Requisitions
4.1.15.2 Set Up Version Management for External Purchasing Documents
4.1.15.3 Define Reasons for Change
4. Project Shield
configuration Document
Page 4 of 182
4.1.16 Vendor Evaluation
4.1.16.1 Define Weighting Keys
4.1.16.2 Define Criteria
4.1.16.3 Define Scope of List
4.1.16.4 Maintain Purchasing Organization Data
4.2 External Services Management -----------------------------------------------------------------------108-111
4.2.1 Service Master
4.2.1.1 Define Service Category
4.2.1.2 Define Number Ranges
4.2.2 Number Ranges
4.2.2.1.1 Define Number Ranges for Service Entry Sheet
4.2.2.1.2 Define Internal Number Range for Service Specifications
4.2.2.1.3 Assign Number Ranges
4.2.3 Define Attributes of System Messages
4.3 Inventory Management and Physical Inventory--------------------------------------------------112-124
4.3.1 Goods Issue / Transfer Postings
4.3.1.1 Create Storage Location Automatically
4.3.1.2 Set Up Dynamic Availability Check
4.3.2 Goods Receipt
4.3.2.1 Set Tolerance Limits
4.3.2.2 Create Purchase Order Automatically
4.3.2.3 Set "Delivery Completed" Indicator
4.3.3 Reservation
4.3.3.1 Define Default Values
4.3.4 Physical Inventory
4.3.4.1 Cycle Counting
4.3.5 Movement Types
4.3.5.1 Record Reason for Goods Movements
4.3.6 Output Determination
4.3.6.1 Maintain Condition Tables
4.3.6.2 Maintain Access Sequences
4.3.6.3 Maintain Output Types
4.3.6.4 Maintain Output Determination Procedures
4.3.6.5 Maintain Conditions
4.4 Valuation and Account Assignment------------------------------------------------------------------125-139
4.4.1 Define Price Control for Material Types
4.4.2 Split Valuation
4.4.2.1 Activate Split Valuation
4.4.2.2 Configure Split Valuation
4.4.3 Account Determination
4.4.3.1 Account Determination Without Wizard
5. Project Shield
configuration Document
Page 5 of 182
4.4.3.1.1 Define Valuation Control
4.4.3.1.2 Define Valuation Classes
4.4.3.1.3 Configure Automatic Postings
4.5 Logistics Invoice Verification--------------------------------------------------------------------------140-145
4.5.1 Define Attributes of System Messages
4.5.2 Incoming Invoice
4.5.2.1 Number Assignment
4.5.2.1.1 Maintain Number Assignments for Accounting Documents
4.5.2.1.2 Maintain Number Assignment for Logistics Documents
4.5.2.1.2.1 Transaction - Assign Number Range
4.5.2.1.2.2 Maintain Number Range Intervals for Invoice Documents
4.5.3 Maintain Default Values for Tax Codes
4.5.4 Invoice Block
4.5.4.1 Determine Payment Block
4.5.4.2 Set Tolerance Limits
4.6 Consumption-Based Planning ------------------------------------------------------------------------146-146
4.6.1 Master Data
4.6.1.1 Define MRP Controllers
5. Financial Accounting (New) [ TAXINN-Condition based Procedure]-------------------------147-157
5.1 Tax on Sales/Purchases
5.1.1 Basic Settings
5.1.1.1 Check Calculation Procedure
a) Access Sequences
b) Define Condition Types
c) Define Procedures
5.1.1.2 Assign Country to Calculation Procedure
5.1.1.3 Check and Change Settings for Tax Processing
5.2 Calculation
5.2.1 Define Tax Codes for Sales and Purchases
5.3 Posting
5.3.1 Define Tax Accounts
6. Logistics – General [Country India Version-CIN Settings] :-----------------------------157-182
6.1 Tax on Goods Movements [India]
6.1.1 Basic Settings
6.1.1.1 Maintain Excise Registrations
6.1.1.2 Maintain Company Code Settings
6.1.1.3 Maintain Plant Settings
6.1.1.4 Maintain Excise Groups
6.1.1.5 Maintain Series Groups
6.1.2 Determination of Excise Duty
6.1.2.1 Select Tax Calculation Procedure
6. Project Shield
configuration Document
Page 6 of 182
6.1.2.2 Maintain Excise Defaults
6.1.3 Condition-Based Excise Determination
6.1.3.1 Define Tax Code for Purchasing Documents
6.1.3.2 Assign Tax Code to Company Codes
6.1.3.3 Classify Condition Types
6.1.4 Master Data
6.1.4.1 Assign Users to Material Master Screen Sequence for Excise Duty
6.1.4.2 Maintain Chapter IDs
6.1.5 Account Determination
6.1.5.1 Define G/L Accounts for Taxes
6.1.5.2 Specify Excise Accounts per Excise Transaction
6.1.5.3 Specify G/L Accounts per Excise Transaction
6.1.6 Business Transactions
6.1.6.1 Incoming Excise Invoices
6.1.6.1.1 Maintain Rejection Codes
6.1.6.1.2 Specify Which Movement Types Involve Excise Invoices
6.1.7 Outgoing Excise Invoices
6.1.7.1 Assign Billing Types to Delivery Types
6.1.7.2 Maintain Default Excise Groups and Series Groups
6.1.8 Subcontracting
6.1.8.1 Maintain Movement Type Groups
6.1.8.2 Subcontracting Attributes
6.1.9 Tools
6.1.9.1 Number Ranges
6.1.9.2 Message Control
---------------------------------------------------------------------------------------------------------------------------------------
7. Enterprise structure Related to Materials Management
Definition
Define valuation level
SPRO Enterprise Structure Definition
For GMR – Valuation level is defined at Plant Level.
Define, copy, delete, check plant
SPRO / IMG -> Enterprise Structure
check plant
Project Shield
configuration Document
Page 7 of 182
structure Related to Materials Management
Definition Logistic General Define Valuation Level
Valuation level is defined at Plant Level.
Define, copy, delete, check plant
> Enterprise Structure -> Definition -> Logistics General -> Define copy delete
structure Related to Materials Management
Define Valuation Level
> Define copy delete
8. Project Shield
configuration Document
Page 8 of 182
Following plants are defined for GMR.
2000 GMR Energy Limited
2001 Kamalanga Thermal Power Projec
2002 Talong
2003 Bajoli Holi
2004 GMR Energy Limited(Corp Off)
2005 GMR Enegry Ltd (Delhi Off )
2100 GMR Power Corporation Pvt Ltd
2101 HYUNDAI HEAVY IND. CO.LTD. C/O. GMR POWER CORP.
2150 Vemagiri Power Generation Ltd
2151 Korea Plant Service & Eng Co L
2200 GMR Hydro Power Gen Pvt Ltd
3110 GMR T.T EXPRESSWAYS PVT LTD
3120 GMR Tuni Anakapali Exp Pvt Ltd
3130 GMR Pochanpalli Exp Pvt Ltd
3210 GMR Ambala-Chand Exp Pvt Ltd
3220 GMR Jadcherla Exp.ways Pvt Ltd
3230 GMR Ulundurpet Exp Pvt Ltd
3310 GMR PROJECTS PVT.LTD.
4001 GMR Ind.Ltd,Sugar Div,Sankili Sugar Division- SANKILI
4002 GMR Ind.Ltd,Co-gen Div,Sankili Co-Gen Division - SANKILI
4003 GMR Ind.Ltd,Dist Div,Sankili Distillery Division-SANKILI
4011 GMR Ind.Ltd,Sugar Div,Haliyal Sugar Division - HALIYAL
10. Project Shield
configuration Document
Page 10 of 182
Following storage location are defined for GMR.
