Schedule agreement release processing

As of SAP R/3 Release 4.5

Overall process

In simplified terms, scheduling agreement processing consists of three main steps:


Material requirements planning
Release generation (FRC/JIT)
Output/Transmission of releases




1. Material Requirements Planning

The current overall delivery schedule for a material that is procured via scheduling
agreement releases changes continuously during an MRP run due to the
requirements for that material (dependent requirements and so on). This results in
quantities and delivery dates that are to be transmitted to the vendor in the form of
releases against the relevant scheduling agreement. Therefore the field EKPO-
ETDRK will get a value unequal “space”. Is the value 1, then this does mean that the
delivery schedule was created via MRP, is the value 2, then the delivery schedule
was created via ME38.
The prerequisite for automatic creation of schedule lines during requirements
planning is that a scheduling agreement is flagged as MRP-relevant in the source list.
You can do this in the Purchasing menu: Master data -> Source list -> Maintain
(transaction ME01).
You must maintain a record for the material here and in this record, the field ‘MRP’
must contain the indicator ‘2’. The schedule lines created by the MRP run are
assigned creation indicator ‘B’ and are contained in table EKET in field ESTKZ.
In contrast, manually created schedule lines are assigned creation indicator ‘R’.
Another difference between manual schedule lines and schedule lines from
requirements planning is that you can only enter a time for manual schedule lines.
We will not go into more detail on the individual steps of MRP here.
Schedule agreement release processing                                               -2-




2. Release types / Release generation

Basically, release generation ‘translates’ the current overall delivery schedule in the
system into a release. Releases inform the vendor of which quantities of a material
are to be delivered on which date. The individual releases are recorded using the
release documentation and can therefore be displayed at any time. You can only
create releases for scheduling agreements with release documentation. (Document
type in the standard system is LPA or the Release docu. indicator must be flagged in
Customizing for Purchasing -> Scheduling Agreement -> Define Document Types.) If
a scheduling agreement was created under these customizing settings, the field
EKKO-LPHIS has got the value “X”. Via this check you see very fast if you are
working with LPA or LP.




Note:
There is no release documentation for stock transport scheduling agreements. Even
if the Release docu. indicator is flagged for document type LU in Customizing, it has
no effect.
There are the following types of releases



•   Forecast delivery schedule (FRC)
    Provides the vendor with information over the longer term about which quantities
    of a material are to be delivered on which date. Delivery dates are usually
    specified as calendar months or weeks.

•   JIT delivery schedule (JIT)
    Provides the vendor with information about which quantities of a material are to
    be delivered at which point in time in the near future. Exact delivery dates
    (calendar days) or even delivery times are usually specified. The suggested
    quantity for goods receipts is based on the last release transmitted. If you use
    both types of release, the system suggests the data in the JIT schedule. If you
    use only the forecast schedule, the system suggests the data in the forecast
    schedule.


    Note: In order to work with JIT delivery schedules, you must have set the JIT
    schedule indicator in the material master record (MARC-FABKZ) and in the
    scheduling agreement item. (You do this on the ‘Purchasing’ view or on the ‘MRP
    2’ view of the material master record.) This indicator controls whether JIT delivery
    schedules can be created for a material in addition to forecast schedules.
Schedule agreement release processing                                                -3-


Possible cause of error: Customer cannot create any JIT schedules:
If you have set the JIT schedule indicator in the material master record and the
scheduling agreement had, however, already been created, you cannot create any
JIT schedules for this scheduling agreement. Check if there are any change
documents in the material master record for the JIT schedule indicator and check
when the scheduling agreement item was created.
You can use creation profiles to influence the quantities and dates transmitted. You
configure a creation profile in Customizing for Purchasing by choosing Scheduling
Agreement -> Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu. (transaction
OMUP). We will go into more detail on these Customizing settings later.
The system stores a transmitted release with a release number and includes the
document in the release ‘history’. The system then generates the next release of that
particular release type with a number increased by one. Forecast schedules and JIT
schedules have separate number ranges.


Table:

EKEK (Header Data for Scheduling Agreement Releases)
EKEH (Scheduling Agreement Release Documentation)
When creating releases, the system reads extensive control parameters from the
creation profile.



Creating a release:
You can create releases using a report (RM06EFLB up to Rel. 4.5X) (intended for
regular releases). Please see also note 182210 which describes which report is valid
for the appropriate Release.


You can also create releases manually. You can do this from the scheduling
agreement delivery schedule by choosing Edit -> Generate JIT sched. or Generate
forc. schd. as well as from the item overview screen of transaction ME38 by choosing
Edit -> Generate JIT sched. or Generate forc. schd.



Note:
You must note that the system does NOT carry out a tolerance check or backlog
determination when you manually create releases. The system only aggregates
scheduled quantities. The backlog determination is only active if it is defined in the
creation profile. When creating releases the function module
ME_CREATE_SCHEDULE_DOC will be called (this is independent if transaction
ME84 oder ME38 is used). If a creation profile is maintained in the scheduling
agreement item and in this creation profile the flag “Determine backlog” is set, then
the routine Backlog_IM_Requirements will be called.
Schedule agreement release processing                                                -4-


To check how a release was created (e.g. via report RM06EFLB or via transaction
ME38) it is possible to look in table EKEK. In field STAAB there could be the
following entries:

Space: this does mean via ME38
1: this does mean via ME84
2: this does mean MDXX (transactions like MD03, MD04)


Release creation basically consists of the following steps:


   •   Conversion of the current overall delivery schedule in the system into
       aggregated release dates and quantities where applicable (see also ‘Creation
       Profile’ for more information on this)
   •   Creation of a release (FRC/JIT) in accordance with a particular creation
       strategy (for example, next creation date reached, current overall delivery
       schedule has changed). You use both the ‘General parameters’ and the
       ‘Creation periodicity’ in the creation profile to control this. You can prevent
       release creation based on a change in the current overall schedule by means
       of a tolerance check, if necessary, so that minor changes compared to the last
       release do not necessarily lead to the creation of a new release.
   •   Optional calculation or statement of backlogs and immediate requirements, if
       this function is active.
   •   In the case of release creation ‘Based on changes’, optional tolerance check
       that only allows creation of a release only if changes that lie outside a defined
       tolerance limit have occurred since transmission of the last release


If the system creates a release, it also creates a message record at the same time.
This message record is a prerequisite for the output and transmission of the release
to the vendor.
Schedule agreement release processing                                               -5-




Output / transmission of releases

You can process the message records for the newly created releases either
immediately or in a subsequent collective output. Messages are output immediately if
transmission time ‘4’ is set.

Collective processing is possible if you are working with transmission time ‘1’ (output
via RSNAST00) or ‘3’ (output via the application-specific output program).

Attention: RSNAST00 can process only datasets with dispatch time 1 and 2. The
report does not process data sets with dispatch time 4.

You create message condition records in the Purchasing menu by choosing Master
data -> Messages -> Sch. agmt. schedule -> Create.

