SlideShare uma empresa Scribd logo
1 de 52
AMSYSCO, INC.
Post-Tensioned
Concrete
INFORMATION
SESSION
1
Copyright © 2010 AMSYSCO, Inc.
OUTLINE of INFO SESSION
PART ONE
1. Introduction to
Post-Tension
2. Components of
Post-Tension
3. Construction Team
4. Submittals
PART TWO
5. Pre-Installation
6. Installation
Management
7. Post-Concrete
Placement
PART THREE
8. Troubleshooting
2
Copyright © 2010 AMSYSCO, Inc.
Click this icon to view
video in presentation
1. INTRO to POST-TENSIONING
3
Copyright © 2010 AMSYSCO, Inc.
1.1 History of Post-Tensioning
 Post-Tensioning is a
method of
prestressing.
Concrete is weak in
tension. PT
increases concrete’s
ability to perform
under tensile
stresses. Tendons are
tensioned after the
concrete is poured.
 1928 : Modern
Prestressed Concrete
“invented.”
 1946 : Post-
Tensioning gained
momentum in Europe
due to steel shortage.
 1951 : 1st
PT bridge
constructed in U.S.
 1963 : Prestressed
Concrete
incorporated into ACI
Code.
 1976 : Post-
Tensioning Institute
(PTI) founded.
4
Copyright © 2010 AMSYSCO, Inc.
1.2 AMSYSCO, Inc.
5
 1981 : AMSYSCO, Inc. founded by Rattan Khosa
 1984 : Joined PTI
 1985 : Installed extrusion line equipment
 1989 : Became PTI Plant Certified
 1990 : Rattan Khosa elected to PTI Executive
Committee
 1999 : Rattan Khosa became President of PTI (2yrs)
 2000 : Completed 400th
unbonded PT project
 2003 : Neel Khosa joined AMSYSCO
 2007 : Moved headquarters to Romeoville, IL
 2008 : Awarded PTI Project of the Year (Guthrie)
 2009 : Completed Target Field (MN Twins)
Copyright © 2010 AMSYSCO, Inc.
AMSYSCO, Inc. P: 630-296-8383
1200 Windham Parkway F: 630-296-8380
Romeoville, IL 60446 www.amsyscoinc.com
1.3.1 Types of Post-Tensioning
6
PRESTRESSING STEEL TENDONS
 Mono-Strand = One single strand per tendon.
 Multi-Strand = Multiple strands per tendon.
 Unbonded: Tendon encased in plastic
sheathing. Does not bond to concrete. Force
transferred by the anchorage only.
 Bonded: Tendon installed in ducts that are
pumped with grout after stressing. Bonds to
concrete.
Copyright © 2010 AMSYSCO, Inc.
 Commercial High-Rise
 Multi-Family Housing
 Residential Housing (SOG)
 Parking Structures
 Stadiums / Theaters
1.3.2 Uses of Post-Tensioning
 Bridges
 Stadiums
 Tennis Courts
 Water Tanks / Silos
 Nuclear Plants
 Repair & Restoration
7
Copyright © 2010 AMSYSCO, Inc.
1.4 Benefits of Unbonded Post-
Tension8
Copyright © 2010 AMSYSCO, Inc.
2. COMPONENTS of Post-Tension
9
Copyright © 2010 AMSYSCO, Inc.
2.1.1 Strand – Bare
10
 Strand: Hig h-stre ng th ste e lwire . 6 -wire s twist aro und
7 th
ce ntral“king ”-wire . Typicaldiam e te rs are 0 . 5” and
0 . 6 ”.
 Tendon: Strand that is e ncase d with a laye r o f
co rro sive -inhibito r (g re ase ) and plastic she athing .Strand 0.5” 0.6” Units
Weight 0.525 0.740 lbs per ft
Ultimate Stress 270 270 ksi
Cross-sectional area 0.153 0.217 sq.in.
MUTS = ksi x sq.in. 41.3 58.6 kips
Jacking Force = 80% MUTS 33 46.8 kips
Avg. Final Effective Force ~27.5 ~38.0 kips
Elongation = approx. 8” per 100’-0 tendon length inches
Copyright © 2010 AMSYSCO, Inc.