PLANT SLOC DESCRIPTION
2000 ACST A/C Stores
2000 ADST Admin Stores
2000 ASTA Bulk Acid ST- A
2000 ASTB Bulk Acid ST- B
2000 CHTR Chlor tonner Rm
2000 COCR CO2 Cyl(Cntrl Rm
2000 COGT CO2 Cyl(GTG)
2000 CSTA Bulk Castic ST-A
2000 CSTB Bulk Castic ST-B
2000 ELST Elec Maint Store
2000 FST1 Fuel Stor Tank
2000 INST Instr Maint Stor
2000 LOSC Lube Oil Scrap
2000 MESC Metal Scrap Yard
2000 MEST Mech Maint Stor
2000 NEWH New Warehouse
2000 NMSC Non-Metalic Scrp
2000 NTFL Nitrogen Cyl(FH)
2000 NTST Nitrogen Cyl(STG
2000 OLWH Old Warehouse
2000 OPST Operation Stores
2000 OPYD Open Yard
11. Project Shield
configuration Document
Page 11 of 182
2000 RHST Raw HSD Tank
2000 RNT1 Raw Naphta Tank1
2000 RNT2 Raw Naphta Tank2
2000 SAST Safety Stores
2000 THST HSD Trt Stor Tan
2001 PK1
2002 PT1
2003 PBH1
2004 PB1
2005 PD1
2100 101A Tank 101-A
2100 101B Tank 101-B
2100 102A Tank 102-A
2100 102B Tank 102-B
2100 201A Cyl Lube oil - A
2100 201B Cyl Lube oil - B
2100 ACST Sul Acid ST
2100 ADST Admin Store
2100 CHTR Chl tonner SA
2100 CLST Service Tank
2100 CTCH Cooling Tower SA
2100 FLT8 Fuel tank - 8
2100 FLT9 Fuel tank - 9
2100 HYST Hyd Lime St Area
12. Project Shield
configuration Document
Page 12 of 182
2100 MAST Main Store
2100 MLST Tank 200
2100 OMST O&M Store
2100 SCYD Scrap Yard
2100 STCH STP Chem Store
2100 T104 LDO Tank
2100 T108 HSD Tank
2100 T200 System Oil
2100 T205 Talusia
2100 T600 Oil sludge ST
2100 T601 Sep Oil Sludg ST
2100 ULOS Used Lube Oil
2101 ENGE Engine Room
2101 OMST O&M Store
2150 ACST A/C Stores
2150 ACWA BAST-A(CW PLANT)
2150 ACWB BAST-B(CW PLANT)
2150 ADST GMR Admn Store
2150 ARSH Argonite Shed
2150 ASTA BAST-A(DM PLANT)
2150 ASTB BAST-B(DM PLANT)
2150 CHEM Chemical Lab
2150 CHTR Chl Stor Yard
2150 CMHS Chemical House
13. Project Shield
configuration Document
Page 13 of 182
2150 CNTR Containers (8 no
2150 COGT CO2 Tank for GTG
2150 COSH CO2 Cyl Shed GTG
2150 CSTA BCST Tank - A
2150 CSTB BCST Tank - B
2150 ELEC Electrical Lab
2150 HKST House Keep Store
2150 HYSH Hydrogen Shed
2150 INST Instrumentation
2150 LOTR Tran.oil yard
2150 MESC Metal Scrap Yard
2150 NTBL Nit Cyl HRSG
2150 NTFL Nit Cyl Fuel Han
2150 OPYD Open Yard
2150 SAST Safety Stores
2150 WHSE Ware House
2151 OMST O&M Store
2200 PA1
3100 RS01 TAMBARAM-TINDIVA
3120 RS02 Tuni-Anakapalli
3130 RS03 Pochanpalli
3210 RS04 Ambala-Chandigar
3220 RS05 Jadcherla
14. Project Shield
configuration Document
Page 14 of 182
3230 RS06 Ulundurpet
3310 RS07 GMR Projects
4001 FR10 FERT- PALAKONDA
4001 FR11 R.A.VALASA - 1
4001 FR12 R.A.VALASA - 2
4001 FRT1 FERT-MAIN STORE
4001 FRT2 FERT-KOTTURU
4001 FRT3 FERT-VEERAGATAM
4001 FRT4 FERT-VANGARA
4001 FRT5 FERT - RAJAM
4001 FRT6 FERT - CHEEPURUP
4001 FRT7 FERT - DEVADI
4001 FRT8 FERT - RANASTHAL
4001 FRT9 FERT - GARA
4001 SC01 Com Mat - Mech
4001 SC02 Com Mat - Elec
4001 SC03 Com Mat - Proces
4001 SC31 Torr Steels
4001 SC32 Structural Mat
4001 SC33 Metal Steels
4001 SC35 Pipes 1
4001 SC36 Pipes 2
4001 SC37 Pipes 3
4001 SC39 Oil & Fuel Stor
15. Project Shield
configuration Document
Page 15 of 182
4001 SC40 Diesel Bunk
4001 SC41 Gas1-Oxygen
4001 SC42 Gas2-D.A Others
4001 SC43 Gas3 - Empty
4001 SC45 Chemicals
4001 SC90 Rejected Mat
4001 SC95 Scrap Material
4001 SC99 Statry/EDP Mat
4001 SCRP SCRAP MATERIAL
4001 SCRT CUSTOMER RETURNS
4001 SFG1 SUGAR FG 1A & 1B
4001 SFG2 SUGAR FG 2A & 2B
4001 SFUL SUGAR FUELS
4001 SML1 MOLASSES TANK 1
4001 SML2 MOLASSES TANK 2
4001 SML3 MOLASSES TANK 3
4001 SRMS SUGAR RAW MAT
4001 SS01 Sugar Mat - Mech
4001 SS02 Sugar Mat - Elec
4001 SS03 Sugar Mat - Proc
4001 SS71 FG Storage 1
4001 SS72 FG Storage 2
4001 SS73 FG Storage 3
4001 SS74 FG Storage 4
25. Project Shield
configuration Document
Page 25 of 182
4013 HD81 Coal Yard
4013 HD82 Husk Yard
4013 HD83 Bagrasse Yard
4013 HD84 Ash Storage
4013 HD87 Buffer Tank - 1
4013 HD88 Buffer Tank - 2
4013 HD89 Lagoon - 1
4013 HD90 Lagoon - 2
4013 HD92 Sump
4013 HD93 Leachate Pit
4013 HD94 Bio-Compost Yard
4013 HD95 Scrap Material
4013 HD96 Bio-Fert Storage
4013 HD98 Prod Storage
4098 AVST Aviation St Loc
4099 CR01 Stainary/EDP Mat
5010 PR01 GMRPPL
5010 PR02 DAPL
6600 FMS1 Skip House
6600 FMS2 King Street 1
6600 FMS3 King Street 2
6600 FMS4 MTB
6600 FMS5 SBM
6600 FMS6 HMG
26. Project Shield
configuration Document
Page 26 of 182
6600 FMS7 IBCKP-10/11Floor
8000 RX01 Uniforms
8000 RX02 Arms & Weapons
8100 1 Location 0001
8100 88 Lager 0088 (WM)
8100 100 Lagerort WM&HU
8100 200 SCM-EWM
8601 VF01 Estates & Hostel
8602 VF02 GMRVF-GMRIT-ENGG
8603 1 Location 0001
8603 VF03 GMRIT-P.G.DIPLOM
8604 VF04 SGCSRC-UG&PG
8605 VF05 SGCSRC-B.Ed
8606 VF06 CSW-RAJAM
8607 VF07 CORPORATE
Maintain purchasing organization
In this step, you set up your purchasing organizations. From the Materials Management and
purchasing view, the purchasing organization is responsible for the complete processing of
purchasing activities (such as requests for quotations, purchase orders & Scheduling
Agreements).
Path: SPRO / IMG -> Enterprise Structure -> Definition -> Materials Management-> Maintain
purchasing organization
27. Project Shield
configuration Document
Page 27 of 182
ASSIGNMENT
Assign plant to company code
In the step "Assign plant to company code"; you assign each plant to a company code. A Plant
can only belong to one company code.
SPRO / IMG -> Assignment -> Logistics – General-> Assign plant to company code
Co code Plant Name of the plant Company name
2000 2000 GMR Energy Limited GMR Energy Limited
2000 2001 Kamalanga Thermal Power Projec GMR Energy Limited
2000 2002 Talong GMR Energy Limited
2000 2003 Bajoli Holi GMR Energy Limited
2000 2004 GMR Energy Limited(Corp Off) GMR Energy Limited
2000 2005 GMR Enegry Ltd (Delhi Off ) GMR Energy Limited
2100 2100 GMR Power Corporation Pvt Ltd GMR Power Corporation
2100 2101 HYUNDAI HEAVY IND. CO.LTD. GMR Power Corporation
2150 2150 Vemagiri Power Generation Ltd Vemagiri Power Generation
29. Project Shield
configuration Document
Page 29 of 182
8600 8603 GMRVF-GMRIT-P.G.DIPLOMA GMR Varalakshmi Foundtn
8600 8604 GMRVF-SGCSRC-UG&PG GMR Varalakshmi Foundtn
8600 8605 GMRVF-SGCSRC-B.Ed GMR Varalakshmi Foundtn
8600 8606 GMRVF-CSW-RAJAM GMR Varalakshmi Foundtn
Assign purchasing organization to company code
In this Implementation Guide (IMG) activity, you assign purchasing organizations to company codes
SPRO / IMG -> Assignment -> Materials Management-->Assign purchasing organization to
company code
Assign purchasing organization to plant :
SPRO Assignment Materials Management Assign purchasing organization to plant
In this IMG activity, you assign purchasing organizations to the plants for which they
are responsible.