When the system outputs a message (function module
ME_UPDATE_FROM_PRINTING is therefore responsible), certain updates take
place that designate the release as ‘completed and output’. Therefore it is necessary
that in customizing in transaction OMQP the field for “Update print-dependant
data”for the appropriate message type is set (T161N-DRUAB). If the system has not
yet output a release as a message, any generation of a further release will cause the
last release, which the system has not yet output, to be overwritten.

After the system has output the release using the main message type (see below for
an explanation of this), the fields ‘Output date’ and ‘Output time’ are filled.
Another important detail that is updated at this point in time is the resetting of the
‘Changed’ indicator (EKPO-ETDRK is changed into space) in the scheduling
agreement item. This means that after a release is output, the scheduling agreement
item in question is no longer regarded as ‘Changed’ (as regards the overall delivery
schedule in the system) until you process the schedule again manually or by means
of the MRP run.

The system can create a separate message for each release for a scheduling
agreement item. This means that the vendor receives one document for each
release. This lets you output releases individually or re-output releases that have
already been transmitted.
In order to have the system create a separate message for each release, you must
set the indicator ‘Rel. mess.’ (message per release) in Customizing for Purchasing,
by choosing Messages -> Message Determination Schemas -> Define Message
Schemas for Scheduling Agreement Release/Expediter -> Assign Schema to
Scheduling Agreement Release/Expediter.

If the R/3 system is customized in that manner then we talk about ”message
determination on release level”. With this customizing setting NO change messages
can be created. Technical explanation for that: Change messages can only be
formed when in table NAST already an entry exists with the same objectkey. This
means you can only work with change messages when in customizing the message
determination is maintained at “header level”. Messages created under “message
“determination at release level” can be displayed in transaction ME38 by selecting
Schedule agreement release processing                                                 -6-


the relevant item and choosing SA Release docu., then selecting the relevant release
number and choosing Messages per release, NOT via ME38 -> Header ->
Messages.



Note:
You can only output messages created at release level via the Purchasing menu, by
choosing Outline agreement -> Scheduling agreement -> Delivery schedule ->
Print/transmit (transaction ME9E).

If there are messages for the scheduling agreement that have not been output and
you subsequently set the ‘Messages per release’ indicator, you can still find the
messages that have not been output via Header -> Messages. You will find newly
created messages via the release documentation (ME38 -> select the relevant item -
> SA release docu. -> select the relevant release -> Messages per release).

The system stores the messages for a release in table NAST using the following key:

Object key (this means the document number)
Item
Release type (FRC or JIT)
Release number


Prerequisites for the transmission of scheduling agreements releases as messages
to the vendor:
As of Release 4.0, you must define exactly one message type as the ‘Main message
type’ for each release type in Customizing for MM, Message Determination for
Scheduling Agreement Schedules. Field ‘U’ (Update print-dependent data) must be
flagged for the message type in question in Customizing for Materials Management -
> Purchasing -> Messages -> Output Control -> Message Types -> Define Message
Types for Scheduling Agreement


Alle Abrufe müssen immer mit der Hauptnachrichtenart erstellt werden, da das
System sonst die druckabhängigen Daten nicht aktualisiert. Dies ist insbesondere
dann wichtig, wenn Sie mit verschiedenen Nachrichtenarten arbeiten.

Set the flag „Update print-dependant data“ or not?
In Release 4.6B you will get an error message if you try to set this flag several for the
same operation type.
In Release 4.6C you get a warning message. Background for this different
systembehaviour is the following:
If you are working with message determination on “release level” then several
message types for one operation could be flagged. If you work with message
determination at “header level” then only one message type per operation should be
flagged.
Schedule agreement release processing                                             -7-




Recommendation:
You must always use the main message type to create all releases, otherwise the
system does not update the print-dependent data. This is particularly important if
you use several different message types (e.g. main message with medium 6 for EDI
and another message for medium 1 for printing which is not maintained as main
message.


You can only set the indicator once for each release type. Operation ‘9’ corresponds
to the forecast delivery schedule, and operation ‘A’ corresponds to the JIT delivery
schedule.
Example (transaction OMQP):

Operations for Message Type U (Update Print-Dependent Data)

9       LPH1         x       main message type for FRC
9       LPH2                 additional message type
A       LPJ1         x       main message type for JIT
A       LPJ2                 additional message type

After determination of the message type that updates the print-dependent data for
each release type (that is, for each operation), you must make sure that releases are
always created with this message type (called ‘main message type’).
You are allowed to create a second message type in parallel, whereby the main
message type should be the one that is created first (such as LPH2 as the second
message type for LPH1).


Please note:
Messages which aren’t the main message are called auxilliary messages. These are
all messages which have not set the flag for “update print-dependant data”.
Auxilliary messages must always be output before the main message is output, when
you work with message determination at “header level”.

After determination of the message type that updates the print-dependent data for
each release type (that is, for each operation), you must make sure that releases are
always created with this message type (called ‘main message type’).
You are allowed to create a second message type in parallel, whereby the main
message type should be the one that is created first (such as LPH2 as the second
message type for LPH1).

The messages for scheduling agreement delivery schedules in the standard system:

    •   LPH1 for FRC; updates data relevant for printing
    •   LPJ1 for FAB; updates data relevant for printing
    •   LPET for conventional scheduling agreements without release documentation
    •   LPMA for scheduling agreement expediters
Schedule agreement release processing                                               -8-


Creation Profile

The extensive configuration options in the creation profile allow you to produce the
most varied results within the scope of release generation.

The creation profile is assigned to an SA item. (SA release item overview screen ->
Item -> More functions -> Additional data)
You create creation profiles in Customizing for Purchasing via Scheduling Agreement
-> Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu.

Creation profiles are plant-dependent and consist of the following

   •   General parameters
   •   Aggregation horizons
   •   Creation periodicity


General Parameters:

In the general parameters, you specify the following for each release type:
    • If and, if so, under which conditions, the system creates a release of this type
       (Creation strategy)
    • If backlogs and immediate requirements are to be calculated and identified
   Backlog: Quantities with a delivery date in the past that were transmitted to
   the vendor by means of a scheduling agreement release, but which have not
   yet been delivered
   Immediate requirements: Quantities that are required immediately (today or
   earlier) but which have not yet been transmitted to the vendor by means of a
   scheduling agreement release.
Schedule agreement release processing                                              -9-




Notes on Creation Strategy:

The settings for the creation strategy in the profile of the scheduling agreement item
act as a filter for the creation strategy of the creation run.
This ‘filter function’ is necessary, since it makes more sense to execute the creation
run using the strategy ‘Changed or next date’. This selects all scheduling agreements
in the plant in question that either indicate a change in the overall delivery schedule
in the system or for which the next transmission date is the same as or earlier than
the current date. This means by working with transaction ME84 with the scope of
select = blank determines the maximum number of scheduling agreement items. The
settings in the release creation profile restrict the selection then once more.
The creation strategy in the profile now controls if, and if so, on the basis of which
events the system has to create a forecast schedule and/or a JIT schedule for each
scheduling agreement item.
Schedule agreement release processing                                              - 10 -


Only in this way is it possible, for example, to prevent creation of both a forecast
schedule and a JIT schedule during the creation run if the overall delivery schedule
for the scheduling agreement is changed. In the example, the system should only
create the forecast schedule based on the next creation date.