2.1.2 Strand – Coated
11
 PT Coating or Tendon Grease
 Reduces friction during stressing
 Le ss frictio n m e ans m o re fo rce pe r te ndo n.
 Eliminates rifling in plastic sheathing
 Protects Strand from corrosion
 PT Sheathing or Plastic Sheathing
 Extruded HDPE
 Acts as bond breaker to enable stressing
 Contains PT Coating
 Acts as additional corrosion barrier
Copyright © 2010 AMSYSCO, Inc.
2.2 Anchor, Wedges, Pocket
Former12
 Anchor: Casting which houses wedges used
to transfer prestressing force to concrete.
 Fixed Anchor – installed in supplier’s plant
 Intermediate Stressing – located at construction
joints
 Stressing Anchor – where jacking force is applied
 Wedges : Tapered high-strength steel with
teeth.
 Pocket Former: Temporary device that
creates opening/pocket in concrete to allow for
stressing.Copyright © 2010 AMSYSCO, Inc.
2.3 Encapsulated vs. Regular
13
Component ENCAPSULATED REGULAR
Plastic Sheathing 50 ML 40 or 50 ML
Anchors Plastic-Coated
Metal
Uncoated Metal
Pocket Formers YES YES
Snap Caps YES NO
Wedges YES YES
Translucent Sleeves YES NO
- filled with grease YES N/A
Positive Mechanical
Connection
YES NO
Seal Plugs YES NO
Protection during shipping YES De pe nds o n spe c.
Copyright © 2010 AMSYSCO, Inc.
2.4.1 Supports – Definitions
14
 C.G.S. = Center of Gravity of Steel
 C.G.C. = Center of Gravity of Concrete
 AT ANCHORAGES: C.G.S. = C.G.C.
______________________________________
_____
 Profile /Drape: Te ndo n e le vatio n inside
co ncre te .
 Slab-On-Ground has no drape in slab (not in
beams).
 High Point: Co ntro lpo int at co lum n suppo rts .
Copyright © 2010 AMSYSCO, Inc.
2.4.2 Supports – Function
15
 Maintains tendon drape & Reduces tendon
wobble.
 Stabilizes tendon during concrete placement.
 Support Chair: Plastic supports used in slabs.
 Support Bar: #4 Bar.
 Slab Bolster: Used at slab midspans. No bar
required.
 BeamSupports: Attach U-bars to stirrups.
 Maximum 48” spacing (U.N.O.)
Copyright © 2010 AMSYSCO, Inc.
2.5 Stressing Equipment
16
 Hydraulic Jack/Ram and Electric Pump with
Gauge.
 Needs 110V, 30 amps power with cords that
are 3-wire, 12-gauge and less than 100 feet
long.
Copyright © 2010 AMSYSCO, Inc.
 Used for pedestrian and/or vehicular restraint.
 Same as 0.5” Post-Tensioning strand.
 Except for galvanization or epoxy coating.
 Anchorage devices may be different also.
2.6 Barrier Cable
17
Copyright © 2010 AMSYSCO, Inc.
3. CONSTRUCTION TEAM
18
Copyright © 2010 AMSYSCO, Inc.
3.1 Architect & Structural
Engineer19
 ARCHITECT
 Provides building dimensions and layout.
 Provides barrier cable design.
 STRUCTURAL ENGINEER
 Provides structural design for post-tensioning,
etc.
 Provides concrete mix design requirements.
 Adherence to building and seismic codes (IBC,
etc.)
 General and special requirements.
Copyright © 2010 AMSYSCO, Inc.
3.2 General Contractor
20
 Provides latest design documents to PT
Supplier.
 Approves pour sequence.
 Coordinates post-tensioning with other trades
(embeds, stairs, openings etc.) that may affect
the access to stressing tendons.
 Manages post-tensioning process.
Copyright © 2010 AMSYSCO, Inc.
Should obtain from PT Supplier:
• Bare and Gross weight of PT
• # of Holes in bulkhead to stress
• # Pockets to grout
• Support/Backup bar tonnage
(epoxy)
• Pour Sequence
3.3 Post-Tension Supplier
21
 Must ship material from a PTI Certified Plant.
