NFPA 1:43, Spraying, Dipping, andCoatingUsing Flammable or Combustible Materials
• Introduction
• NFPA 1:43
– Scope and Key Terms
– Location, Design, and Construction
– Ventilation
– Storage and Handling
– Fire Protection
– Operations, Maintenance, and Training
• Hands-On
– Spray Booth/System Walkthrough
▪ FFPC/NFPA 1, Fire Code
▪ NFPA 1:43, Spraying, Dipping , and Coating Using
Flammable and Combustible Materials
▪ NFPA 33, Standard for Spray Application Using
Flammable or Combustible Materials
✓ Compressed air atomization
✓ Airless or hydraulic atomization
✓ Electrostatic application methods
✓ Fluidized bed application methods
✓ Electrostatic fluidized bed application methods
✓ “Other” acceptable application means
Spray application of flammable liquids, combustible liquids, or combustible powders
by any of the following methods…
✓ Water-borne
✓ Water-based
✓ Water-reducible
…materials that contain flammable or combustible liquids or that
produce combustible deposits or residues.
Spray application of flammable liquids, combustible liquids, or combustible powders
by any of the following methods…
Ø Spray operations using less than 1 L in any 8-hour period
Ø Spray applications performed outdoors
Ø Portable spraying equipment
Ø Aerosol products up to 1 L not used repeatedly in same location
Ø Spray application of noncombustible materials
Ø The hazards of toxicity or industrial health and hygiene
Combustible Liquid
Flash point at or above 100˚F
Flammable Liquid
Flash point below 100˚F
Combustible Dust
A finely divided combustible particulate solid that presents a flash
fire hazard or explosion hazard when suspended in air or the
process-specific oxidizing medium over a range of concentrations
Spray Area
Any area in which dangerous quantities of flammable or
combustible vapors, mists, residues, dusts or deposits are present
due to the operation of spray processes
Spray Booth
Power-ventilated enclosure for spray application operation or
process that confines and limits escape of material being sprayed
Spray Room
A power ventilated full enclosed room used exclusively for open
spraying of flammable or combustible materials
Fluidized Bed
A chamber holding powder coating
material that is aerated from below to
form an air-supported, expanded cloud
of the powder
Electrostatic Fluidized Bed
Powder is electrically charged with a
charge opposite to that of the object
being coated
Not permitted in...
• Assembly, educational, institutional, residential
Exception…
• Separated by 2-hour rated construction and protected
by fire sprinkler system
Construction
Non-combustible, limited combustible materials
Smooth interior surface
Spray Rooms
Separated by 1-hour fire rated construction
Means of egress per NFPA 101
Conveyor openings as small as practical
Spray Booths
Separated from other operations by 3’, or 1-hour fire
rated construction
All parts readily accessible for cleaning
Maintain clear space of 3’ on all sides and above
Vehicles movement prohibited until spray ops cease and
room is properly ventilated
▪ Light Fixtures and
Panels
▪ Heat treated, laminated, wired,
hammered wired
▪ Sealed to confine vapors
▪ Separated from fixture (temps
NTE 200˚F)
▪ NFPA 70, NEC
▪ Class, Division, Zone
▪ Flammability/combustibility of
atmosphere
▪ Identifies location, proximity, isolation
from electrical hazards
▪ Protective measures vary based on
hazard class
• Classes
▪ Class I – flammable gas or vapors are or may be present
▪ Class II – presence of combustibledust
▪ Divisions
▪ Division 1 – vapors are always present or likely to be
▪ Division 2 – vapors are not normally present
▪ Zones
▪ Zone 0 – ignitable atmosphere is alwayspresent
▪ Zone 1 – ignitable atmosphere is likely to be present
▪ Zone 2 – ignitable atmosphere is not normally present
▪ Zone 20 – ignitable concentration of combustible dust is always present
▪ Zone 21 – ignitable concentration of combustible dust is likelypresent
▪ Zone 22 – ignitable concentration of combustible dust is not normally present
• Classes
▪ Class I – flammable gas or vapors are or may be present
▪ Class II – presence of combustibledust
▪ Divisions