Indicator: Determine backlog/imm.reqt:

This indicator is also taken into account while creating a release via transaction
ME84. When the flag for “Determine backlog/imm.reqt is set in the release creation
profile, then in table EKEK the field RUSKZ is unequal space.

Explanation to the settings of the above screenshot:
In the JIT schedules is the presentation of “backlog/imm.reqt” activated, in the
forecast schedules cut off.

Basically is recommended by SAP, that backlog and immediate requirement should
only be presented in the delivery relevant release.

Indicator: „Backlog creation-relevant“:
This field is only relevant when transaction ME84 is used.

Please note:
If transaction ME84 is executed “without restrictions” then the settings in the release
creation profile are effectless. Only the settings concerning aggregation horizons und
the settings concerning internet are checked.
Schedule agreement release processing                                                 - 11 -


Aggregation horizons:

In the ‘Aggregation horizons’ area, you specify for each release type which time
horizon the system uses to determine release quantities and for which periods the
system aggregates the quantities to ‘period quantities’, where applicable.
The example below shows how you would set the parameters in the ‘Aggregation
horizons’ area to transmit monthly requirements quantities for the next nine months in
the forecast schedule and daily quantities for the next ten days in the JIT schedule.

In the field ‘Plan. ca’ (Planning calendar), you can store a planning calendar. You
maintain this planning calendar in Customizing -> Materials Management ->
Consumption-Based Planning -> Master Data -> Maintain Planning Calendar

The data entered in this example results in the system determining daily quantities
for the next ten working days in the JIT schedule.

The system determines monthly quantities for the next 180 working days (= 9
months, each containing 20 working days) in the forecast schedule.
Schedule agreement release processing                                                     - 12 -


Creation Periodicity:

In the ‘Creation Periodicity’ area, you specify for each release type if, and if so, at
what intervals, the system is to create a release of that type.

Every time that the system creates a release, it calculates the next transmission date
for periodic transmission based on the date.


Example:
The system is to create a forecast schedule once a month and at least one JIT
schedule per week. You need to set the parameters in the ‘Creation periodicity’
Schedule agreement release processing                                                        - 13 -




Tolerance Profile:

In the ‘Tolerance Profile’ area, you specify for each release type if the system checks
by how much the current release to be created differs from the last release
transmitted, and if so, how it carries out this check.

The purpose of the tolerance check is to limit the frequency of schedule updates


Hints:
• During the tolerance check, the system compares the release schedule lines in
   table, not the schedule lines in table EKET and of the latest transmitted delivery
   schedule (not necessarily to the last generated delivery schedule).

•   During the tolerance check, the system does not check backlogs and immediate
    requirements.

•   There is a User-Exit to change the results of the tolerance check, please have a
    look at note 506600.



Difference between individual and overall check:

The example below contains the following schedule lines

Old schedule line                   Schedule line changed to the following values:
---------------------------         ------------------------------------------------------
Day               Quantity old      Quantity new
xx.xx.xx          20                40
xx.xx.xx          30                30
xx.xx.xx          40                36
                  ∑ 90              ∑ 106

In the tolerance check, upper and lower tolerance limits for this period are set to
20%.
If you make these changes to the schedule lines, with a basic overall check with 20%
as the upper and lower tolerance limits, the system does not create a new release.
The overall quantity of the schedule lines was 90 pieces and after the changes the
total of the new schedule lines is 106. Therefore, the change does not exceed the
20% upper limit. 20% of 90 pieces = 18 pieces and the quantity has changed by only
16 pieces.

In this example, if you check the schedule lines individually, the system would create
a release because you have changed the quantity in the first line by more than 20%
and it therefore exceeds the tolerance limit.
Schedule agreement release processing                                               - 14 -


Internet:

Specifies whether the type of release created is an Internet release.

Use:
Internet releases are not made available to the vendor in the conventional manner as
printouts of EDI or fax messages. Instead, if the Supplier Workplace is used, the
vendor can view them via the Internet and acknowledge them if necessary.

Dependencies:

If you wish to use Internet releases, you must implement the Supplier Workplace and
enable your vendors to access it via the Internet. Internet releases are displayed in
the Supplier Workplace and can be acknowledged there by your vendors.

Via the Acknowledgment by vendor indicator, you can specify that the Internet
release does not count as "outputted" until it has been acknowledged by the vendor.

If you do not set this indicator, the Internet release counts as "outputted" immediately
it is created or itself released (approved).

In both cases, the output date and time are updated and the Internet release is
included in the release documentation. When the next release creation cycle takes
place, a new release number is generated.
Schedule agreement release processing                                            - 15 -




Programs:
SAPLEINL             main program for release documentation
RM06EFLB             Release generation report as of release 4.5


Function group MEDE (Scheduling Agmt. Schedule Lines from MRP):

ME_UPDATE_SCHEDULES_DISPO               Create scheduling agreement schedule lines
                                        from MRP


Funktionsgruppe EINM (EDI Message Output: Purchasing):

IDOC_OUTPUT_DELINS                            Ausgabe Lieferplaneinteilungen LAB
                                        (neu ab 4.0)


Funktionsgruppe EINL (Scheduling Agreement Releases):

ME_CREATE_SCHEDULE_DOC                  fixieren des auszugebenden Lieferplanabrufs

ME_READ_LAST_RELEASE                            Lesen des letzten übermittelten Abrufs
                                        (hier ist insbesondere Kennzeichen FABKZ
                                        wichtig. Wenn FABKZ gesetzt, dann bringt er
                                        den letzten Feinabruf (FAB), wenn nicht
                                        gesetzt, dann ist der letzte Lieferabruf (LAB)
                                        relevant.

ME_SIMULATE_SCHEDULE_DOC                dieser FB läuft bei der Toleranzprüfung, FB
                                        wird durchlaufen, wenn man sich den
                                        neueste Abruf ansieht

ME_UPDATE_SCHEDULE_DOC                  Verbuchung der fixierten Abrufdaten; wird bei
                                        der ME84 direkt aufgerufen. Bei der ME38
                                        wird er indirekt aufgerufen, d.h. in
                                        ME_UPDATE_SCHEDULE_DOC wird
                                        ME_UPDATE_DOCUMENT aufgerufen.