Porg Description Plant Name1
2000 Energy Pur Org 2000 GMR Energy Limited
2000 Energy Pur Org 2001 Kamalanga Thermal Power Projec
2000 Energy Pur Org 2002 Talong
2000 Energy Pur Org 2003 Bajoli Holi
2000 Energy Pur Org 2004 GMR Energy Limited(Corp Off)
2000 Energy Pur Org 2005 GMR Enegry Ltd (Delhi Off )
2000 Energy Pur Org 2006
2000 Energy Pur Org 2100 GMR Power Corporation Pvt Ltd
2000 Energy Pur Org 2150 Vemagiri Power Generation Ltd
2000 Energy Pur Org 2200 GMR Hydro Power Gen Pvt Ltd
2101 Pur Org for HHI 2101 HYUNDAI HEAVY IND. CO.LTD.
2151 Pur org for KPS 2151 Korea Plant Service
3000 Roads Pur Org 3110 GMR T.T EXPRESSWAYS PVT LTD
3000 Roads Pur Org 3120 GMR Tuni Anakapali Exp Pvt Ltd
33. Project Shield
configuration Document
Page 33 of 182
Logistic General : Material Master
Materials Management---Logistics – General
SPRO Logistics - General Configuring the Material Master Assign Screen Sequences to
User/Material Type/Transaction/Industry Sector
34. Project Shield
configuration Document
Page 34 of 182
Material Type
Refer following chart for various material type defined for GMR
SPRO / IMG -> Logistics - General -> Material Master Basic Settings-> Material Types Define
Attributes of Material Types
Mtyp Material Type Description
ZAWA Trading Goods
ZBYP By Product
ZCAP Capital Goods
ZDIN Service
ZERS Spare Parts
ZFRT Finished Product
ZHER Manufacturer Part
ZHIB Operating supplies
ZHLB Semifinished Product
ZHMI Production Resource/Tool
ZNBW Nonvaluated materials
ZPIP Pipeline materials
ZRBY Semifinished Product
ZROH Raw materials
ZSCM Scrap Materials
36. Project Shield
configuration Document
Page 36 of 182
SPRO Logistics - General - > Material Master Basic setting material type Define Number
Ranges for Each Material Type
External Number ranges Used
37. Project Shield
configuration Document
Page 37 of 182
Setting for key field
Material Group
In this IMG activity, you define material groups to group together materials with the same
attribute or purpose.
SPRO / IMG -> Logistics - General -> Material Master-> Settings for Key Fields Define
Material Groups
Various material groups have been defined as per GMR requirement.
Matl Group Matl Group Description
AUTOMOBL Automobiles
BULKMAT Bulk material
BYPRODUCT By - Products
CAPITEMS Capital Items
CEMENT Cement
CHEMICALS Chemicals
CIVSANIRR Civil, Santory & Irr
COMPRESSR Compressor
CONSTMAT Construction Materia
CONSULTCY Consultancy
CONTRLSYS Control system
ELECEQUIP Electrical Equipment
ELECSPARE Electrical Spares
ENGINE Engine
FERRUSMAT Ferrous materials
FINSHDGDS Finished Goods
FIRNSAFTY Fire and safety
FUELS Fuels
38. Project Shield
configuration Document
Page 38 of 182
GENCONSM General Consumables
GENEQUIP General Equipment
GENERATOR Generator
GENRLADMN General Administrati
INSCNTRSP Instrument & Control
INSTNELEC Instruments & Electr
INTRNFURN Interiors/Furnishing
ITHARDWRE IT Hardware
LABORATRY Laboratory
MECHEQUIP Mechanical Equipment
MECHSPARE Mechanical Spares
MOTORS Motors
NONFERMAT Non-Ferrous material
OFFSUPPLS Office supplies
PACKNGMAT Packing Materials
PROCSSMAT Process Materials
PROTSYS Protection system
PUMPS Pumps
RAWMATRLS Raw materials
REFAIRCON Refrig & Airconditon
RUBMATERL Rubber Materials
SCRAP Scrap Material
SECTYEQPT Security Equipment
SECTYUNFM Security Uniforms
39. Project Shield
configuration Document
Page 39 of 182
SEMIFDGDS Semi-finished goods
SERVICES Services
SOFTWARE Software
STEEL Steel
TOOLNTACK Tools & tackles
TURBINE Turbine
VESSELS Vessels
VLVPIPFIT Valves, Pipes and Fi
Divisions
SPRO / IMG -> Logistics - General -> Material Master-> Settings for Key Fields Define Divisions
Business Patner
SPRO / IMG -> Logistics - General -> Business Partner Vendors control Define Account Groups and
Field Selection (Vendor)
40. Project Shield
configuration Document
Page 40 of 182
Vendor - Define Vendor Account Group
Following vendor vendor groups are defined for GMR
Group Description
GDMV Domestic Vendor
GEMV Employee Vendor
GFEV Founder Employee Vendor
GGRO Grower Vendor
GHAR Harvesting Vendors
GIMV Import Vendor
GINT GMR Internal Group Companies
GONV One-time Vendor
GRPC Treasury Group Companies
GRXP One-time Vendor-Recruit Expens
GSRV Service Vendor
GSTV Stock Transfer Vendor
SPRO / IMG -> Logistics - General -> Business Partner Vendors controls Define Number Ranges for
Vendor Master Records
43. Project Shield
configuration Document
Page 43 of 182
Materials Management--Purchasing
Path: SPRO/IMG Materials Management Purchasing Environment Data Define Attributes of
System Messages System messages
Path: SPRO/IMG Materials Management Purchasing Environment Data Define Default Values
for Buyers
44. Project Shield
configuration Document
Page 44 of 182
SPRO/IMG Materials Management Purchasing Material Master Define Shipping Instructions
SPRO/IMG Materials Management Purchasing Material Master Define Purchasing Value Keys
Vendor Master
SPRO MaterialsManagement Purchasing Vendor Master Define Terms of Payment
In this step, you make the system settings that are relevant to the vendor master record from the Purchasing point of view.
Define Terms of Payment : Payment terms created as per GMR team requirement as follows.
payment Terms Description
G001 10% Advance against Bank Guarantee
G002 20% Advance against Bank Guarantee
G003 30% Advance against Bank Guarantee
G004 70% Payment Against Proforma Invoice
G005 70% Payment Against Proforma Invoice
G006 50% Payment against Proforma Invoice
G007 50% Agst Pro Inv before Des & After Inspection
G008 30% Agst Pro Inv before Des & After Inspection
45. Project Shield
configuration Document
Page 45 of 182
G009 20% Agst Pro Inv before Des & After Inspection
G010 10% Agst Pro Inv before Des & After Inspection
G011 10% on submission of Performenc Bank Guarantee
G012 20% on submission of Performenc Bank Guarantee
G013 30% on submission of Performenc Bank Guarantee
G014 20% Advance on Acceptence of PO
G015 10% Advance on Acceptence of PO
G016 30% Advance on Acceptence of PO
G017 40% Advance on Acceptence of PO
G018 50% Advance on Acceptence of PO
G019 100% Advance on Acceptence of PO
G020 10% Against Release of Documents
G021 20% Against Release of Documents
G022 30% Against Release of Documents
G023 10% Against Approval Drawings
G024 Perf BG Valid for 12 months from date of Com/18mon
G025 Perf BG Valid for 12 months from date of Erection
G026 40% After Receipt of Materials at our site
G027 50% After Receipt of Materials at our site
G028 60% After Receipt of Materials at our site
G029 70% After Receipt of Materials at our site
G030 80% After Receipt of Materials at our site
G031 90% After Receipt of Materials at our site
G032 100% After Receipt of Materials at our site
G033 100% Cash on Delivery Basis
G034 75% Payment Through Bank
G035 100% Payment Through Bank
46. Project Shield
configuration Document
Page 46 of 182
G036 100% Payment Through DD
G037 100% Payment Through at per Cheque
G038 100% Payment Against Proof of Despatch
G039 Other Charges as meniotned in Notes
G040 100% Payment Within 15 Days of Recpt of Material
G041 100% Payment Within 21 Days of Recpt of Material
G042 100% Payment Within 7 Days of Recpt of Material
G043 100% Payment Within 30 Days of Recpt of Material
G044 100% Payment on Completion of Services
G045 100% Pmt on Completion of Service & Submision bill
G046 100% Payment on Successful Commissioning
G047 5% After Succesful Erection,Testing & Commitioning
G048 10%After Sucesful Erection,Testing & Commitioning
G049 20%After Sucesful Erection,Testing & Commitioning
G050 30%After Sucesful Erection,Testing & Commitioning
G051 50%After Sucesful Erection,Testing & Commitioning
G052 75%After Sucesful Erection,Testing & Commitioning
G053 100%After Sucesful Erection,Testing & Commitioning
G054 5% Advance Payment on Release of Service Order
G055 10% Advance Payment on Release of Service Order
G056 20% Advance Payment on Release of Service Order
G057 30% Advance Payment on Release of Service Order
G058 50% Advance Payment on Release of Service Order
G059 40% Advance Payment on Release of Service Order
G060 5% Payment on Receipt of Materials at Site
G061 10% Payment on Receipt of Materials at Site
G062 20% Payment on Receipt of Materials at Site
47. Project Shield
configuration Document
Page 47 of 182
G063 30% Payment on Receipt of Materials at Site
G064 40% Payment on Receipt of Materials at Site
G065 50% Payment on Receipt of Materials at Site