▪ Division 1 – vapors are always present or likely to be
▪ Division 2 – vapors are not normally present
▪ Zones
▪ Zone 0 – ignitable atmosphere is alwayspresent
▪ Zone 1 – ignitable atmosphere is likely to be present
▪ Zone 2 – ignitable atmosphere is not normally present
▪ Zone 20 – ignitable concentration of combustible dust is always present
▪ Zone 21 – ignitable concentration of combustible dust is likelypresent
▪ Zone 22 – ignitable concentration of combustible dust is not normally present
hazard classification for
unenclosed spray areas
hazard classification for areas adjacent
to an open-face or open-front spray
booth/room
hazard classification areas
adjacent to an enclosed
spray booth/room
Portable Light Fixtures
Not permitted unless….
“Electrical wiring and utilization equipment that is located in the
spray are and is not subject to deposits of combustible residues shall
be listed for such exposure and shall be suitable for Class I, Division 1;
Class I, Zone 1; Class II, Division 1; or Zone 21 locations.”
Flexible Power Cords:
▪ Approved for extra-hard usage
▪ Equipped with grounding conductor
▪ Properly connected to terminals or conductors
▪ Supported by mechanical clamp, prevents strain and
easy replacement
▪ Explosion-proof or dust-tight seals provided at junction
boxes, fittings, enclosures
▪ Listed for composites of combustible residue
NFPA 91
Standard for Exhaust Systems for Air Conveying of
Vapors, Gases, Mists, and Noncombustible Particulate
Solids
Ventilation to be operational during spray operations
Make-up air adequate to compensate for exhaust air
Duct to outside of building
Follow most direct route to discharge
Not to penetrate fire walls
Directed away from fresh air intakes
Minimum 6’ from exterior wall or roof
Discharge away from combustible construction
Doors or panels available for inspection and maintenance
NFPA 30
Flammable and Combustible Liquids Code
For storage, handling, mixing of flammable and combustible
liquids
MAQ
Maximum Allowable Quantity
Control Area
An area in which hazardous materials are allowed to be stored,
used, dispensed, or handled in quantities not exceeding the
MAQ
Mixing Rooms
▪ Shall not exceed 150 sq.ft.
▪ Contain spill of rooms contents
▪ Continuously operating mechanical ventilation system
▪ Electrical area classification same as enclosed spray booth
▪ Automatic fire protection system
▪ Portable fire extinguishers
Shall be protected with an approved
automatic fire protection system.
▪ Automatic water sprinkler system (NFPA 13)
▪ Automatic foam water sprinkler system (NFPA 16)
▪ Carbon dioxide extinguishing system (NFPA 12)
▪ Dry chemical extinguishing system (NFPA 17)
▪ Gaseous agent extinguishing system (NFPA 2001)
Automatic water sprinkler system design considerations…
▪ Wet, dry, pre-action, deluge
▪ Extra Hazard Group II (NFPA 13:5.4.2)
▪ Sufficient to supply all heads likely to open without
depleting supply for firefighting operations
Extra Hazard Grp. II -
“…moderate to substantial amounts of
flammable or combustible liquids or
occupancies where shielding of
combustibles is extensive.”
Extra Hazard Grp. II -
“…moderate to substantial amounts of
flammable or combustible liquids or
occupancies where shielding of
combustibles is extensive.”
System activation sequence –
Activatelocalalarm
Transmit alarm signal
Shut down materialdelivery system
Shut down spray applicationoperations
Stop all conveyors
▪ Controlled by separate
valve
▪ Heads protected from
overspray residue
▪ Covered by cellophane or
thin paper bags
▪ Coated heads to be
replaced
NFPA 10
Standard for Portable Fire Extinguishers
Other requirements:
For automated powder application and liquid electrostatic
spray application, flame detection required.
Responsibility of the users
General housekeeping practices
Free of excess residue
Replacement of filters
Daily debris clean-up
Contaminated clothing in metal locker
Training of Operators:
Safety and health hazards
Operational, maintenance, emergency procedures
Constant awareness
Safe handling, storage, use of materials
Use, maintenance, storage of PPE and equipment
NFPA 1:43, Spraying, Dipping, andCoatingUsing Flammable or Combustible Materials