ME_UPDATE_SCHEDULE_EKPO                 Fortschreibung des nächsten
                                        Übermittlungsdatums. Wird nur bei der ME84
                                        aufgerufen und ist zuständig für das nächste
                                        LAB/FAB Datum. Dieser FB wird nur
                                        durchlaufen, wenn mit einem
                                        Erstellungsprofil in der Lieferplanposition
                                        gearbeitet wird.
Schedule agreement release processing                                         - 16 -




Funktionsgruppe MEDRUCK:

Include LMEDRUCKF17 is important, because here does the output for the release
takes place.


Funktionsgruppe EINL:

ME_CHECK_TOLERANCE                  Toleranzprüfung bei Lieferplanabrufen



Printprogram: SAPFM06P
    • Program ENTRY_LPHE should only be used for LPA’s and not for LP’s.

   •   Beginning with Rel. 4.0B the field EKPO-DRUNNR is no more longer used,
       but rather the field Feld EKEK-ABRUF => Therefore no gaps can exist in the
       release docuemdadurch.


Tables:

EKET
EKEH
EKEK
Schedule agreement release processing                                               - 17 -


FAQ:

While using transaction ME84 messages can drop away.
Via ME84 you create at the same time JIT and forecast delivery schedules. This
phenomenon can only occur when message determination is customized at header
level.

Solution: So that no messages can drop away you have to execute the ME84 one
time for JIT and a second time for forecast delivery schedules.



Specific messages can’t be output:
You work with several messages at the same time and you have maintained the
message determination at header level.

Solution: The main message (that message which has got in customizing the flag for
„update print-dependant data „ must be printed last. Therefore you should work with
dispatch time 3 for this mainmessage to make sure that this message is printed last.

This difficulty concerns only LPA’s. For LP’s you don’t work with mainmessages and
auxilliary messages.



Is there a possibility to repeat printout for a release?
If you are working with message determination at release level, then a repeat printout
is always possible.

Are you working with message determination at header level, then auxilliary
messages can be repeated output as long as the main message is not output. As
soon as the main message is output, then the auxilliary messages can no longer be
output. A main message can’t be repeated, there is only the possibility for a testprint.



When do you work with change messages for delivery schedules?
Change messages could only be generated if you work with message determination
at header level. You can only generate a change flag for the message if there is
already existing an objectkey in table NAST. By using message determination at
release level the objectkey is always unique and therefore it can’t happen that there
is existing the same entry yet.

The objectkey is established as follows:

XXXXXXXXXXYYYYYZAAAAAAAAAA

X stands for purchasing document (10 digits)
Y stands for item (5 digits)
Z stands for release type (1 means forecast schedule line, 2 means JIT)
Schedule agreement release processing                     - 18 -


A stands for release number (10 digits)

Example: In table NAST we have got the following entry:


55000006270001010000000001

      It is scheduling agreement 5500000627
      Item 10
      Release type 1 => Forecast delivery schedule
      Release Number 0000000001

Mais conteúdo relacionado

Mais procurados

Ewm erp qm_basic_inspection_process
Ewm erp qm_basic_inspection_processEwm erp qm_basic_inspection_process
Ewm erp qm_basic_inspection_processManikandanVijayan2
 
04.pricing and conditions_sdbfpr
04.pricing and conditions_sdbfpr04.pricing and conditions_sdbfpr
04.pricing and conditions_sdbfprPiyush Bose
 
Make to order document
Make to order document Make to order document
Make to order document Hari Krishna
 
SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1Intelligroup, Inc.
 
Pricing Concept in SAP SD by Venkat Mannam
Pricing Concept in SAP SD by Venkat MannamPricing Concept in SAP SD by Venkat Mannam
Pricing Concept in SAP SD by Venkat MannamVenkat Mannam
 
Product allocation during sales order entry
Product allocation during sales order entryProduct allocation during sales order entry
Product allocation during sales order entrysuryanarayana tata
 
Production Supply with SAP EWM
Production Supply with SAP EWMProduction Supply with SAP EWM
Production Supply with SAP EWMVictor Cerullo
 
Sd configuration steps for automatic batch determination in delivery
Sd   configuration steps for automatic batch determination in deliverySd   configuration steps for automatic batch determination in delivery
Sd configuration steps for automatic batch determination in deliveryShivaprakash Shastri Hiremath
 
SAP STO config
SAP STO configSAP STO config
SAP STO configsamitchak
 

Mais procurados (20)

Transfer of requirements in SAP SD
Transfer of requirements in SAP SDTransfer of requirements in SAP SD
Transfer of requirements in SAP SD
 
Ewm erp qm_basic_inspection_process
Ewm erp qm_basic_inspection_processEwm erp qm_basic_inspection_process
Ewm erp qm_basic_inspection_process
 
Intercompany config
Intercompany configIntercompany config
Intercompany config
 
04.pricing and conditions_sdbfpr
04.pricing and conditions_sdbfpr04.pricing and conditions_sdbfpr
04.pricing and conditions_sdbfpr
 
Make to order document
Make to order document Make to order document
Make to order document
 
Third party process
Third party processThird party process
Third party process
 
SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1SAP Account determination MM-FI by Odaiah Pelley - 1
SAP Account determination MM-FI by Odaiah Pelley - 1
 
Sap mm tickets
Sap mm ticketsSap mm tickets
Sap mm tickets
 
Pricing Concept in SAP SD by Venkat Mannam
Pricing Concept in SAP SD by Venkat MannamPricing Concept in SAP SD by Venkat Mannam
Pricing Concept in SAP SD by Venkat Mannam
 
SAP EWM Cross Docking
SAP EWM Cross DockingSAP EWM Cross Docking
SAP EWM Cross Docking
 
STO
STOSTO
STO
 
Sap sd org
Sap sd org Sap sd org
Sap sd org
 
Product allocation during sales order entry
Product allocation during sales order entryProduct allocation during sales order entry
Product allocation during sales order entry
 
Production Supply with SAP EWM
Production Supply with SAP EWMProduction Supply with SAP EWM
Production Supply with SAP EWM
 
Sd configuration steps for automatic batch determination in delivery
Sd   configuration steps for automatic batch determination in deliverySd   configuration steps for automatic batch determination in delivery
Sd configuration steps for automatic batch determination in delivery
 
SAP MM Essential Master Data
SAP MM Essential Master DataSAP MM Essential Master Data
SAP MM Essential Master Data
 
SAP MM Standard Business Processes
SAP MM Standard Business ProcessesSAP MM Standard Business Processes
SAP MM Standard Business Processes
 
SAP STO config
SAP STO configSAP STO config
SAP STO config
 
Availability Check in SAP SD
Availability Check in SAP SDAvailability Check in SAP SD
Availability Check in SAP SD
 
Consignment process
Consignment processConsignment process
Consignment process
 

Semelhante a Scheduling agreement konwledge paper

Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-ppLokesh Modem
 
Oracle Accounting reporting sequences
Oracle Accounting reporting sequencesOracle Accounting reporting sequences
Oracle Accounting reporting sequencesAli Ibrahim
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2Dr. Mahmoud Al-Naimi
 
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...Sanjay Kumar PMP
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-infoMBA, MSc, Alberto Castellano
 
Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planning Manufacturing.
 