 Responsibilities include:
 Provide installation shop drawings and calcs that
meet requirement in structural design drawings.
 Furnish post-tensioning tendons and accessories
to meet structural specifications.
 Certify calibrated stressing equipment.
 Assist in solving preconstruction and field issues
related to post-tensioning.
 Provide theoretical elongation ranges.
Copyright © 2010 AMSYSCO, Inc.
3.4 Post-Tension Installer
 Should be PTI
Certified – Level 2
Ironworker (o r
e q ual).
 For safety reasons,
individuals operating
stressing equipment
must have
experience in
stressing and basic
maintenance.
 Should keep a copy
of the PTI ‘Fie ld
Manual’ onsite.
22
Copyright © 2010 AMSYSCO, Inc.
3.5 Post-Tension Inspector
23
 Should be PTI Certified – Level 2 Inspector.
 Independent party from PT Supplier and
Installer.
 Responsibilities include:
 Check tendon profiles.
 Monitor stressing operations.
 Measure elongations after stressing.
 Compare measured to theoretical elongations.
 Make elongation report for Str. Engineer’s
approval.Copyright © 2010 AMSYSCO, Inc.
3.6 Other Subcontractors
24
 RebarSupplier– needs bar list for support
steel.
 Forming Contractor– needs pour sequence.
 Concrete Supplier– mix design to ensure
adequate concrete strength at time of
stressing.
 MEPTrades – coordinate openings for
office/residential.
 Trades with Embeds –
architectural precast,
Copyright © 2010 AMSYSCO, Inc.
4. SUBMITTALS
25
Copyright © 2010 AMSYSCO, Inc.
4.1 Construction Documents
26
 Drawings
 Structural
 Architectural
 Specifications
 Post-Tensioning (Division 3)
 Barrier Cable (Division 5)
 Construction Schedule
 Forming, Delivery, Installation and Stressing
dates
Copyright © 2010 AMSYSCO, Inc.
4.2 Pre-Detailing
27
 CAD Files
 Pour Sequence
 Construction Joints
 Pour Strips
 Stressing Restrictions
 Scope review
 Special requirements
 Coordination with other trades
 Openings (MEP, crane) & Embeds (precast,
curtainwall)
Copyright © 2010 AMSYSCO, Inc.
4.3 Post-Tensioning Submittals
28
 Installation Drawings
 Tendon Plan
 Support Plan
 Beam End View Details
 Friction Calculations
 Product / Test Data
 Bar List (support/backup)
 Mill Certificates
 Samples
Copyright © 2010 AMSYSCO, Inc.
5. PRE-INSTALLATION
29
Copyright © 2010 AMSYSCO, Inc.
5.1 PTI Certified Plant
 Fabrication
 Raw Materials
 PT Coating/Grease
 Plastic Sheathing
 Corrosion Protection
 Delivery
 Mill Certs
 Bill of Lading
 Cutting Lists
 Jack Calibration
30
Copyright © 2010 AMSYSCO, Inc.
5.2 Jobsite
 Unloading &
Handling without
damaging PT
 Storage to protect
from corrosion.
 Organization of
post-tension
inventory.
 Safety during
installation and
stressing.
31
Copyright © 2010 AMSYSCO, Inc.
6. JOBSITE INSTALLATION
32
Copyright © 2010 AMSYSCO, Inc.
6.1 PTI Field Procedures
Manual
 Published by Post-
Tensioning Institute
 Provides
procedures and
details for post-
tensioned concrete
installation.
 Introduction
 Document Control
 Delivery, Acceptance,
Handling and Storage
 Installation Concrete
Placement
 Tendon Stressing
 Elongation
 Tendon Finishing
 Encapsulation
 Jobsite Troubleshooting
 Appendix
33
Copyright © 2010 AMSYSCO, Inc.
6.2 Anchor Types
34
A. Fixed /Dead End – Anchor attached on one end of tendon.
Installed by PT supplier.
B. Intermediate Anchor– Anchor placed on tendon by PT
supplier. Moves freely until it is installed at construction joint
by PT installer.
C. Stressing /Live End – Anchor attached on one or two end(s)
of tendon. Installed by PT installer. Stressing occurs after
concrete reaches specified strength.
Copyright © 2010 AMSYSCO, Inc.