Mais conteúdo relacionado

Mais procurados

7SJ66 BCU Protective Relay
7SJ66 BCU Protective Relay7SJ66 BCU Protective Relay
7SJ66 BCU Protective Relayashwini reliserv
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classificationdebuddit
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
 
IP protection or ingress protection
IP protection or ingress protectionIP protection or ingress protection
IP protection or ingress protectionKamran Hassan
 
Rule 1080: Personal Protective Equipment (PPE) OSH Standards
Rule 1080: Personal Protective Equipment (PPE) OSH Standards Rule 1080: Personal Protective Equipment (PPE) OSH Standards
Rule 1080: Personal Protective Equipment (PPE) OSH Standards Nicely Jane Eleccion
 
Electrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsElectrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsMohd Azmatullah
 
Complete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the WorkplaceComplete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the Workplacehudsonelectrical
 
Soldering Training PPT
Soldering Training PPTSoldering Training PPT
Soldering Training PPTANANT PATIL
 
Ehouse Specification Sample
Ehouse Specification SampleEhouse Specification Sample
Ehouse Specification SampleBlas Bigotti
 

Mais procurados (15)

Esd protection
Esd protectionEsd protection
Esd protection
 
7SJ66 BCU Protective Relay
7SJ66 BCU Protective Relay7SJ66 BCU Protective Relay
7SJ66 BCU Protective Relay
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Electrical Safety by OSHA
Electrical Safety by OSHAElectrical Safety by OSHA
Electrical Safety by OSHA
 
IP protection or ingress protection
IP protection or ingress protectionIP protection or ingress protection
IP protection or ingress protection
 
Ingress protection
Ingress protectionIngress protection
Ingress protection
 
Rule 1080: Personal Protective Equipment (PPE) OSH Standards
Rule 1080: Personal Protective Equipment (PPE) OSH Standards Rule 1080: Personal Protective Equipment (PPE) OSH Standards
Rule 1080: Personal Protective Equipment (PPE) OSH Standards
 
Electrical Safety and Risk Assessments
Electrical Safety and Risk AssessmentsElectrical Safety and Risk Assessments
Electrical Safety and Risk Assessments
 
Complete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the WorkplaceComplete Guide to Electrical Safety in the Workplace
Complete Guide to Electrical Safety in the Workplace
 
Soldering Training PPT
Soldering Training PPTSoldering Training PPT
Soldering Training PPT
 
Nfpa 557
Nfpa 557Nfpa 557
Nfpa 557
 
Portable Appliance Testing
Portable Appliance TestingPortable Appliance Testing
Portable Appliance Testing
 
IP Ratings & Ingress Protection
IP Ratings & Ingress ProtectionIP Ratings & Ingress Protection
IP Ratings & Ingress Protection
 
Ehouse Specification Sample
Ehouse Specification SampleEhouse Specification Sample
Ehouse Specification Sample
 

Semelhante a Spray Applications and the Fire Code

Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Kathiresan Nadar
 
Basic fire safety
Basic fire safety Basic fire safety
Basic fire safety umar farooq
 
Basic Fire Safety
Basic Fire Safety Basic Fire Safety
Basic Fire Safety umar farooq
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Electrical maintenance in Hazardous area
Electrical maintenance in Hazardous area Electrical maintenance in Hazardous area
Electrical maintenance in Hazardous area BHAGWAN PRASAD
 
Arkansas STEPS Network Presentation - Classified Areas
Arkansas STEPS Network Presentation - Classified AreasArkansas STEPS Network Presentation - Classified Areas
Arkansas STEPS Network Presentation - Classified AreasArkansas STEPS Network
 