IDE Sending Settlement Results EXPSETTLPA
IDE Sending Settlement Results EXPSETTLPAIDE Sending Settlement Results EXPSETTLPA
IDE Sending Settlement Results EXPSETTLPARakesh Dasgupta
 
Engineering Technical Report
Engineering Technical ReportEngineering Technical Report
Engineering Technical ReportJim Tu
 
Sap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopSap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopKanapon Gunprom
 
Lead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail PresentationLead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail Presentationdynamicp
 
Predictive automated marginal trading technology pamtt part 4
Predictive automated marginal trading technology  pamtt part 4Predictive automated marginal trading technology  pamtt part 4
Predictive automated marginal trading technology pamtt part 4Yuri Martemianov
 
Vendor consignment configuration doc
Vendor consignment configuration docVendor consignment configuration doc
Vendor consignment configuration docLokesh Modem
 
1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docxnavinsurya3
 
SAP MM IM Physical inventory -cycle counting
SAP MM IM Physical inventory -cycle countingSAP MM IM Physical inventory -cycle counting
SAP MM IM Physical inventory -cycle countingLokesh Modem
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxGulaHangus
 
Etm equipment and_tools management
Etm equipment and_tools managementEtm equipment and_tools management
Etm equipment and_tools managementPiyush Bose
 
Excess and Obsolete Inventory Reserves
Excess and Obsolete Inventory ReservesExcess and Obsolete Inventory Reserves
Excess and Obsolete Inventory ReservesJade Global
 

Semelhante a Scheduling agreement konwledge paper (20)

Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
 
Practical questions
Practical questionsPractical questions
Practical questions
 
Oracle Accounting reporting sequences
Oracle Accounting reporting sequencesOracle Accounting reporting sequences
Oracle Accounting reporting sequences
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
 
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...
SAP S/4 Simple Finance Implementation Strategy: Central Finance Deployment Op...
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
 
Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP Planificador de Producción a capacidad finita Simatic IT Preactor AP
Planificador de Producción a capacidad finita Simatic IT Preactor AP
 
Why contract savings are missing
Why contract savings are missingWhy contract savings are missing
Why contract savings are missing
 
IDE Sending Settlement Results EXPSETTLPA
IDE Sending Settlement Results EXPSETTLPAIDE Sending Settlement Results EXPSETTLPA
IDE Sending Settlement Results EXPSETTLPA
 
Engineering Technical Report
Engineering Technical ReportEngineering Technical Report
Engineering Technical Report
 
Sap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopSap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sop
 
Lead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail PresentationLead Time System (LTS) Detail Presentation
Lead Time System (LTS) Detail Presentation
 
Predictive automated marginal trading technology pamtt part 4
Predictive automated marginal trading technology  pamtt part 4Predictive automated marginal trading technology  pamtt part 4
Predictive automated marginal trading technology pamtt part 4
 
Vendor consignment configuration doc
Vendor consignment configuration docVendor consignment configuration doc
Vendor consignment configuration doc
 
1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx
 
Copa implementation
Copa implementationCopa implementation
Copa implementation
 
SAP MM IM Physical inventory -cycle counting
SAP MM IM Physical inventory -cycle countingSAP MM IM Physical inventory -cycle counting
SAP MM IM Physical inventory -cycle counting
 
MASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptxMASTER PRODUCTION SCHEDULE (MPS).pptx
MASTER PRODUCTION SCHEDULE (MPS).pptx
 
Etm equipment and_tools management
Etm equipment and_tools managementEtm equipment and_tools management
Etm equipment and_tools management
 
Excess and Obsolete Inventory Reserves
Excess and Obsolete Inventory ReservesExcess and Obsolete Inventory Reserves
Excess and Obsolete Inventory Reserves
 

Mais de armindajack

Vendor evaluation
Vendor evaluationVendor evaluation
Vendor evaluationarmindajack
 
Third party knowledge paper
Third party knowledge paperThird party knowledge paper
Third party knowledge paperarmindajack
 
Release strategy
Release strategyRelease strategy
Release strategyarmindajack
 
Configure automatic postings
Configure automatic postingsConfigure automatic postings
Configure automatic postingsarmindajack
 
Condition changes with mekp mekr and mekl
Condition changes with mekp mekr and meklCondition changes with mekp mekr and mekl
Condition changes with mekp mekr and meklarmindajack
 
Commitments in purchasing
Commitments in purchasingCommitments in purchasing
Commitments in purchasingarmindajack
 

Mais de armindajack (7)

Vendor evaluation
Vendor evaluationVendor evaluation
Vendor evaluation
 
Third party knowledge paper
Third party knowledge paperThird party knowledge paper
Third party knowledge paper
 
Release strategy
Release strategyRelease strategy
Release strategy
 
Mm pur-gf-oc
Mm pur-gf-ocMm pur-gf-oc
Mm pur-gf-oc
 
Configure automatic postings
Configure automatic postingsConfigure automatic postings
Configure automatic postings
 
Condition changes with mekp mekr and mekl
Condition changes with mekp mekr and meklCondition changes with mekp mekr and mekl
Condition changes with mekp mekr and mekl
 
Commitments in purchasing
Commitments in purchasingCommitments in purchasing
Commitments in purchasing
 

Último

THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxPoojaSen20
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 

Último (20)

THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 

Scheduling agreement konwledge paper

  • 1. Schedule agreement release processing -1- Schedule agreement release processing As of SAP R/3 Release 4.5 Overall process In simplified terms, scheduling agreement processing consists of three main steps: Material requirements planning Release generation (FRC/JIT) Output/Transmission of releases 1. Material Requirements Planning The current overall delivery schedule for a material that is procured via scheduling agreement releases changes continuously during an MRP run due to the requirements for that material (dependent requirements and so on). This results in quantities and delivery dates that are to be transmitted to the vendor in the form of releases against the relevant scheduling agreement. Therefore the field EKPO- ETDRK will get a value unequal “space”. Is the value 1, then this does mean that the delivery schedule was created via MRP, is the value 2, then the delivery schedule was created via ME38. The prerequisite for automatic creation of schedule lines during requirements planning is that a scheduling agreement is flagged as MRP-relevant in the source list. You can do this in the Purchasing menu: Master data -> Source list -> Maintain (transaction ME01). You must maintain a record for the material here and in this record, the field ‘MRP’ must contain the indicator ‘2’. The schedule lines created by the MRP run are assigned creation indicator ‘B’ and are contained in table EKET in field ESTKZ. In contrast, manually created schedule lines are assigned creation indicator ‘R’. Another difference between manual schedule lines and schedule lines from requirements planning is that you can only enter a time for manual schedule lines. We will not go into more detail on the individual steps of MRP here.
  • 2. Schedule agreement release processing -2- 2. Release types / Release generation Basically, release generation ‘translates’ the current overall delivery schedule in the system into a release. Releases inform the vendor of which quantities of a material are to be delivered on which date. The individual releases are recorded using the release documentation and can therefore be displayed at any time. You can only create releases for scheduling agreements with release documentation. (Document type in the standard system is LPA or the Release docu. indicator must be flagged in Customizing for Purchasing -> Scheduling Agreement -> Define Document Types.) If a scheduling agreement was created under these customizing settings, the field EKKO-LPHIS has got the value “X”. Via this check you see very fast if you are working with LPA or LP. Note: There is no release documentation for stock transport scheduling agreements. Even if the Release docu. indicator is flagged for document type LU in Customizing, it has no effect. There are the following types of releases • Forecast delivery schedule (FRC) Provides the vendor with information over the longer term about which quantities of a material are to be delivered on which date. Delivery dates are usually specified as calendar months or weeks. • JIT delivery schedule (JIT) Provides the vendor with information about which quantities of a material are to be delivered at which point in time in the near future. Exact delivery dates (calendar days) or even delivery times are usually specified. The suggested quantity for goods receipts is based on the last release transmitted. If you use both types of release, the system suggests the data in the JIT schedule. If you use only the forecast schedule, the system suggests the data in the forecast schedule. Note: In order to work with JIT delivery schedules, you must have set the JIT schedule indicator in the material master record (MARC-FABKZ) and in the scheduling agreement item. (You do this on the ‘Purchasing’ view or on the ‘MRP 2’ view of the material master record.) This indicator controls whether JIT delivery schedules can be created for a material in addition to forecast schedules.
  • 3. Schedule agreement release processing -3- Possible cause of error: Customer cannot create any JIT schedules: If you have set the JIT schedule indicator in the material master record and the scheduling agreement had, however, already been created, you cannot create any JIT schedules for this scheduling agreement. Check if there are any change documents in the material master record for the JIT schedule indicator and check when the scheduling agreement item was created. You can use creation profiles to influence the quantities and dates transmitted. You configure a creation profile in Customizing for Purchasing by choosing Scheduling Agreement -> Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu. (transaction OMUP). We will go into more detail on these Customizing settings later. The system stores a transmitted release with a release number and includes the document in the release ‘history’. The system then generates the next release of that particular release type with a number increased by one. Forecast schedules and JIT schedules have separate number ranges. Table: EKEK (Header Data for Scheduling Agreement Releases) EKEH (Scheduling Agreement Release Documentation) When creating releases, the system reads extensive control parameters from the creation profile. Creating a release: You can create releases using a report (RM06EFLB up to Rel. 4.5X) (intended for regular releases). Please see also note 182210 which describes which report is valid for the appropriate Release. You can also create releases manually. You can do this from the scheduling agreement delivery schedule by choosing Edit -> Generate JIT sched. or Generate forc. schd. as well as from the item overview screen of transaction ME38 by choosing Edit -> Generate JIT sched. or Generate forc. schd. Note: You must note that the system does NOT carry out a tolerance check or backlog determination when you manually create releases. The system only aggregates scheduled quantities. The backlog determination is only active if it is defined in the creation profile. When creating releases the function module ME_CREATE_SCHEDULE_DOC will be called (this is independent if transaction ME84 oder ME38 is used). If a creation profile is maintained in the scheduling agreement item and in this creation profile the flag “Determine backlog” is set, then the routine Backlog_IM_Requirements will be called.
  • 4. Schedule agreement release processing -4- To check how a release was created (e.g. via report RM06EFLB or via transaction ME38) it is possible to look in table EKEK. In field STAAB there could be the following entries: Space: this does mean via ME38 1: this does mean via ME84 2: this does mean MDXX (transactions like MD03, MD04) Release creation basically consists of the following steps: • Conversion of the current overall delivery schedule in the system into aggregated release dates and quantities where applicable (see also ‘Creation Profile’ for more information on this) • Creation of a release (FRC/JIT) in accordance with a particular creation strategy (for example, next creation date reached, current overall delivery schedule has changed). You use both the ‘General parameters’ and the ‘Creation periodicity’ in the creation profile to control this. You can prevent release creation based on a change in the current overall schedule by means of a tolerance check, if necessary, so that minor changes compared to the last release do not necessarily lead to the creation of a new release. • Optional calculation or statement of backlogs and immediate requirements, if this function is active. • In the case of release creation ‘Based on changes’, optional tolerance check that only allows creation of a release only if changes that lie outside a defined tolerance limit have occurred since transmission of the last release If the system creates a release, it also creates a message record at the same time. This message record is a prerequisite for the output and transmission of the release to the vendor.
