SlideShare a Scribd company logo
1 of 30
PROJECT MANAGEMENT
 CPM & PERT TECHNIQUES
FLOW OF PRESENTATION




 INTRODUCTION
 NETWORK PLANNING
 ESTIMATING TIME
 CPM
 PERT
Project Management



Project
• A project is an interrelated set of activities that has a definite
   starting and ending point and that results in a unique product
   or service.

Project management
• Project management is a scientific way of planning, implementing,
   monitoring & controlling the various aspects of a project such as time,
   money, materials, manpower & other resources.
Network Planning Methods



    Methods used for network planning are:
       CPM
       PERT

    Managing a project with network planning methods involves four steps:

1.   Describing the Project.
2.   Diagramming the Network.
3.   Estimating time of completion.
4.   Monitoring Project Progress.
Network Diagram



Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram




1.   Before an activity can begin, its preceding
     activities must be completed.
2.   Arrows indicate logical precedence.
3.   Flow of the diagram is from left to right.
4.   Arrows should not intersect.
5.   Dangling should be avoided.
APPRAOCHES FOR
                                   NETWORK DIAGRAM



ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
  to represent events.
• It is Event Oriented.
                     3



         1     2                    6     7     8




                         4   5
DUMMY ACTIVITY

    AOA approach requires the addition of a                Dummy
    Activity to clarify the precedence relationships     between
    the two activities. It is a zero time activity and
    consumes no resources.

Dummy Activity is used in two situations:
1) When two or more activities start and end at the same
   nodes
                                 1             3



                                           2
2) When two or more activities share the same
   precedence activity but not all the precedence are
   shared.

                 1       3       5

                                           7

                 2       4           6
ACTIVITY ON NODE(AON):


Uses nodes to represent activities and arcs indicate
precedence relationships between       them.
It is Activity Oriented.
ESTIMATING TIME
                                                      OF
                                                  COMPLETION

Planning the schedule of the project

Time estimates include:
1)   Total time for completion.
2)    ES- Earliest start time: the earliest time at which the activity
     can start given that its precedent activities must be completed first.

3)   EF-Earliest finish time: equals to the earliest start time for the activity
     plus the time required to complete the activity.

4)   LF- Latest finish time: the latest time in which the activity can be
     completed without delaying the project.

5)   LS- Latest start time: equal to the latest finish time minus the time
     required to complete the activity.
6)   FORWARD PASS:
     The early start and early finish times are calculated by
     moving forward through the network and considering the
     predecessor activities Considers maximum

7)   BACKWARD PASS:
     The latest start and finish times are calculated by moving backward through the
     network.
     Considers minimum

8)   SLACK TIME:
     Slack time for an activity is the difference between its earliest and latest start
     time or between the earliest and latest finish time.
     Critical path is the path of activities having zero Slack time.
A Simple Project




Activity    Immediate      Expected
           Predecessor       Time
   A            -              5
   B            -             6
   C           A              4
   D          A, B            2
Precedence Diagram
ES      Earliest Starting (time)
EF      Earliest Finishing
LS      Latest Starting
LF      Latest Finishing
Slack   Difference Time
CRITICAL PATH
                                         METHODS(CPM)

HISTORY :
  It was developed by J.E.KELLY of REMINGTON-RAND
  and M.R.WALKER of DU PONT and the emphasis was
  on the trade-off between the cost of project and its overall
  completion time. The first test was made in 1958,when CPM
  was applied to the construction of a new chemical plant.

DEFINITION:
  Critical path is the sequence of activities between a project’s
  start and finish that takes the longest time to complete.
STEPS IN DETERMINING
                                      CRITICAL PATH


• Specify the individual activities.

• Determine the sequence of the activities.

• Draw the network diagram.

• Estimate the activity completion time.

• Identify the critical path.

• Update the CPM diagram.
Activit Preceden Normal time   Normal
y       ce       (week)        Cost (Rs)


A         -            3       300
B         A            3       30
C         A            7       420
D         A            9       720
E         D            5       250
F       B,C,E          6       320
G         F            4       400
H         F           13       780
I         G           10       1000
Total                          4220
4           7




1   2       5   6




        3
                    8
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
             4             7




  1      2             6
                 5


             3
                           8
TIME ESTIMATES


o Optimistic time (to) – It is the shortest time     in which the
   activity can be completed.
o Most likely time (tm) – It is the probable time
   required to perform the activity.
o Pessimistic time (tp) – It is the longest estimated time
   required to perform an activity.
o Expected time
  te = to + 4tm + tp
                6
STEPS IN PERT

1.   Identify the specific activities.

2.   Determine proper sequence of the activities.

3.   Construct the network diagram.

4.   Estimate the time required for each activity.

5.   Determine the critical path.

6.   Update the PERT chart.
Activity   Descrip Preced    Optimis Most      Pessimi Expecte
           tion    ence      tic time Likely   stic    d time
                                      time     time

A          Initial      -      12       16       26      17
           design
B          Survey      A        6        9       18      10
           market
C          Build       A        8       10       18      11
           prototype
D          Test        C        2        3       4       3
           prototype
E          Redesign    B,D      3        4       11      5
           ing
F          Market      E        6        8       10      8
           testing
G          Set up      F       15       20       25      20
           productio
           n
1   2       4      5      6       7




        3


                 A-B-E-F-G = 60
        A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT


• Expected project completion time.