HAC - Hazardous Area Classification
HAC - Hazardous Area ClassificationHAC - Hazardous Area Classification
HAC - Hazardous Area ClassificationHarkishan Prajapati
 
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxFIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxMEP ENGINEER'S SERVICES
 
Fire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.pptFire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.pptBenounaFert
 
Fire Protection and Prevention Training by RoofSafe
Fire Protection and Prevention Training by RoofSafeFire Protection and Prevention Training by RoofSafe
Fire Protection and Prevention Training by RoofSafeAtlantic Training, LLC.
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...AnkitaGorhe
 
Dafo FORREX - Conveyor Belt Proactive Fire Protection System
Dafo FORREX - Conveyor Belt Proactive Fire Protection SystemDafo FORREX - Conveyor Belt Proactive Fire Protection System
Dafo FORREX - Conveyor Belt Proactive Fire Protection SystemPedro Perim
 
Hazardous Area Classification in Oil & Gas Industry.pdf
Hazardous Area Classification in Oil & Gas Industry.pdfHazardous Area Classification in Oil & Gas Industry.pdf
Hazardous Area Classification in Oil & Gas Industry.pdfjoshwiksai
 
Confined space (Student version)(1)(2).pptx
Confined space (Student version)(1)(2).pptxConfined space (Student version)(1)(2).pptx
Confined space (Student version)(1)(2).pptxKuenStock
 
Fire prevention.ppt
Fire prevention.pptFire prevention.ppt
Fire prevention.pptSahl Ahmed
 

Semelhante a Spray Applications and the Fire Code (20)

Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...Hazardous area classification and Elecrtical, Instrument and Process Engineer...
Hazardous area classification and Elecrtical, Instrument and Process Engineer...
 
Basic fire safety
Basic fire safety Basic fire safety
Basic fire safety
 
Basic Fire Safety
Basic Fire Safety Basic Fire Safety
Basic Fire Safety
 
Chapter 06
Chapter 06Chapter 06
Chapter 06
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Hazardous classified locations
Hazardous classified locationsHazardous classified locations
Hazardous classified locations
 
Electrical maintenance in Hazardous area
Electrical maintenance in Hazardous area Electrical maintenance in Hazardous area
Electrical maintenance in Hazardous area
 
Safety For Special Work
Safety For Special WorkSafety For Special Work
Safety For Special Work
 
Arkansas STEPS Network Presentation - Classified Areas
Arkansas STEPS Network Presentation - Classified AreasArkansas STEPS Network Presentation - Classified Areas
Arkansas STEPS Network Presentation - Classified Areas
 
HAC - Hazardous Area Classification
HAC - Hazardous Area ClassificationHAC - Hazardous Area Classification
HAC - Hazardous Area Classification
 
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptxFIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
FIRE FIGHTING NOTES PART 01 BY ER. EZAZUL HAQUE SIDDIQUE pptx
 
BFP Basics.pptx
BFP Basics.pptxBFP Basics.pptx
BFP Basics.pptx
 
Fire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.pptFire Prevention & Protection or Fire Fighting.ppt
Fire Prevention & Protection or Fire Fighting.ppt
 
Fire Protection and Prevention Training by RoofSafe
Fire Protection and Prevention Training by RoofSafeFire Protection and Prevention Training by RoofSafe
Fire Protection and Prevention Training by RoofSafe
 
Fire protection system...
Fire protection system...Fire protection system...
Fire protection system...
 