G066 75% Payment on Receipt of Materials at Site
G067 90% Payment on Receipt of Materials at Site
G068 90% Payment on Receipt of Materials at Site
G069 90% Payment on Submission of Invoice
G070 100% Payment on Submission of Invoice
G071 30% Pmnt on Completion of Progresive Work as in SO
G072 40% Pmnt on Completion of Progresive Work as in SO
G073 50% Pmnt on Completion of Progresive Work as in SO
G074 75% Pmnt on Completion of Progresive Work as in SO
G075 100% Pmnt on Completon of Progresive Work as in SO
G076 10% Payment on Mobilization of Labour at site
G077 20% Payment on Mobilization of Labour at site
G078 25% Payment on Mobilization of Labour at site
G079 30% Payment on Mobilization of Labour at site
G080 10% Against First Part Payment
G081 20% Against First Part Payment
G082 25% Against First Part Payment
G083 30% Against First Part Payment
G084 10% Against Subsequent Part Payment
G085 20% Against Subsequent Part Payment
G086 25% Against Subsequent Part Payment
G087 30% Against Subsequent Part Payment
G088 5% Advance along with confirmation of Contract
G089 10% Advance along with confirmation of Contract
48. Project Shield
configuration Document
Page 48 of 182
G090 20% Advance along with confirmation of Contract
G091 5% toward preparation of Statuatory Dwg for Approv
G092 10% toward preparation of Statuatry Dwg for Approv
G093 20% toward preparation of Statuatry Dwg for Approv
G094 25% toward preparation of Statuatry Dwg for Approv
G095 5% on Acceptence of Dwg for Fabrication/Manufactin
G096 10% on Acceptene of Dwg for Fabrication/Manufactin
G097 15% on Acceptene of Dwg for Fabrication/Manufactin
G098 20% on Acceptene of Dwg for Fabrication/Manufactin
G099 10% after Submission of Dwg,O&M Manual & Comp Cert
G100 20% after Submission of Dwg,O&M Manual & Comp Cert
G101 10% as First Instmt after comp.of First Milestone1
G102 10% as First Instmt after comp.of First Milestone3
G103 10% as First Instmt after comp.of First Milestone3
G104 10% Mobilization Advance
G105 20% Mobilization Advance
G106 25% Mobilization Advance
G107 10% After Submission of Soil Investigation Report
G108 20% After Submission of Soil Investigation Report
G109 50% Pmt within 7 days from the date of Final Bill
G110 60% Pmt within 7 days from the date of Final Bill
G111 75% Pmt within 7 days from the date of Final Bill
G112 80% Pmt within 7 days from the date of Final Bill
G113 100% Pmt within 7 days from the date of Final Bill
G114 50% Pmt within 15 days from the date of Final Bill
G115 50% Pmt within 15 days from the date of Final Bill
G116 75% Pmt within 15 days from the date of Final Bill
49. Project Shield
configuration Document
Page 49 of 182
Check Incoterms
SPRO MaterialsManagement Purchasing Vendor Master Check Incoterms
Following Incoterms are maintained for GMR.
Inco terms Description
CFR Costs and freight
CIF Costs, insurance & freight
CIP Carriage and insurance paid to
CPT Carriage paid to
DAF Delivered at frontier
DDP Delivered Duty Paid
DDU Delivered Duty Unpaid
DEQ Delivered ex quay (duty paid)
DES Delivered ex ship
EXW Ex Works
FAS Free Alongside Ship
FCA Free Carrier
FH Free house
FOB Free on board
FOR Free On Railway
UN Not Free
Create Purchasing Groups ;Purchasing groups have been created as buyers in GMR. Following logic has been
defined for numbering purchasing group.
SPRO MaterialsManagement Purchasing Create Purchasing Groups
Purchase group Description of pur group
BH1 Badrinath PG 1
50. Project Shield
configuration Document
Page 50 of 182
BH2 Badrinath PG 2
C10 CORPORATE - PURCHA
C11 CORPORATE - FIN &
C12 CORPORATE - HR & A
C13 CORPORATE - FMS
C20 CEO
C30 CFO
C40 JMD
C50 MD
C60 SECTOR HEAD
CH1 Chennai PG 1
CH2 Chennai PG 2
CP1 GIDL Corporate
F01 CS- Deptt Head
F02 IT- Deptt Head
F03 Civil- Deptt Head
F04 Mech- Deptt Head
F05 Elec- Deptt Head
F06 E&C- Deptt Head
F07 Chem- Deptt Head
F08 F&A- Deptt Head
F09 Est - Deptt Head
F10 Hostel- Deptt Head
F11 Rajam-Deptt Head
51. Project Shield
configuration Document
Page 51 of 182
F12 BNG- Deptt Head
F13 Delhi- Deptt Head
F14 HYD- Deptt Head
F15 UTT- Deptt Head
F16 MNG- Deptt Head
F17 Locn 7- Deptt Head
F18 Locn 8- Deptt Head
F19 Locn 9- Deptt Head
F20 Locn 10- Deptt Hea
F21 Locn 11- Deptt Hea
F22 Locn 12- Deptt Hea
F23 Principal
F24 CAO
F25 Director-CSW
F26 Sector Head
FMS GCCL Purchasing Gr
FN1 Found Purch Grp 1
FN2 Found Purch Grp 2
G01 User-FMS-BNG
G02 User-FMS-Hyd
G03 User-FMS-Chn
G04 User-FMS-MUM
G05 User-FMS-DEL
G06 Deptt Head- BNG
62. Project Shield
configuration Document
Page 62 of 182
Purchase Requisition:
SPRO MaterialsManagement Purchasing Purchase Requisition Define Document Types
Define Document Types
Following document types defined for GMR
Type Description No int Int no Range
PIMP Import Pur.Req 10 5
PIND Domestic Pur.Req 10 3
PMMS Maint of Mat & Servi 10 7
PSER Service Pur.Req 10 4
PSTO STO Pur.Req 10 6
SPRO MaterialsManagement Purchasing Purchase Requisition Define Document
Types Define Number Ranges.
01 0010000000 0019999999
02 0090000000 0099999999
03 1000000000 1999999999
04 2000000000 2999999999
05 3000000000 3999999999
06 4000000000 4999999999
07 5000000000 5999999999
Release Procedure for Purchasing Requisition
Path: SPRO MaterialsManagement Purchasing Purchase Requisition Release
Procedure Procedure with Classification Edit Characteristics , class ,
63. Project Shield
configuration Document
Page 63 of 182
Edit Characteristic:In this step, you create characteristics for a release procedure for purchase
Requisition(PR)
Following characteristic are created for a PR- release
PR_DOCTYPE - Purchase Requisition Document 00.00.0000 CHAR
PR_PLANT - Plant 00.00.0000 CHAR
PR_TOTALVALUE - Total value of requisition for 00.00.0000 CURR
Edit Class: In this step, you create classes for a release procedure for purchase orders (POs).
Following class are created for PR- release
PR_REL_CLASS EN 032 REL_CLASSS
Release group
Create a release group for your release procedure and assign it to a class. In the process, you assign release
conditions to the release procedure.Following are setting for GMR Group
REL.GRP REL.OBJ CLASS DESCRIPTION
N1 1 REL_CLASS PR_REL_CLASS
N2 1 REL_CLASS PR_REL_CLASS
Release Code
Group Code Description
N1 1 USER DEPARTMENT
N1 2 USER DEPT HEAD
N1 3 UNIT HEAD
64. Project Shield
configuration Document
Page 64 of 182
N2 1 USER
N2 2 USER DEPT HEAD
N2 3 PLANT HEAD
N2 4 ASSET HEAD
Release indicators : A release indicator shows the release status of a PR
Release id Description
2 RFQ/purchase order
Release strategies: Create a release strategy for your release group and assign your release codes accordingly.
Group Code Value
N1 P1 1.00 - 100000.00 INR
N2 P2 >= 100001.00 INR
Purchase Order:
Define Document Types:
SPRO Materials Management Purchasing Purchase order Define Document Types
Following Documents Defined for the Pos.
Type Description ItInt IntNR ExtNR FldSl
GCAP Budgeted Cap Pur.Ord 10 50 NBF
GDOM Domestic Pur.Order 10 45 NBF
GEME Emergency pur.order 10 49 NBF
GIMP Import Pur.Order 10 46 NBF
GSER Service Pur.Order 10 48 NBF
GSTO Stock Transfer PO 10 47 UBF
65. Project Shield
configuration Document
Page 65 of 182
ZCAP Non Budg.Cap.Pur.ord 10 51 NBF
Release Procedure for Purchase Orders
SPRO MaterialsManagement Purchasing Purchase order Release Procedure for Purchase
Orders Edit Characteristics
In this section, you set up a release procedure for purchase orders(POs).To set up the release procedure, you must
make a series of settings in Customizing. This section provides you with an overview of the necessary activities.You
must perform the following steps:
1. Create characteristics :
PO_DOCTYPE Order Type (Purchasing) 00.00.0000 CHAR
PO_PLANT PO_Plant 00.00.0000 CHAR
PO_PURORG Purchasing Organization 00.00.0000 CHAR
PO_VALUE Total net order value 00.00.0000 CURR
SPRO MaterialsManagement Purchasing Purchase order Release Procedure for Purchase
Orders classes
PO_REL_CLASS EN 032 PO_REL_CLASS
SPRO MaterialsManagement Purchasing Purchase order Release Procedure for Purchase Orders
Release Strategies
2. Set up release procedure
Release Groups
Release Codes
Release indicator
Release Strategies
Workflow
a) Create release group
A1 2 PO_REL_CLASS Release Agro
B1 2 PO_REL_CLASS Release Energy
C1 2 PO_REL_CLASS Release Raxa
D1 2 PO_REL_CLASS Release Fms
66. Project Shield
configuration Document
Page 66 of 182
E1 2 PO_REL_CLASS Release Property
F1 2 PO_REL_CLASS Release Agro Corp.