  • 5. Schedule agreement release processing -5- Output / transmission of releases You can process the message records for the newly created releases either immediately or in a subsequent collective output. Messages are output immediately if transmission time ‘4’ is set. Collective processing is possible if you are working with transmission time ‘1’ (output via RSNAST00) or ‘3’ (output via the application-specific output program). Attention: RSNAST00 can process only datasets with dispatch time 1 and 2. The report does not process data sets with dispatch time 4. You create message condition records in the Purchasing menu by choosing Master data -> Messages -> Sch. agmt. schedule -> Create. When the system outputs a message (function module ME_UPDATE_FROM_PRINTING is therefore responsible), certain updates take place that designate the release as ‘completed and output’. Therefore it is necessary that in customizing in transaction OMQP the field for “Update print-dependant data”for the appropriate message type is set (T161N-DRUAB). If the system has not yet output a release as a message, any generation of a further release will cause the last release, which the system has not yet output, to be overwritten. After the system has output the release using the main message type (see below for an explanation of this), the fields ‘Output date’ and ‘Output time’ are filled. Another important detail that is updated at this point in time is the resetting of the ‘Changed’ indicator (EKPO-ETDRK is changed into space) in the scheduling agreement item. This means that after a release is output, the scheduling agreement item in question is no longer regarded as ‘Changed’ (as regards the overall delivery schedule in the system) until you process the schedule again manually or by means of the MRP run. The system can create a separate message for each release for a scheduling agreement item. This means that the vendor receives one document for each release. This lets you output releases individually or re-output releases that have already been transmitted. In order to have the system create a separate message for each release, you must set the indicator ‘Rel. mess.’ (message per release) in Customizing for Purchasing, by choosing Messages -> Message Determination Schemas -> Define Message Schemas for Scheduling Agreement Release/Expediter -> Assign Schema to Scheduling Agreement Release/Expediter. If the R/3 system is customized in that manner then we talk about ”message determination on release level”. With this customizing setting NO change messages can be created. Technical explanation for that: Change messages can only be formed when in table NAST already an entry exists with the same objectkey. This means you can only work with change messages when in customizing the message determination is maintained at “header level”. Messages created under “message “determination at release level” can be displayed in transaction ME38 by selecting
  • 6. Schedule agreement release processing -6- the relevant item and choosing SA Release docu., then selecting the relevant release number and choosing Messages per release, NOT via ME38 -> Header -> Messages. Note: You can only output messages created at release level via the Purchasing menu, by choosing Outline agreement -> Scheduling agreement -> Delivery schedule -> Print/transmit (transaction ME9E). If there are messages for the scheduling agreement that have not been output and you subsequently set the ‘Messages per release’ indicator, you can still find the messages that have not been output via Header -> Messages. You will find newly created messages via the release documentation (ME38 -> select the relevant item - > SA release docu. -> select the relevant release -> Messages per release). The system stores the messages for a release in table NAST using the following key: Object key (this means the document number) Item Release type (FRC or JIT) Release number Prerequisites for the transmission of scheduling agreements releases as messages to the vendor: As of Release 4.0, you must define exactly one message type as the ‘Main message type’ for each release type in Customizing for MM, Message Determination for Scheduling Agreement Schedules. Field ‘U’ (Update print-dependent data) must be flagged for the message type in question in Customizing for Materials Management - > Purchasing -> Messages -> Output Control -> Message Types -> Define Message Types for Scheduling Agreement Alle Abrufe müssen immer mit der Hauptnachrichtenart erstellt werden, da das System sonst die druckabhängigen Daten nicht aktualisiert. Dies ist insbesondere dann wichtig, wenn Sie mit verschiedenen Nachrichtenarten arbeiten. Set the flag „Update print-dependant data“ or not? In Release 4.6B you will get an error message if you try to set this flag several for the same operation type. In Release 4.6C you get a warning message. Background for this different systembehaviour is the following: If you are working with message determination on “release level” then several message types for one operation could be flagged. If you work with message determination at “header level” then only one message type per operation should be flagged.
  • 7. Schedule agreement release processing -7- Recommendation: You must always use the main message type to create all releases, otherwise the system does not update the print-dependent data. This is particularly important if you use several different message types (e.g. main message with medium 6 for EDI and another message for medium 1 for printing which is not maintained as main message. You can only set the indicator once for each release type. Operation ‘9’ corresponds to the forecast delivery schedule, and operation ‘A’ corresponds to the JIT delivery schedule. Example (transaction OMQP): Operations for Message Type U (Update Print-Dependent Data) 9 LPH1 x main message type for FRC 9 LPH2 additional message type A LPJ1 x main message type for JIT A LPJ2 additional message type After determination of the message type that updates the print-dependent data for each release type (that is, for each operation), you must make sure that releases are always created with this message type (called ‘main message type’). You are allowed to create a second message type in parallel, whereby the main message type should be the one that is created first (such as LPH2 as the second message type for LPH1). Please note: Messages which aren’t the main message are called auxilliary messages. These are all messages which have not set the flag for “update print-dependant data”. Auxilliary messages must always be output before the main message is output, when you work with message determination at “header level”. After determination of the message type that updates the print-dependent data for each release type (that is, for each operation), you must make sure that releases are always created with this message type (called ‘main message type’). You are allowed to create a second message type in parallel, whereby the main message type should be the one that is created first (such as LPH2 as the second message type for LPH1). The messages for scheduling agreement delivery schedules in the standard system: • LPH1 for FRC; updates data relevant for printing • LPJ1 for FAB; updates data relevant for printing • LPET for conventional scheduling agreements without release documentation • LPMA for scheduling agreement expediters
  • 8. Schedule agreement release processing -8- Creation Profile The extensive configuration options in the creation profile allow you to produce the most varied results within the scope of release generation. The creation profile is assigned to an SA item. (SA release item overview screen -> Item -> More functions -> Additional data) You create creation profiles in Customizing for Purchasing via Scheduling Agreement -> Maint. Rel. Creation Profile for Sched. Agmt. w. Rel. Docu. Creation profiles are plant-dependent and consist of the following • General parameters • Aggregation horizons • Creation periodicity General Parameters: In the general parameters, you specify the following for each release type: • If and, if so, under which conditions, the system creates a release of this type (Creation strategy) • If backlogs and immediate requirements are to be calculated and identified Backlog: Quantities with a delivery date in the past that were transmitted to the vendor by means of a scheduling agreement release, but which have not yet been delivered Immediate requirements: Quantities that are required immediately (today or earlier) but which have not yet been transmitted to the vendor by means of a scheduling agreement release.
  • 9. Schedule agreement release processing -9- Notes on Creation Strategy: The settings for the creation strategy in the profile of the scheduling agreement item act as a filter for the creation strategy of the creation run. This ‘filter function’ is necessary, since it makes more sense to execute the creation run using the strategy ‘Changed or next date’. This selects all scheduling agreements in the plant in question that either indicate a change in the overall delivery schedule in the system or for which the next transmission date is the same as or earlier than the current date. This means by working with transaction ME84 with the scope of select = blank determines the maximum number of scheduling agreement items. The settings in the release creation profile restrict the selection then once more. The creation strategy in the profile now controls if, and if so, on the basis of which events the system has to create a forecast schedule and/or a JIT schedule for each scheduling agreement item.
  • 10. Schedule agreement release processing - 10 - Only in this way is it possible, for example, to prevent creation of both a forecast schedule and a JIT schedule during the creation run if the overall delivery schedule for the scheduling agreement is changed. In the example, the system should only create the forecast schedule based on the next creation date. Indicator: Determine backlog/imm.reqt: This indicator is also taken into account while creating a release via transaction ME84. When the flag for “Determine backlog/imm.reqt is set in the release creation profile, then in table EKEK the field RUSKZ is unequal space. Explanation to the settings of the above screenshot: In the JIT schedules is the presentation of “backlog/imm.reqt” activated, in the forecast schedules cut off. Basically is recommended by SAP, that backlog and immediate requirement should only be presented in the delivery relevant release. Indicator: „Backlog creation-relevant“: This field is only relevant when transaction ME84 is used. Please note: If transaction ME84 is executed “without restrictions” then the settings in the release creation profile are effectless. Only the settings concerning aggregation horizons und the settings concerning internet are checked.