Dafo FORREX - Conveyor Belt Proactive Fire Protection System
Dafo FORREX - Conveyor Belt Proactive Fire Protection SystemDafo FORREX - Conveyor Belt Proactive Fire Protection System
Dafo FORREX - Conveyor Belt Proactive Fire Protection System
 
Hazardous Area Classification in Oil & Gas Industry.pdf
Hazardous Area Classification in Oil & Gas Industry.pdfHazardous Area Classification in Oil & Gas Industry.pdf
Hazardous Area Classification in Oil & Gas Industry.pdf
 
Confined space (Student version)(1)(2).pptx
Confined space (Student version)(1)(2).pptxConfined space (Student version)(1)(2).pptx
Confined space (Student version)(1)(2).pptx
 
4072721.ppt
4072721.ppt4072721.ppt
4072721.ppt
 
Fire prevention.ppt
Fire prevention.pptFire prevention.ppt
Fire prevention.ppt
 

Mais de Aaron Johnson

Building an Effective Fire Prevention Organization
Building an Effective Fire Prevention OrganizationBuilding an Effective Fire Prevention Organization
Building an Effective Fire Prevention OrganizationAaron Johnson
 
5 Books to Read in 2019
5 Books to Read in 20195 Books to Read in 2019
5 Books to Read in 2019Aaron Johnson
 
Successful Company Level Inspection Programs
Successful Company Level Inspection ProgramsSuccessful Company Level Inspection Programs
Successful Company Level Inspection ProgramsAaron Johnson
 
Compartmentation and Fire Doors
Compartmentation and Fire DoorsCompartmentation and Fire Doors
Compartmentation and Fire DoorsAaron Johnson
 
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsBasic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsAaron Johnson
 
7 Habits of Highly Effective Fire Prevention Organizations
7 Habits of Highly Effective Fire Prevention Organizations7 Habits of Highly Effective Fire Prevention Organizations
7 Habits of Highly Effective Fire Prevention OrganizationsAaron Johnson
 
Fire Prevention Organization: Assessing Staffing Needs
Fire Prevention Organization: Assessing Staffing NeedsFire Prevention Organization: Assessing Staffing Needs
Fire Prevention Organization: Assessing Staffing NeedsAaron Johnson
 
Are You At Risk? Conducting Fire Risk Assessments to Mitigate Loss
Are You At Risk? Conducting Fire Risk Assessments to Mitigate LossAre You At Risk? Conducting Fire Risk Assessments to Mitigate Loss
Are You At Risk? Conducting Fire Risk Assessments to Mitigate LossAaron Johnson
 
3 Step Risk Assessment
3 Step Risk Assessment3 Step Risk Assessment
3 Step Risk AssessmentAaron Johnson
 
ARFF for Structural Fire Departments
ARFF for Structural Fire DepartmentsARFF for Structural Fire Departments
ARFF for Structural Fire DepartmentsAaron Johnson
 
Understanding Building Construction and Loads
Understanding Building Construction and LoadsUnderstanding Building Construction and Loads
Understanding Building Construction and LoadsAaron Johnson
 
West Helena Chemical Explosion
West Helena Chemical ExplosionWest Helena Chemical Explosion
West Helena Chemical ExplosionAaron Johnson
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work OperationsAaron Johnson
 
Fighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsFighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsAaron Johnson
 
Hoarding in Senior Populations
Hoarding in Senior PopulationsHoarding in Senior Populations
Hoarding in Senior PopulationsAaron Johnson
 
Hoarding In Senior Populations
Hoarding In Senior PopulationsHoarding In Senior Populations
Hoarding In Senior PopulationsAaron Johnson
 
Fire Safety in Assisted Living Facilities
Fire Safety in Assisted Living FacilitiesFire Safety in Assisted Living Facilities
Fire Safety in Assisted Living FacilitiesAaron Johnson
 
Recognizing the 5 Most Common Violations
Recognizing the 5 Most Common ViolationsRecognizing the 5 Most Common Violations
Recognizing the 5 Most Common ViolationsAaron Johnson
 
8 Points - Family Traditions
8 Points - Family Traditions8 Points - Family Traditions
8 Points - Family TraditionsAaron Johnson
 
Juvenile Fire Setter Intervention Program
Juvenile Fire Setter Intervention ProgramJuvenile Fire Setter Intervention Program
Juvenile Fire Setter Intervention ProgramAaron Johnson
 

Mais de Aaron Johnson (20)