• Probability of completion before a specified date.

• The critical path activities that directly impact the completion
  time.

• The activities that have slack time and that can lend resources
  to critical path activities.

• Activity start and end dates.
LIMITATIONS

• The PERT Formula Requires Too Much Work.
• The network charts tend to be large and unwieldy.
• Calculating the time estimates is very complex for all the
  activities.
• Updating of the project is time consuming and requires high
  costs.
• Emphasis is laid only on time factors and cost factors are
  neglected.
Difference between
                                            CPM & PERT

               CPM                                  PERT
• CPM works with fixed               • PERT works with probabilistic
deterministic time                   time
• CPM is useful for repetitive and   • PERT is useful for non repetitive
non complex projects with a          and complex projects with
certain degree of time estimates.    uncertain time estimates.

• CPM includes time-cost trade off. • PERT is restricted to time
                                     variable.

• CPM- for construction projects.    • PERT- used for R&D programs.
Thank You…

More Related Content

What's hot

Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Schedulingsaurabmi2
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 

What's hot (20)

Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Project monitoring
Project monitoringProject monitoring
Project monitoring
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project planning
Project planning Project planning
Project planning
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Network construction
Network construction  Network construction
Network construction
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 

Viewers also liked

Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi AnalysisAnkita Bharti
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniquesCjkayes CjKayes
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pertdjoufack
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GMohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit AnalysisSaurabh Sood
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhiQuery
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics IndustrySunil Singh
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and LogisticseTailing India
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and chinaKaushik Raja
 

Viewers also liked (20)

Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Social Cost Benefi Analysis
Social Cost Benefi AnalysisSocial Cost Benefi Analysis
Social Cost Benefi Analysis
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Project scheduling and control techniques
Project scheduling and control techniquesProject scheduling and control techniques
Project scheduling and control techniques
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Om edit
Om editOm edit
Om edit
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
 
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar GSocial Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
Social Cost Benefit Analysis - SCBA - Seminar by Mohan Kumar G
 
Social Cost Benefit Analysis
Social Cost Benefit AnalysisSocial Cost Benefit Analysis
Social Cost Benefit Analysis
 
Crashing in Project Management
Crashing in Project ManagementCrashing in Project Management
Crashing in Project Management
 
Delhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni ChannelDelhivery Data One- Powering Omni Channel
Delhivery Data One- Powering Omni Channel
 
E logistics
E logisticsE logistics
E logistics
 
16319859 Indian Logistics Industry
16319859 Indian Logistics Industry16319859 Indian Logistics Industry
16319859 Indian Logistics Industry
 
E logistics
E logisticsE logistics
E logistics
 
Gati : eCommerce and Logistics
Gati : eCommerce and LogisticsGati : eCommerce and Logistics
Gati : eCommerce and Logistics
 
Snapdeal vs amazon
Snapdeal vs amazonSnapdeal vs amazon
Snapdeal vs amazon
 
Logistics and ecommerce in india and china
Logistics and ecommerce in india and chinaLogistics and ecommerce in india and china
Logistics and ecommerce in india and china
 

Similar to Pert & cpm project management

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTsalsa moyara
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.pptalbert937613
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7Akihisa Akimoto
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 

Similar to Pert & cpm project management (20)

Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
Pb602 operation management chapter 7
Pb602  operation management chapter 7Pb602  operation management chapter 7
Pb602 operation management chapter 7
 
Project management
Project managementProject management
Project management
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 

Recently uploaded

Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 

Recently uploaded (20)

Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 

Pert & cpm project management

  • 1. PROJECT MANAGEMENT CPM & PERT TECHNIQUES
  • 2. FLOW OF PRESENTATION  INTRODUCTION  NETWORK PLANNING  ESTIMATING TIME  CPM  PERT
  • 3. Project Management Project • A project is an interrelated set of activities that has a definite starting and ending point and that results in a unique product or service. Project management • Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
  • 4. Network Planning Methods  Methods used for network planning are: CPM PERT  Managing a project with network planning methods involves four steps: 1. Describing the Project. 2. Diagramming the Network. 3. Estimating time of completion. 4. Monitoring Project Progress.
  • 5. Network Diagram Concepts • Activity • Precedence relationship • Successor • Event
  • 6. Guidelines for network diagram 1. Before an activity can begin, its preceding activities must be completed. 2. Arrows indicate logical precedence. 3. Flow of the diagram is from left to right. 4. Arrows should not intersect. 5. Dangling should be avoided.
  • 7. APPRAOCHES FOR NETWORK DIAGRAM ACTIVITY ON ARC(AOA): • Uses arcs to represent activities and nodes to represent events. • It is Event Oriented. 3 1 2 6 7 8 4 5
  • 8. DUMMY ACTIVITY AOA approach requires the addition of a Dummy Activity to clarify the precedence relationships between the two activities. It is a zero time activity and consumes no resources. Dummy Activity is used in two situations: 1) When two or more activities start and end at the same nodes 1 3 2
  • 9. 2) When two or more activities share the same precedence activity but not all the precedence are shared. 1 3 5 7 2 4 6
  • 10. ACTIVITY ON NODE(AON): Uses nodes to represent activities and arcs indicate precedence relationships between them. It is Activity Oriented.
  • 11. ESTIMATING TIME OF COMPLETION Planning the schedule of the project Time estimates include: 1) Total time for completion. 2) ES- Earliest start time: the earliest time at which the activity can start given that its precedent activities must be completed first. 3) EF-Earliest finish time: equals to the earliest start time for the activity plus the time required to complete the activity. 4) LF- Latest finish time: the latest time in which the activity can be completed without delaying the project. 5) LS- Latest start time: equal to the latest finish time minus the time required to complete the activity.
  • 12. 6) FORWARD PASS: The early start and early finish times are calculated by moving forward through the network and considering the predecessor activities Considers maximum 7) BACKWARD PASS: The latest start and finish times are calculated by moving backward through the network. Considers minimum 8) SLACK TIME: Slack time for an activity is the difference between its earliest and latest start time or between the earliest and latest finish time. Critical path is the path of activities having zero Slack time.
  • 13. A Simple Project Activity Immediate Expected Predecessor Time A - 5 B - 6 C A 4 D A, B 2
  • 15. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Difference Time
  • 16.
  • 17. CRITICAL PATH METHODS(CPM) HISTORY : It was developed by J.E.KELLY of REMINGTON-RAND and M.R.WALKER of DU PONT and the emphasis was on the trade-off between the cost of project and its overall completion time. The first test was made in 1958,when CPM was applied to the construction of a new chemical plant. DEFINITION: Critical path is the sequence of activities between a project’s start and finish that takes the longest time to complete.
  • 18. STEPS IN DETERMINING CRITICAL PATH • Specify the individual activities. • Determine the sequence of the activities. • Draw the network diagram. • Estimate the activity completion time. • Identify the critical path. • Update the CPM diagram.
  • 19. Activit Preceden Normal time Normal y ce (week) Cost (Rs) A - 3 300 B A 3 30 C A 7 420 D A 9 720 E D 5 250 F B,C,E 6 320 G F 4 400 H F 13 780 I G 10 1000 Total 4220
  • 20. 4 7 1 2 5 6 3 8
  • 21. Overhead cost as per the given data- Rs.50 Paths in the network diagram : A-D-F-G-I = 32 A-D-F-H = 31 A-C-F-H = 29 A-C-F-G-I = 30 A-B-E-F-H = 30 A-B-E-F-G-I = 31
  • 22. Critical path – A-D-F-G-I = 32 4 7 1 2 6 5 3 8
  • 23. TIME ESTIMATES o Optimistic time (to) – It is the shortest time in which the activity can be completed. o Most likely time (tm) – It is the probable time required to perform the activity. o Pessimistic time (tp) – It is the longest estimated time required to perform an activity. o Expected time te = to + 4tm + tp 6
  • 24. STEPS IN PERT 1. Identify the specific activities. 2. Determine proper sequence of the activities. 3. Construct the network diagram. 4. Estimate the time required for each activity. 5. Determine the critical path. 6. Update the PERT chart.
  • 25. Activity Descrip Preced Optimis Most Pessimi Expecte tion ence tic time Likely stic d time time time A Initial - 12 16 26 17 design B Survey A 6 9 18 10 market C Build A 8 10 18 11 prototype D Test C 2 3 4 3 prototype E Redesign B,D 3 4 11 5 ing F Market E 6 8 10 8 testing G Set up F 15 20 25 20 productio n
  • 26. 1 2 4 5 6 7 3 A-B-E-F-G = 60 A-C-D-E-F-G = 64 (CRITICAL PATH)
  • 27. Advantages of PERT • Expected project completion time. • Probability of completion before a specified date. • The critical path activities that directly impact the completion time. • The activities that have slack time and that can lend resources to critical path activities. • Activity start and end dates.
  • 28. LIMITATIONS • The PERT Formula Requires Too Much Work. • The network charts tend to be large and unwieldy. • Calculating the time estimates is very complex for all the activities. • Updating of the project is time consuming and requires high costs. • Emphasis is laid only on time factors and cost factors are neglected.
  • 29. Difference between CPM & PERT CPM PERT • CPM works with fixed • PERT works with probabilistic deterministic time time • CPM is useful for repetitive and • PERT is useful for non repetitive non complex projects with a and complex projects with certain degree of time estimates. uncertain time estimates. • CPM includes time-cost trade off. • PERT is restricted to time variable. • CPM- for construction projects. • PERT- used for R&D programs.