H1 2 PO_REL_CLASS Release Roads
b) Release Code
Here you create the release codes you need for your release strategy and assign the codes to your release group.
Following are setting for GMR Group
Agro Release code
A1 01 Procurement Head
A1 02 Department Head
A1 03 Unit Head
A1 04 Chief Executive Off.
A1 05 Joint Managing Dir.
A1 06 Managing Dir.
A1 07 Sector Head
A1 S1 Shared Services
Energy Release code
B1 11 Procurement Head
B1 12 Department Head
B1 13 Shared ser/Finance
B1 14 Plant Manager
B1 15 Head Asset Mgmt
B1 16 Chief Executive Off.
B1 17 Sector Head
B1 H1 Hpe/Hbm/Abm
Raxa Release code
67. Project Shield
configuration Document
Page 67 of 182
C1 21 Procurement Head
C1 22 Na
C1 23 Shared ser/Finance
C1 24 Chief Security Off.
C1 25 Executive Director
C1 26 Managing Dir.
C1 27 Sector Head
C1 V1 Vice President
FMS Release Code
D1 31 Procurement Head
D1 32 Department Head
D1 33 Shared ser/Finance
D1 34 Location Head
D1 35 Head Fms
D1 36 Sector Head
Property Release Code
E1 41 Gen Manager Projects
E1 42 Gen Manager Contr
E1 43 Assistant Vice Pres.
E1 44 Chief Financial Off.
E1 45 Chief Operation Off.
E1 46 Sector Head
E1 47 Chief Executive Off.
Agro Corporation Release code
68. Project Shield
configuration Document
Page 68 of 182
F1 51 Department Head
F1 52 Chief Financial Off.
F1 53 Chief Executive Off.
F1 54 Joint Managing Dir.
F1 55 Managing Dir.
F1 56 Sector Head
Roads Release code
H1 61 Procurement Head
H1 62 Sectional Head
H1 63 Chief Executive Off.
H1 64 Sector Head
H1 P1 Project Manager Site
C) Create release indicator :-- A release indicator shows the release status of a PO.
R 6 0.0 Released
X 0.0 Blocked
D) Release strategies
Create a release strategy for your release group and assign your release codes accordingly.
Agro Release Strategy
A1 01 AGRO PO GCAP 1-10L GCAP 1 – 1000000
A1 02 AGRO PO GCAP 10L-1CR GCAP 1000000-000000
A1 03 AGRO PO GCAP >1CR GCAP >10000000
A1 04 AGRO PO ZCAP 1 - 10L ZCAP 1-1000000
A1 05 AGRO PO ZCAP >10L ZCAP >1000000
71. Project Shield
configuration Document
Page 71 of 182
E1 41 PROP GCAP 1 - 2L GCAP 1 - 200000
E1 42 PROP GCAP 2L - 25L GCAP 200000 - 2500000
E1 43 PROP GCAP 25L - 1CR GCAP 2500000 - 10000000
E1 44 PROP GCAP >1 CR GCAP >10000000
E1 45 PROP ZCAP 1 - 10L ZCAP 1 - 1000000
E1 46 PROP ZCAP 10L-25L ZCAP 100000 - 2500000
E1 47 PROP ZCAP 25L - 1CR ZCAP 2500000 - 10000000
E1 48 PROP ZCAP >1CR ZCAP >10000000
E1 E1 PROP PO 1 - 1L GDOM 1 - 100000
E1 E2 PROP PO 1L - 10L GDOM 100000 -1000000
E1 E3 PROP PO 10 L - 25L GDOM 1000000 - 2500000
E1 E4 PROP PO 25L - 50 L GDOM 2500000 - 5000000
E1 E5 PROP PO > 50L GDOM >5000000
E1 E6 PROP GEME 1 - 50K GEME 1 - 50000
E1 E7 PROP GEME 50K-5L GEME 50000 - 500000
E1 E8 PROP GEME > 5L GEME >500000
Release Stratergy for Agro Corporation
F1 F1 AG CORP GCAP 1 -1L GCAP 1 - 100000
F1 F2 AG CORP GCAP 1L-25L GCAP 100000 – 2500000
F1 F3 AG CORP GCAP 25L -CR GCAP 2500000 - 10000000
F1 F4 AG CORP GCAP >1CR GCAP >10000000
F1 F5 AG CORP ZCAP 1- 10L ZCAP 1 - 1000000
F1 F6 AG CORP ZCAP >25L ZCAP >25000000
F1 F7 AG CORP PO 1 -10K GDOM 1 - 10000
72. Project Shield
configuration Document
Page 72 of 182
F1 F8 AG CORP PO 10K-10L GDOM 10000 - 1000000
F1 F9 AG CORP PO 10L-15L GDOM 100000 – 1500000
F1 FA AG CORP PO 15L-25L GDOM 1500000 – 2500000
F1 FB AG CORP PO >25L GDOM >2500000
F1 FC AG CORP GEME 1 - 1L GEME 1 - 100000
F1 FD AG CORP GEME >1L GEME >100000
Release Stratergy for Road Corporation;
H1 H1 ROADS PO 1- 25L GDOM 1 – 2500000
H1 H2 ROADS PO 25L - 100L GDOM 2500000 – 1000000000
H1 H3 ROADS PO >100L GDOM >1000000000
H1 H4 ROADS PO GEME 1-10L GEME 1 - 1000000
H1 H5 ROADS PO GEME>10L GEME >1000000
H1 H6 ROADS GCAP 1 - 25L GCAP 1 - 2500000
H1 H7 ROADS GCAP 25L -1CR GCAP 2500000 - 10000000
H1 H8 ROADS GCAP >1CR GCAP >10000000
H1 H9 ROADS ZCAP 1 - 10L ZCAP 1 - 1000000
H1 HA ROADS ZCAP >10L ZCAP >1000000
SPRO Materials Management Purchasing Purchase order Set Tolerance Limits for Price
Variance
73. Project Shield
configuration Document
Page 73 of 182
SPRO Materials Management Purchasing Purchase order Texts for Purchase Orders
Define Text Types for Header Texts
Stock Transport Setup
SPRO Materials Management Purchasing Purchase order Set up Stock Transport Order
Define Shipping Data for Plants
With this data, the system determines the shipping data for the material to be transferred (e.g. the shipping point).
Select the required Plant and Press F8
74. Project Shield
configuration Document
Page 74 of 182
Create Checking Rule:
SPRO Materials Management Purchasing Purchase order Set up Stock Transport Order
Create Checking Rule
In this step, you create rules for the availability check in the case of stock transport orders.
This check enables you to find out whether the quantity requested is available in
the supplying plant, for example, in the case of materials that are to be
transferred over longer distances from one site to another.
SPRO Materials Management Purchasing Purchase order Set up Stock Transport Order
Define Checking Rule.
75. Project Shield
configuration Document
Page 75 of 182
SPRO Materials Management Purchasing Purchase order Set up Stock Transport Order
Assign Delivery Type and Checking Rule
Returns to Vendor
SPRO Materials Management Purchasing Purchase order Set up Stock Transport Order Returns
Order Returns to Vendor
76. Project Shield
configuration Document
Page 76 of 182
Returns Order;- In this step, you define shipping-specific data for the returns
order. You make settings for the required return delivery type for
• purchasing document category F (purchase order),
• purchasing document type
o NB - standard purchase order
o UB - stock transport order
• the supplying plant
Contract
Path: SPRO Materials Management Purchasing Contract Number range
41 4100000000 4199999999
44 4400000000 4499999999
45 4500000000 4599999999
46 4600000000 4699999999
47 4700000000 4799999999
48 4800000000 4899999999
49 4900000000 4999999999
50 5000000000 5099999999
51 5100000000 5199999999
52 5200000000 5299999999
77. Project Shield
configuration Document
Page 77 of 182
SPRO Materials Management Purchasing Contract Define Document Types
Type Description Itm int No range int Updategrp Fieldsel
GAGH Acc& guesth contract 10 54 SAP WKK
GCLK Con.& lgl contract 10 55 SAP WKK
GCMK GMR Qty Contract 10 56 SAP MKK
GCWK GMR Value Contract 10 57 SAP WKK
GITK IT.Related contract 10 58 SAP WKK
GLTC Long term contracts 10 59 SAP WKK
GOMK Office main.Contract 10 60 SAP WKK
GPMK Hiring of Plnt & m/c 10 61 SAP WKK
GPRK Project Related Cont 10 62 SAP WKK
Release Procedure for Contract:
Path: SPRO Materials Management Purchasing Contract Release Procedure for Contracts
Edit Characteristic: In this step, you create characteristics for a release procedure for Contract
Following characteristic are created for a contract release
PO_DOCTYPE
PO_PLANT
PO_VALUE
PO_PURORG
Edit Class :In this step, you create classes for a release procedure for Contract
Following class are created for Contract release
REL_CLASS
78. Project Shield
configuration Document
Page 78 of 182
Release strategies
Create a release strategy for your release group and assign your release codes accordingly.