  • 11. Schedule agreement release processing - 11 - Aggregation horizons: In the ‘Aggregation horizons’ area, you specify for each release type which time horizon the system uses to determine release quantities and for which periods the system aggregates the quantities to ‘period quantities’, where applicable. The example below shows how you would set the parameters in the ‘Aggregation horizons’ area to transmit monthly requirements quantities for the next nine months in the forecast schedule and daily quantities for the next ten days in the JIT schedule. In the field ‘Plan. ca’ (Planning calendar), you can store a planning calendar. You maintain this planning calendar in Customizing -> Materials Management -> Consumption-Based Planning -> Master Data -> Maintain Planning Calendar The data entered in this example results in the system determining daily quantities for the next ten working days in the JIT schedule. The system determines monthly quantities for the next 180 working days (= 9 months, each containing 20 working days) in the forecast schedule.
  • 12. Schedule agreement release processing - 12 - Creation Periodicity: In the ‘Creation Periodicity’ area, you specify for each release type if, and if so, at what intervals, the system is to create a release of that type. Every time that the system creates a release, it calculates the next transmission date for periodic transmission based on the date. Example: The system is to create a forecast schedule once a month and at least one JIT schedule per week. You need to set the parameters in the ‘Creation periodicity’
  • 13. Schedule agreement release processing - 13 - Tolerance Profile: In the ‘Tolerance Profile’ area, you specify for each release type if the system checks by how much the current release to be created differs from the last release transmitted, and if so, how it carries out this check. The purpose of the tolerance check is to limit the frequency of schedule updates Hints: • During the tolerance check, the system compares the release schedule lines in table, not the schedule lines in table EKET and of the latest transmitted delivery schedule (not necessarily to the last generated delivery schedule). • During the tolerance check, the system does not check backlogs and immediate requirements. • There is a User-Exit to change the results of the tolerance check, please have a look at note 506600. Difference between individual and overall check: The example below contains the following schedule lines Old schedule line Schedule line changed to the following values: --------------------------- ------------------------------------------------------ Day Quantity old Quantity new xx.xx.xx 20 40 xx.xx.xx 30 30 xx.xx.xx 40 36 ∑ 90 ∑ 106 In the tolerance check, upper and lower tolerance limits for this period are set to 20%. If you make these changes to the schedule lines, with a basic overall check with 20% as the upper and lower tolerance limits, the system does not create a new release. The overall quantity of the schedule lines was 90 pieces and after the changes the total of the new schedule lines is 106. Therefore, the change does not exceed the 20% upper limit. 20% of 90 pieces = 18 pieces and the quantity has changed by only 16 pieces. In this example, if you check the schedule lines individually, the system would create a release because you have changed the quantity in the first line by more than 20% and it therefore exceeds the tolerance limit.
  • 14. Schedule agreement release processing - 14 - Internet: Specifies whether the type of release created is an Internet release. Use: Internet releases are not made available to the vendor in the conventional manner as printouts of EDI or fax messages. Instead, if the Supplier Workplace is used, the vendor can view them via the Internet and acknowledge them if necessary. Dependencies: If you wish to use Internet releases, you must implement the Supplier Workplace and enable your vendors to access it via the Internet. Internet releases are displayed in the Supplier Workplace and can be acknowledged there by your vendors. Via the Acknowledgment by vendor indicator, you can specify that the Internet release does not count as "outputted" until it has been acknowledged by the vendor. If you do not set this indicator, the Internet release counts as "outputted" immediately it is created or itself released (approved). In both cases, the output date and time are updated and the Internet release is included in the release documentation. When the next release creation cycle takes place, a new release number is generated.
  • 15. Schedule agreement release processing - 15 - Programs: SAPLEINL main program for release documentation RM06EFLB Release generation report as of release 4.5 Function group MEDE (Scheduling Agmt. Schedule Lines from MRP): ME_UPDATE_SCHEDULES_DISPO Create scheduling agreement schedule lines from MRP Funktionsgruppe EINM (EDI Message Output: Purchasing): IDOC_OUTPUT_DELINS Ausgabe Lieferplaneinteilungen LAB (neu ab 4.0) Funktionsgruppe EINL (Scheduling Agreement Releases): ME_CREATE_SCHEDULE_DOC fixieren des auszugebenden Lieferplanabrufs ME_READ_LAST_RELEASE Lesen des letzten übermittelten Abrufs (hier ist insbesondere Kennzeichen FABKZ wichtig. Wenn FABKZ gesetzt, dann bringt er den letzten Feinabruf (FAB), wenn nicht gesetzt, dann ist der letzte Lieferabruf (LAB) relevant. ME_SIMULATE_SCHEDULE_DOC dieser FB läuft bei der Toleranzprüfung, FB wird durchlaufen, wenn man sich den neueste Abruf ansieht ME_UPDATE_SCHEDULE_DOC Verbuchung der fixierten Abrufdaten; wird bei der ME84 direkt aufgerufen. Bei der ME38 wird er indirekt aufgerufen, d.h. in ME_UPDATE_SCHEDULE_DOC wird ME_UPDATE_DOCUMENT aufgerufen. ME_UPDATE_SCHEDULE_EKPO Fortschreibung des nächsten Übermittlungsdatums. Wird nur bei der ME84 aufgerufen und ist zuständig für das nächste LAB/FAB Datum. Dieser FB wird nur durchlaufen, wenn mit einem Erstellungsprofil in der Lieferplanposition gearbeitet wird.
  • 16. Schedule agreement release processing - 16 - Funktionsgruppe MEDRUCK: Include LMEDRUCKF17 is important, because here does the output for the release takes place. Funktionsgruppe EINL: ME_CHECK_TOLERANCE Toleranzprüfung bei Lieferplanabrufen Printprogram: SAPFM06P • Program ENTRY_LPHE should only be used for LPA’s and not for LP’s. • Beginning with Rel. 4.0B the field EKPO-DRUNNR is no more longer used, but rather the field Feld EKEK-ABRUF => Therefore no gaps can exist in the release docuemdadurch. Tables: EKET EKEH EKEK
  • 17. Schedule agreement release processing - 17 - FAQ: While using transaction ME84 messages can drop away. Via ME84 you create at the same time JIT and forecast delivery schedules. This phenomenon can only occur when message determination is customized at header level. Solution: So that no messages can drop away you have to execute the ME84 one time for JIT and a second time for forecast delivery schedules. Specific messages can’t be output: You work with several messages at the same time and you have maintained the message determination at header level. Solution: The main message (that message which has got in customizing the flag for „update print-dependant data „ must be printed last. Therefore you should work with dispatch time 3 for this mainmessage to make sure that this message is printed last. This difficulty concerns only LPA’s. For LP’s you don’t work with mainmessages and auxilliary messages. Is there a possibility to repeat printout for a release? If you are working with message determination at release level, then a repeat printout is always possible. Are you working with message determination at header level, then auxilliary messages can be repeated output as long as the main message is not output. As soon as the main message is output, then the auxilliary messages can no longer be output. A main message can’t be repeated, there is only the possibility for a testprint. When do you work with change messages for delivery schedules? Change messages could only be generated if you work with message determination at header level. You can only generate a change flag for the message if there is already existing an objectkey in table NAST. By using message determination at release level the objectkey is always unique and therefore it can’t happen that there is existing the same entry yet. The objectkey is established as follows: XXXXXXXXXXYYYYYZAAAAAAAAAA X stands for purchasing document (10 digits) Y stands for item (5 digits) Z stands for release type (1 means forecast schedule line, 2 means JIT)
  • 18. Schedule agreement release processing - 18 - A stands for release number (10 digits) Example: In table NAST we have got the following entry: 55000006270001010000000001  It is scheduling agreement 5500000627  Item 10  Release type 1 => Forecast delivery schedule  Release Number 0000000001