Building an Effective Fire Prevention Organization
Building an Effective Fire Prevention OrganizationBuilding an Effective Fire Prevention Organization
Building an Effective Fire Prevention Organization
 
5 Books to Read in 2019
5 Books to Read in 20195 Books to Read in 2019
5 Books to Read in 2019
 
Successful Company Level Inspection Programs
Successful Company Level Inspection ProgramsSuccessful Company Level Inspection Programs
Successful Company Level Inspection Programs
 
Compartmentation and Fire Doors
Compartmentation and Fire DoorsCompartmentation and Fire Doors
Compartmentation and Fire Doors
 
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity ClassificationsBasic Guide to NFPA 13 Occupancy and Commodity Classifications
Basic Guide to NFPA 13 Occupancy and Commodity Classifications
 
7 Habits of Highly Effective Fire Prevention Organizations
7 Habits of Highly Effective Fire Prevention Organizations7 Habits of Highly Effective Fire Prevention Organizations
7 Habits of Highly Effective Fire Prevention Organizations
 
Fire Prevention Organization: Assessing Staffing Needs
Fire Prevention Organization: Assessing Staffing NeedsFire Prevention Organization: Assessing Staffing Needs
Fire Prevention Organization: Assessing Staffing Needs
 
Are You At Risk? Conducting Fire Risk Assessments to Mitigate Loss
Are You At Risk? Conducting Fire Risk Assessments to Mitigate LossAre You At Risk? Conducting Fire Risk Assessments to Mitigate Loss
Are You At Risk? Conducting Fire Risk Assessments to Mitigate Loss
 
3 Step Risk Assessment
3 Step Risk Assessment3 Step Risk Assessment
3 Step Risk Assessment
 
ARFF for Structural Fire Departments
ARFF for Structural Fire DepartmentsARFF for Structural Fire Departments
ARFF for Structural Fire Departments
 
Understanding Building Construction and Loads
Understanding Building Construction and LoadsUnderstanding Building Construction and Loads
Understanding Building Construction and Loads
 
West Helena Chemical Explosion
West Helena Chemical ExplosionWest Helena Chemical Explosion
West Helena Chemical Explosion
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work Operations
 
Fighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered BuildingsFighting Fires in Sprinklered Buildings
Fighting Fires in Sprinklered Buildings
 
Hoarding in Senior Populations
Hoarding in Senior PopulationsHoarding in Senior Populations
Hoarding in Senior Populations
 
Hoarding In Senior Populations
Hoarding In Senior PopulationsHoarding In Senior Populations
Hoarding In Senior Populations
 
Fire Safety in Assisted Living Facilities
Fire Safety in Assisted Living FacilitiesFire Safety in Assisted Living Facilities
Fire Safety in Assisted Living Facilities
 
Recognizing the 5 Most Common Violations
Recognizing the 5 Most Common ViolationsRecognizing the 5 Most Common Violations
Recognizing the 5 Most Common Violations
 
8 Points - Family Traditions
8 Points - Family Traditions8 Points - Family Traditions
8 Points - Family Traditions
 
Juvenile Fire Setter Intervention Program
Juvenile Fire Setter Intervention ProgramJuvenile Fire Setter Intervention Program
Juvenile Fire Setter Intervention Program
 

Último

CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 

Último (20)

CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 

Spray Applications and the Fire Code

  • 1. NFPA 1:43, Spraying, Dipping, andCoatingUsing Flammable or Combustible Materials
  • 2. • Introduction • NFPA 1:43 – Scope and Key Terms – Location, Design, and Construction – Ventilation – Storage and Handling – Fire Protection – Operations, Maintenance, and Training • Hands-On – Spray Booth/System Walkthrough
  • 3. ▪ FFPC/NFPA 1, Fire Code ▪ NFPA 1:43, Spraying, Dipping , and Coating Using Flammable and Combustible Materials ▪ NFPA 33, Standard for Spray Application Using Flammable or Combustible Materials
  • 4. ✓ Compressed air atomization ✓ Airless or hydraulic atomization ✓ Electrostatic application methods ✓ Fluidized bed application methods ✓ Electrostatic fluidized bed application methods ✓ “Other” acceptable application means Spray application of flammable liquids, combustible liquids, or combustible powders by any of the following methods…
  • 5. ✓ Water-borne ✓ Water-based ✓ Water-reducible …materials that contain flammable or combustible liquids or that produce combustible deposits or residues. Spray application of flammable liquids, combustible liquids, or combustible powders by any of the following methods…
  • 6. Ø Spray operations using less than 1 L in any 8-hour period Ø Spray applications performed outdoors Ø Portable spraying equipment Ø Aerosol products up to 1 L not used repeatedly in same location Ø Spray application of noncombustible materials Ø The hazards of toxicity or industrial health and hygiene
  • 7. Combustible Liquid Flash point at or above 100˚F Flammable Liquid Flash point below 100˚F
  • 8. Combustible Dust A finely divided combustible particulate solid that presents a flash fire hazard or explosion hazard when suspended in air or the process-specific oxidizing medium over a range of concentrations
  • 9. Spray Area Any area in which dangerous quantities of flammable or combustible vapors, mists, residues, dusts or deposits are present due to the operation of spray processes Spray Booth Power-ventilated enclosure for spray application operation or process that confines and limits escape of material being sprayed Spray Room A power ventilated full enclosed room used exclusively for open spraying of flammable or combustible materials
  • 10.
  • 11. Fluidized Bed A chamber holding powder coating material that is aerated from below to form an air-supported, expanded cloud of the powder Electrostatic Fluidized Bed Powder is electrically charged with a charge opposite to that of the object being coated
  • 12. Not permitted in... • Assembly, educational, institutional, residential Exception… • Separated by 2-hour rated construction and protected by fire sprinkler system
  • 13. Construction Non-combustible, limited combustible materials Smooth interior surface
  • 14. Spray Rooms Separated by 1-hour fire rated construction Means of egress per NFPA 101 Conveyor openings as small as practical
  • 15. Spray Booths Separated from other operations by 3’, or 1-hour fire rated construction All parts readily accessible for cleaning Maintain clear space of 3’ on all sides and above Vehicles movement prohibited until spray ops cease and room is properly ventilated
  • 16. ▪ Light Fixtures and Panels ▪ Heat treated, laminated, wired, hammered wired ▪ Sealed to confine vapors ▪ Separated from fixture (temps NTE 200˚F)
  • 17. ▪ NFPA 70, NEC ▪ Class, Division, Zone ▪ Flammability/combustibility of atmosphere ▪ Identifies location, proximity, isolation from electrical hazards ▪ Protective measures vary based on hazard class
  • 18. • Classes ▪ Class I – flammable gas or vapors are or may be present ▪ Class II – presence of combustibledust ▪ Divisions ▪ Division 1 – vapors are always present or likely to be ▪ Division 2 – vapors are not normally present ▪ Zones ▪ Zone 0 – ignitable atmosphere is alwayspresent ▪ Zone 1 – ignitable atmosphere is likely to be present ▪ Zone 2 – ignitable atmosphere is not normally present ▪ Zone 20 – ignitable concentration of combustible dust is always present ▪ Zone 21 – ignitable concentration of combustible dust is likelypresent ▪ Zone 22 – ignitable concentration of combustible dust is not normally present