Contract Release Stratergy Agro
.A1 AA AG CONT GCMK,WK 1-1K GCMK 1 -1000
A1 AB AGRO CONT 1K - 10L GCMK 1000-1000000
A1 AC AGRO CONT 10L - 15L GCMK 1000000-1500000
A1 AD AGRO CONT 15L - 25L GCMK 1500000-2500000
A1 AE AGRO CONT >25L GCMK >2500000
A1
AF AGRO CONT GITK 1- 1
GITK 1-1000000
A1 AG AGROCONT GITK10L-15L GITK 100000-1500000
A1 AH AGROCONT GITK15L-25L GITK 1500000-2500000
A1 AI AGRO CONT GITK >25L GITK >2500000
A1 AJ AGRO CONT GCLK 1-1L GCLK 1 - 100000
A1 AK AGRO CONT GCLK 1L-5L GCLK 100000 - 500000
A1 AL AGRO CONT GCLK >5L GCLK >500000
A1 AM AGRO CONT GLTC 1 -1K GLTC 1 - 1000
A1 AN AGRO CONT GLTC1K-10L GLTC 1000 - 1000000
A1 AO AGROCONTGLTC10L-15L GLTC 1000000 - 1500000
A1 AP AGROCONTGLTC15L-25L GLTC 1500000 - 2500000
A1 AQ AGRO CONT GLTC >25L GLTC >2500000
A1 AR AGRO CONT GAGH 1-5K GAGH 1-5000
A1 AS AGROCONT GAGH5K-25K GAGH 5000-25000
A1 AT AGRO CONT GAGH >25K GAGH >25000
Contract Release Stratergy Energy
B1 B8 ENGY CONT 1 - 2L GCMK 1 - 200000
83. Project Shield
configuration Document
Page 83 of 182
CONDITIONS
Define Price Determination Process
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Access Sequences
Define Access Sequences
In this step you define access sequences. An access sequence is a search strategy with the aid of which the SAP System searches for valid
condition records for a condition type.
AS Description Description
0002 Gross Price Access sequence relevant for pricing
WBTC Trading Contract (WBTC) Access sequence relevant for pricing
WB2B Trading Contract (WB2B) Access sequence relevant for pricing
WBTC Trading Contract (WBTC) Access sequence relevant for pricing
WTC1 Trading Contract (WBC1) Access sequence relevant for pricing
Define Condition Types
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Condition Types.
84. Project Shield
configuration Document
Page 84 of 182
The condition types are used to represent pricing elements such as prices, discounts, surcharges, taxes, or delivery
costs in the SAP System. These are stored in the system in condition records. Following condition types are define
for GMR which can subsequently be used in GMR Pricing Procedure.
86. Project Shield
configuration Document
Page 86 of 182
Define Calculation Schema
In the MM area, a calculation schema - a framework of steps used to calculate or determine something - is used among other things to
calculate costs, prices, period-end rebates, and taxes.
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Calculation Schema.
Procedure Description
GMRDOM GMR Domestic Pricing Procedure
GMRIMP GMR Import Pricing Procedure
GMR Local pricing procedure as follows.
Ste
p
Cnt
r CTyp Description
Fro
m To
Man
.
Req
t
Prin
t
SubT
o
Sta
t
AltCT
y
AltCB
V
ActK
y
Accrl
s
1 1 PB00 Gross Price X 9
1 2 PBXX Gross Price 5 X 9
5 GDC1 Discount(Perct) 1
7 GDC2 Discount/Quantity 1
9 GDC3 Discount (Value) 1
11 GPK1 Pack & Forwa(Perct) 1 9 GP1 GP1
13 GPK2 Pack & Forwa(Value) 1 9 GP1 GP1
87. Project Shield
configuration Document
Page 87 of 182
15 GCH1 Other Charges(Perct) 1 GO1 GO1
17 GCH2 Other Charge (Value) 1 GO1 GO1
19 GCH3 Other Charge/Qty 1 GO1 GO1
20 GCH4 Surcharge% 1
21 GCH5 Surcharge value 1
25
Sub Tot 1(Price - Dis +
P&F ) 1 21 X X
28 JEXC IN Manual Excise 5 X
30 ZADC ADC in pricing 2 X
37 Sub Tot 2(Net Price + ED) 25 36 X
45 JEXS Taxes on the PO X X
50
Sub Tot 3 (Net Price
+ED+Tax) 37 45 X
53 GENT Entry Tax (Perct) 50 X
56 JOCM IN Octroi 50 X
58 GIN1 Insurence (Perct) 1 X GN1 GN1
60 GIN2 Insurence (Value) 1 X GN1 GN1
62 GDOC Document Charg(Perct 1 X GC1 GC1
64 GDO1 Document Char(Value) 1 X GC1 GC1
66 GLD1 Loding & Unlod Ch(Pe 1 X GL1 GL1
68 GLD2 Loding & Unlod Ch(Va 1 X GL1 GL1
70 GLD3 Loding & Unlod Ch(Qt 1 X GL1 GL1
72 GHD1 Hand Charges(Perct) 1 X GH1 GH1
74 GHD2 Hand Char(Value) 1 X GH1 GH1
76 GHD3 Hand Char(Qty) 1 X GH1 GH1
78 GFR1 Freight Charg(Perct) 1 X FR1 FR1
80 GFR2 Freight Charg(Value) 1 X FR1 FR1
82 GFR3 Freight Charg(Qty) 1 X FR1 FR1
84 GDR1 Demurrage Cha(Perct) 78 82 X GD1 GD1
86 GDR2 Demurrage Cha Value 78 82 X GD1 GD1
88. Project Shield
configuration Document
Page 88 of 182
88 GDR3 Demurrage Char Qty 78 82 X GD1 GD1
90 GIC1 Insp.Charges(Perct) 1 X GI1 GI1
91 GIC2 Insp.Charges(Value) 1 X GI1 GI1
93 GBC1 Brokerage Cha(Perct) 1 X GB1 GB1
95 GBC2 Brokerage Cha(Value) 1 X GB1 GB1
97 GBC3 Brokerage Char(Qty) 1 X GB1 GB1
99 Sub Tot 4(Other Charges) 53 97 X
100 Copy of Sub Tot 3 50 X
101 Total PO Cost 99
10
0 S X
103 NAVS Non-Deductible Tax 37 X
104 SKTO Cash Discount 37 17 X
110
GRW
R Statistical Value 8 C X
GMR Import Pricing procedure as Follows.
Step Cou Cond Type Description From To Print SubTot Reqmt Calc Bas ty Acck Accrls
1 1 PB00 Gross Price 0 0 X 9 0 0 0
1 2 PBXX Gross Price 0 0 X 9 5 0 0
5 0 GDC1 Discount(Perct) 1 0 0 0 0
7 0 GDC2 Discount/Quantity 1 0 0 0 0
9 0 GDC3 Discount (Value) 1 0 0 0 0
11 0 GPK1 Pack & Forwa(Perct) 1 9 0 0 0 GP1 GP1
13 0 GPK2 Pack & Forwa(Value) 1 9 0 0 0 GP1 GP1
15 0 GCH1 Other Charges(Perct) 1 0 0 0 0 GO1 GO1
17 0 GCH2 Other Charge (Value) 1 0 0 0 0 GO1 GO1
19 0 GCH3 Other Charge/Qty 1 0 0 0 0 GO1 GO1
90. Project Shield
configuration Document
Page 90 of 182
100 0 GHD1 Hand Charges(Perct) 1 0 0 0 0 GH1 GH1
102 0 GHD2 Hand Char(Value) 1 0 0 0 0 GH1 GH1
104 0 GHD3 Hand Char(Qty) 1 0 0 0 0 GH1 GH1
106 0 GFR1 Freight Charg(Perct) 1 0 0 0 0 FR1 FR1
108 0 GFR2 Freight Charg(Value) 1 0 0 0 0 FR1 FR1
110 0 GFR3 Freight Charg(Qty) 1 0 0 0 0 FR1 FR1
112 0 GDR1 Demurrage Cha(Perct) 106 110 0 0 0 GD1 GD1
114 0 GDR2 Demurrage Cha Value 106 110 0 0 0 GD1 GD1
116 0 GDR3 Demurrage Char Qty 106 110 0 0 0 GD1 GD1
118 0 GIC1 Insp.Charges(Perct) 1 0 0 0 0 GI1 GI1
120 0 GIC2 Insp.Charges(Value) 1 0 0 0 0 GI1 GI1
122 0 GBC1 Brokerage Cha(Perct) 1 0 0 0 0 GB1 GB1
124 0 GBC2 Brokerage Cha(Value) 1 0 0 0 0 GB1 GB1
126 0 GBC3 Brokerage Char(Qty) 1 0 0 0 0 GB1 GB1
129 0 Sub-Tot 5(Other Charges) 88 126 0 0 0
132 0 Copy of Sub-Tot 4 86 0 0 0 0
135 0 Total Landing Cost 129 132 0 0 0
160 0 SKTO Cash Discount 0 0 17 0 0
165 0 Actual price 0 0 S 0 0 0
170 0 GRWR Statistical Value 0 0 X C 8 0 0
Define Schema Group :These allow you to group together certain purchasing organizations that use the
same calculation schema. You can also use them to group together vendors for whom the same calculation schema
is valid.
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Schema Group
Schema Groups: Vendor
91. Project Shield
configuration Document
Page 91 of 182
Schema Groups for Purchasing Organizations
Assignment of Schema Group to Purchasing Organization
Schema Groups: Vendor
Sch.grp.vendor Desciption
DS Domestic Schema Vendor
IS Import Schema Vendor
Schema Groups for Purchasing Organizations
GMR Schema Group for Purchasing Organization
PurGr Sc Description
G001 GMR Schema Pur Org
Assign Schema Group to Purchasing Organisation
POrg Description Pur Sch Gr
2000 Energy Pur Org G001
2101 Pur Org for HHI G001
4000 Agro Pur org G001
5000 Property Pur Org
G001
6600 GCCL Pur Org G001
8000 Raxa Pur Org G001
8100 Aviation Pur org G001
8600 Foundation Pur Org G001
Define Schema Determination: In this step we define for various combination of Purchasing Schema Group and
Vendor Schema Group which pricing procedure is applicable. Following is GMR settings for various combinations.
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Schema Determination
Determine Calculation Schema for Standard Purchase Orders
92. Project Shield
configuration Document
Page 92 of 182
Pur Sch Grp Vend Sch Grp Price rocedure Description
G001 DS GMRDOM GMR Domestic Pricing Procedure
G001 IS GMRIMP GMR Import Pricing Procedure
Determine Schema for Stock Transport Orders
G001 GSTO GSTPP1 GMR Stock Transfer Pricing
Path: SPRO Materials Management Purchasing Conditions Define Price Determination
Process Define Transaction/Event Keys
Trans./Event Key; - To enable the system to find the relevant account for provisions (for accrued delivery costs or
miscellaneous provisions, for example), you must assign a transaction/event (internal processing) key to each
condition type that is relevant to provisions in the step Define Calculation Schema.
95. Project Shield
configuration Document
Page 95 of 182
Version Management;;-
Set Up Version Management for External Purchasing Documents: In this step, you set up the version management
facility for external purchasing documents.For a combination of purchasing organization, document category, and document type,
you can:
• Activate version management
If version management is active, changes to a purchasing document are managed in versions.
• Define field selection for versions
You can specify the attributes certain fields of the version are to have: mandatory entry, optional entry, display only, field
suppressed.
Path: SPRO Materials Management Purchasing Version Management Set Up Version
Management for External Purchasing Documents
96. Project Shield
configuration Document
Page 96 of 182
Path: SPRO Materials Management Purchasing Version Management Define Reasons for
Change
Vendor Evaluation :
In this section, you make the settings for vendor evaluation that apply to all purchasing organizations:
• Define weighting keys
• Define criteria
• Define scope of list
In the step Define Purchasing Organization Data for Vendor Evaluation, you define individual values for each
purchasing organization.
SPRO Materials Management Vendor Evaluation Define Weighting Keys
103. Project Shield
configuration Document
Page 103 of 182
Similarly we need to maintain Main and Sub criteria’s for all required Purchase organizations
Weighting for Purchase org
109. Project Shield
configuration Document
Page 109 of 182
External Services Management
External Services Management:
Use this menu to make the special system settings that are necessary to carry
out procurement transactions involving external services.You should not
process procurement transactions in the SAP System until you have worked
through this chapter. All settings of general relevance to the procurement of
both services and materials are made via the "Purchasing" menu.
Service Master:
SPRO Materials Management External Services Management Service Master Define Service
Category
SPRO Materials Management External Services Management Service Master Define Number
Ranges
111. Project Shield
configuration Document
Page 111 of 182
SPRO Materials Management External Services Management Number Ranges Define Number
Ranges for Service Entry Sheet
SPRO Materials Management External Services Management Number Ranges Define Internal
Number Range for Service Specifications
SPRO Materials Management External Services Management Number Ranges Assign Number
Ranges.
SPRO Materials Management External Services Management Define Attributes of System
Messages
112. Project Shield
configuration Document
Page 112 of 182
Material Management- Inventory Management and Physical Inventory
In this section, you complete the system settings required for the following:
goods movements, including:
goods issues
transfer postings.
goods receipts.
reservations
physical inventory
reporting /evaluations
transfer of data from external DP systems.
SPRO Materials Management Inventory Management and Physical Inventory Goods Issue / Transfer
Postings Create Storage Location Automatically
114. Project Shield
configuration Document
Page 114 of 182
Set Up Dynamic Availability Check: In this step, you configure the dynamic availability check.
In Inventory Management, two types of availability check are carried out.
• availability check during the entry of reservations
• availability check during the entry of goods movements
The system checks whether the material to be withdrawn is available and issues a message, if necessary.
SPRO Materials Management Inventory Management and Physical Inventory Issue / Transfer
Postings Set Up Dynamic Availability Check
120. Project Shield
configuration Document
Page 120 of 182
Movement Types
SPRO Materials Management Inventory Management and Physical Inventory movement type Record
Reason for Goods Movements
121. Project Shield
configuration Document
Page 121 of 182
Output Determination :
In Inventory Management, output is text that is created at the time of goods movements. There are output documents
such as:-
goods receipt/issue slips ( example, GR/GI slips, pallet slips) /Labels/ kanban cards/ MAIL messages which
Inventory Management uses to communicate with other departments (purchasing or materials planning, for example)
Depending on the type, an output document can be printed or sent to a recipient (for example, via MAIL). An output
control mechanism that depends on different criteria allows to process and send the output documents with defined
restrictions and under certain conditions.
Goods accompanying slips such as goods receipt or goods issue slips can be printed for every movement. The
goods accompanying slip (also referred to in the system as goods receipt/issue slip) can be printed in three versions:
Version 1: individual slip : -In this version, one goods receipt/issue slip is printed per item.
Version 2: individual slip with inspection text: -This version is also used to print individual slips. The printout also
contains the quality inspection text, provided it exists in the material master record.
Version 3: collective slip:-In this version, a collective slip is printed for all items of the material document.
When entering a goods movement, the user can define through an indicator whether an output document is created,
that is, whether a goods receipt/issue slip is printed or not. Printing a goods receipt/ issue slip in a separate step after
entering the goods movement is also possible.
An output type (also referred to as condition type) is defined for every type of goods receipt/issue slip and for every
version. That is, the following output types are available in the standard system:
GR slip, version 1 / GR slip, version 2/ GR slip, version 3/ GI slip, version 1/ GI slip, version 2.
For particular cases, such as subcontract order processing, separate output types are defined. Return delivery slips
use the same output types as GR slips.
All information relevant for printing the corresponding goods receipt/issue slip is stored for every output type, for
example:
SAPscript layout set / print parameters (for example, immediate print)
When a goods movement is entered, the system checks whether the conditions for an output type are met. For
example, if an output type is defined for the respective transaction type, movement type, and version, an output
document is generated automatically.
In this section, you define which output type is created for a goods movement and how the output document is
processed.
You have to check or maintain the following objects so that the system creates an output document when a goods
movement is entered: -
condition table / access sequence/ output types /output determination procedure / condition records / SAPscript
layout set for the output type / Printer determination
Requirements :
122. Project Shield
configuration Document
Page 122 of 182
1. In the Print control section, you must have: a) defined print indicators b) allocated print indicators to movement
types c) allocated versions to transactions
2. Before you set up the output determination, you have to run the program RM07NCUS for each client in which you
want to use the output determination function.
This program copies the basic settings from the SAP standard client (000).
Note:In the case of a goods receipt for a purchase order, MAIL messages are sent to purchasing in two cases:
if Purchasing has set the indicator "GR output" in the purchase order /
if an order price quantity has been entered at the time of a goods receipt which lies outside the tolerances (for a
warning message).