  • 19. • Classes ▪ Class I – flammable gas or vapors are or may be present ▪ Class II – presence of combustibledust ▪ Divisions ▪ Division 1 – vapors are always present or likely to be ▪ Division 2 – vapors are not normally present ▪ Zones ▪ Zone 0 – ignitable atmosphere is alwayspresent ▪ Zone 1 – ignitable atmosphere is likely to be present ▪ Zone 2 – ignitable atmosphere is not normally present ▪ Zone 20 – ignitable concentration of combustible dust is always present ▪ Zone 21 – ignitable concentration of combustible dust is likelypresent ▪ Zone 22 – ignitable concentration of combustible dust is not normally present
  • 21. hazard classification for areas adjacent to an open-face or open-front spray booth/room
  • 22. hazard classification areas adjacent to an enclosed spray booth/room
  • 23.
  • 24. Portable Light Fixtures Not permitted unless…. “Electrical wiring and utilization equipment that is located in the spray are and is not subject to deposits of combustible residues shall be listed for such exposure and shall be suitable for Class I, Division 1; Class I, Zone 1; Class II, Division 1; or Zone 21 locations.”
  • 25. Flexible Power Cords: ▪ Approved for extra-hard usage ▪ Equipped with grounding conductor ▪ Properly connected to terminals or conductors ▪ Supported by mechanical clamp, prevents strain and easy replacement ▪ Explosion-proof or dust-tight seals provided at junction boxes, fittings, enclosures ▪ Listed for composites of combustible residue
  • 26. NFPA 91 Standard for Exhaust Systems for Air Conveying of Vapors, Gases, Mists, and Noncombustible Particulate Solids
  • 27.
  • 28. Ventilation to be operational during spray operations Make-up air adequate to compensate for exhaust air Duct to outside of building Follow most direct route to discharge Not to penetrate fire walls Directed away from fresh air intakes Minimum 6’ from exterior wall or roof Discharge away from combustible construction Doors or panels available for inspection and maintenance
  • 29. NFPA 30 Flammable and Combustible Liquids Code For storage, handling, mixing of flammable and combustible liquids
  • 30. MAQ Maximum Allowable Quantity Control Area An area in which hazardous materials are allowed to be stored, used, dispensed, or handled in quantities not exceeding the MAQ
  • 31.
  • 32. Mixing Rooms ▪ Shall not exceed 150 sq.ft. ▪ Contain spill of rooms contents ▪ Continuously operating mechanical ventilation system ▪ Electrical area classification same as enclosed spray booth ▪ Automatic fire protection system ▪ Portable fire extinguishers
  • 33. Shall be protected with an approved automatic fire protection system.
  • 34. ▪ Automatic water sprinkler system (NFPA 13) ▪ Automatic foam water sprinkler system (NFPA 16) ▪ Carbon dioxide extinguishing system (NFPA 12) ▪ Dry chemical extinguishing system (NFPA 17) ▪ Gaseous agent extinguishing system (NFPA 2001)
  • 35. Automatic water sprinkler system design considerations… ▪ Wet, dry, pre-action, deluge ▪ Extra Hazard Group II (NFPA 13:5.4.2) ▪ Sufficient to supply all heads likely to open without depleting supply for firefighting operations
  • 36. Extra Hazard Grp. II - “…moderate to substantial amounts of flammable or combustible liquids or occupancies where shielding of combustibles is extensive.”
  • 37. Extra Hazard Grp. II - “…moderate to substantial amounts of flammable or combustible liquids or occupancies where shielding of combustibles is extensive.”
  • 38. System activation sequence – Activatelocalalarm Transmit alarm signal Shut down materialdelivery system Shut down spray applicationoperations Stop all conveyors
  • 39. ▪ Controlled by separate valve ▪ Heads protected from overspray residue ▪ Covered by cellophane or thin paper bags ▪ Coated heads to be replaced
  • 40. NFPA 10 Standard for Portable Fire Extinguishers
  • 41. Other requirements: For automated powder application and liquid electrostatic spray application, flame detection required.
  • 42. Responsibility of the users General housekeeping practices Free of excess residue Replacement of filters Daily debris clean-up Contaminated clothing in metal locker
  • 43. Training of Operators: Safety and health hazards Operational, maintenance, emergency procedures Constant awareness Safe handling, storage, use of materials Use, maintenance, storage of PPE and equipment
  • 44. NFPA 1:43, Spraying, Dipping, andCoatingUsing Flammable or Combustible Materials