In the case of a goods receipt of missing parts, a mail message is sent to the MRP controller if the missing parts
check is active for the plant.
The standard system contains all settings for this output. You only have to maintain the mail texts for the following
output types:
MLGR (GR message) / MLMD (GR quantity variance )/ MLFH (goods receipt of missing part)
SPRO Materials Management Inventory Management and Physical Inventory Output Determination
Maintain Condition Tables
SPRO Materials Management Inventory Management and Physical Inventory Output Determination
Maintain Access Sequences
125. Project Shield
configuration Document
Page 125 of 182
Material Management:-Valuation and Account Assignment
In this section, you make the system settings required for the following areas:
-Material valuation
-Link between Materials Management and Financial Accounting
Requirements;
You must have processed the defaults for the material types before you can make your configurations for "Valuation
and Account Determination."
SPRO Materials Management Valuation and Account Assignment Define Price Control for
Material Types
127. Project Shield
configuration Document
Page 127 of 182
SPLIT VALUATION:
Split valuation enables you to valuate substocks of a material in different ways (for example, according to external
procurement or in-house production or by batches).
Under the menu option "Split valuation", you can determine whether and how you want to use split valuation at your
company.
SPRO Materials Management Valuation and Account Assignment split valuation Activate Split
Valuation
SPRO Materials Management Valuation and Account Assignment split valuation Configure Split
Valuation
132. Project Shield
configuration Document
Page 132 of 182
Account Determination:
In this step, you can make the settings for account determination in Inventory Management and Invoice
Verification. Account determination without the wizard enables you to make a more complex configuration than
account determination with the wizard, but requires that you are already familiar with the principle of automatic
account determination in the ERP System. /You can configure account determination with the wizard in the first
instance, for example. Then, if the wizard does not meet your company's account determination requirements, you
can work without it.
Detailed documentation on account determination is contained in the step Configure automatic postings.
Further notes
You have to work without the wizard if you use the material ledger.
SPRO Materials Management Valuation and Account Assignment Account Determination
Without Wizard Define Valuation Control
SPRO Materials Management Valuation and Account Assignment Account Determination
Without Wizard Define Valuation Classes
137. Project Shield
configuration Document
Page 137 of 182
Configure Automatic Postings : In this step, you enter the system settings for Inventory Management and Invoice
Verification transactions for automatic postings to G/L accounts.You can then check your settings using a simulation function.
What are automatic postings?
Postings are made to G/L accounts automatically in the case of Invoice Verification and Inventory Management transactions relevant to Financial and
Cost Accounting.
Example:
Posting lines are created in the following accounts in the case of a goods issue for a cost center:
Stock account / Consumption account
How does the system find the relevant accounts?
When entering the goods movement, the user does not have to enter a G/L account, since the ERP system automatically finds the accounts to which
postings are to be made using the following data:
-Chart of accounts of the company code:
If the user enters a company code or a plant when entering a transaction, the ERP system determines the chart of accounts which is valid for the
company code.
hou must define the automatic account determination individually for each chart of accounts.
aluation grouping code of the valuation area : If the automatic account determination within a chart of accounts is to run differently for certain
company codes or plants (valuation areas), assign different valuation grouping codes to these valuation areas.
You must define the automatic account determination individually for every valuation grouping code within a chart of accounts. It applies to all valuation
areas which are assigned to this valuation grouping code.
If the user enters a company code or a plant when entering a transaction, the system determines the valuation area and the valuation grouping code.
Transaction/event key (internal processing key):
Posting transactions are predefined for those inventory management and invoice verification transactions relevant to accounting. Posting records,
which are generalized in the value string, are assigned to each relevant movement type in inventory management and each transaction in invoice
verification. These contain keys for the relevant posting transaction (for example, inventory posting and consumption posting) instead of actual G/L
account numbers.
You do not have to define these transaction keys, they are determined automatically from the transaction (invoice verification) or the movement type
(inventory management). All you have to do is assign the relevant G/L account to each posting transaction.
Account grouping (only for offsetting entries, consignment liabilities, and price differences)
Since the posting transaction "Offsetting entry for inventory posting" is used for different transactions (for example, goods issue, scrapping, physical
inventory), which are assigned to different accounts (for example, consumption account, scrapping, expense/income from inventory differences), it is
necessary to divide the posting transaction according to a further key: account grouping code.
An account grouping is assigned to each movement type in inventory management which uses the posting transaction "Offsetting entry for inventory
posting".
Under the posting transaction "Offsetting entry for inventory posting", you must assign G/L accounts for every account grouping, that is, assign G/L
accounts.
If you wish to post price differences to different price difference accounts in the case of goods receipts for purchase orders, goods receipts for orders,
or other movements, you can define different account grouping codes for the transaction key.
Using the account grouping, you can also have different accounts for consignment liabilities and pipeline liabilities.
138. Project Shield
configuration Document
Page 138 of 182
Valuation class of material or (in case of split valuation) the valuation type
The valuation class allows you to define automatic account determination that is dependent on the material. for example: you post a goods receipt of a
raw material to a different stock account than if the goods receipt were for trading goods, even though the user enters the same transaction for both
materials.
You can achieve this by assigning different valuation classes to the materials and by assigning different G/L accounts to the posting transaction for
every valuation class.
If you do not want to differentiate according to valuation classes you do not have to maintain a valuation class for a transaction.
SPRO Materials Management Valuation and Account Assignment Account Determination
Without Wizard Configure Automatic Postings
140. Project Shield
configuration Document
Page 140 of 182
Logistics Invoice Verification:
In the Implementation Guide for Logistics Invoice Verification, you make the system settings that are required for the following areas:
Processing invoice receipts
Connection to Financial Accounting
Note : You must process the sections for document types and number ranges in the Incoming Invoice unit.
SPRO Materials Management Logistics Invoice Verification Define Attributes of System Messages
SPRO Materials Management Logistics Invoice Verification Incoming Invoice Number
Assignment
143. Project Shield
configuration Document
Page 143 of 182
SPRO Materials Management Logistics Invoice Verification Maintain Number Assignment for
Logistics Documents Transaction - Assign Number Range
SPRO Materials Management Logistics Invoice Verification Maintain Number Assignment for
Logistics Documents Maintain Number Range Intervals for Invoice Documents
147. Project Shield
configuration Document
Page 147 of 182
Financial Accounting (New)
TAXES ON SALES/PURCHASE
The taxes on sales/purchases include input tax, output tax, acquisition tax and additional taxes.
In addition to tax codes, percentage rates and tax accounts, you have to specify whether the cash discount amount reduces the tax
base amount, depending on the company code. This reduction is, for example, possible in Belgium but not in Germany.
The following sections describe the specifications you must make for calculating taxes on sales/purchases.
SPRO Financial Accounting (New) Tax on Sales/Purchases Basic Settings Check Calculation
Procedure
Check Calculation Procedure
In this activity, you can check and, if necessary, change existing procedures for tax calculation.
Standard settings
Calculation procedures containing the necessary specifications for the calculation and posting of taxes on sales/purchases have
already been defined in the standard SAP system for certain countries. Every calculation procedure groups several tax types
together into a condition type (for example, output tax or input tax) in the calculation procedure, and determines calculation rules
for it.
The calculation procedure determines for which amount the individual condition types are to be calculated. This can be the base
amount (total of the expense items and the revenue items) or a subtotal. The entry in column FrmLvl, determines for which amount
tax is calculated.
Note:- In this activity, the condition types for the check and the possible change provided in the standard system are also displayed.
Here, for example, the condition calculation rule, or for which base amount the tax is calculated is determined (= condition type).
Recommendation:-If possible, do not change the condition types and calculation procedures provided in the standard system. Only
check the standard condition types and calculation procedures regarding whether you can use them for your requirements. If
necessary, make changes.
Activities :If you cannot use the standard settings, change the condition types and calculation procedures delivered to meet your
requirements.
153. Project Shield
configuration Document
Page 153 of 182
SPRO Financial Accounting (New) Tax on Sales/Purchases Basic Settings Assign Country to
Calculation Procedure
SPRO Financial Accounting (New) Tax on Sales/Purchases Basic Settings Check and Change
Settings for Tax Processing
Check &Change Settings for Tax processing:-
In this activity you make the necessary specifications for posting taxes. In doing this you specify under a process key
the following indicators:
• Tax type :- Output tax, input tax, additional taxes, or "not tax-relevant" can be specified as the tax type.
• Nondeductibility of tax amounts:- For this, tax amounts are marked as not deductible.
• Posting indicator: - Here you specify whether the tax amount is posted separately or distributed to expense
or revenue items.
• Tax not relevant to cash discount (Not discount relevant) :-This indicator is set only for Canada. If you
select it, the system does not take into account the corresponding tax amount when determining the tax
base.
[For a every new conditions defined we need to create one Accounting Key w.r.t The business
requirement. Example- In Ta x procedure we have defined new condition For Ecess on Service=ZESS
Condition and for this we have created new Accounting Key as –ZES-ECS on Service Tax in this session ]