C B A
6.3 One-Way Slab
 BeamTendon – Group of
tendons placed inside a
beam. Supported by rebar.
(similar to girders, joists).
 Slab Tendon – Tendons or
Bundles of Tendons placed
in the slab that run
perpendicular to the beam.
Supported by chair and/or
rebar.
 Temperature Tendon –
Tendons placed in the slab
that run parallel to the
beam. Installed for crack-
control. Supported by
chair/rebar and/or on main
tendons.
35
Copyright © 2010 AMSYSCO, Inc.
6.4 Two-Way Slab
36
 Banded Tendon – Group
of tendons placed
together in a narrow strip
along the column line.
 Uniform/Distributed
Tendon – Tendons or
Bundles of Tendons
spaced uniformly that run
perpendicular to the
banded tendons.Copyright © 2010 AMSYSCO, Inc.
6.5 Slab-On-Ground
37
 Used mainly in residential housing foundation,
industrial floors or grade-level parking areas.
 Distributed tendons supported by chairs at
each intersection. Profile at mid-depth of slab
(unless there is a grade-beam).
 Tendons equally spaced, each way.
Copyright © 2010 AMSYSCO, Inc.
6.6 Concrete Placement
38
 Important to have proper strength before
stressing.
 Stressing should occur within 3-4 days of
pour.
 Dependant on 28 day strength and project
specs.
Copyright © 2010 AMSYSCO, Inc.
7. POST-CONCRETE PLACEMENT
39
Copyright © 2010 AMSYSCO, Inc.
7.1 Safety
40
 Proper installation and storage affects safety
 Equipment O&M Manuals
 Stressing by qualified personnel
 Controlled Access Area: No one allowed along
entire length of tendon.
 Recommend placing sand bags on top of Fixed
End and Stressing End in case of blowouts.
 Listen and watch equipment and concrete.
Copyright © 2010 AMSYSCO, Inc.
7.2 Stressing
41
 Before stressing:
 Concrete reach proper strength (typically 3000
psi)
 Clean anchor cavity with WD-40
 Install wedges, check alignment.
 Cross-Check equipment (automatic-seater)
 Stressing Video on AMSYSCO website
Copyright © 2010 AMSYSCO, Inc.
7.3 Elongations
 Paint Markings
 Proper Measuring
 Use metal object
 Stressing Record
 Approved by Structural Engineer
 “Negative” elongation is slippage
42
Copyright © 2010 AMSYSCO, Inc.
7.4 Cutting
43
 Different methods of cutting tendon tails:
 Oxyacetylene Torch (recommend fire-
watch/welder)
 Hydraulic Shear
 Plasma Cutter
 Abrasive Wheel
 Enough tail has to be cut to install snap cap.
 Abrasive wheel not recommended for this reason.
Copyright © 2010 AMSYSCO, Inc.
7.5 Grouting
 Non-shrink, Non-
chloride, Non-
corrosive.
 Reach required
strength.
 Clean anchor cavity
prior to grouting.
 Spray resin in
pocket to produce
better grout cap.
 Grout within 1-2
days of approved
stressing.
44
Copyright © 2010 AMSYSCO, Inc.
8. TROUBLESHOOTING
45
Copyright © 2010 AMSYSCO, Inc.
8.1 Pre-Installation Issues #1
 Missing Tendons
 Check packing slips
 Check color coding
 Check other bundles
 Short Length
Tendons
 Splice Coupler and
piece of tendon
 Or Replace tendon
 Damaged Tendons
 Anchor damage
(replace anchor)
 Kink in strand
(replace tendon)
46
Copyright © 2010 AMSYSCO, Inc.
8.1 Pre-Installation Issues #2
 Missing Accessories
 Support Chairs
 Anchors
 Wedges
 Pocket Formers
 Snap Caps, etc.
 Which Pours were
shipped? Compare
to packing slips.
 Plastic Sheathing
Issues
 Cuts (use repair
tape)
 Shrinkage at
anchors (use repair
tape/split-tubing or
replace tendon).
 Rebar congestion
 Beam anchor detail
 Allow for concrete
consolidation.
47
Copyright © 2010 AMSYSCO, Inc.
8.2 Equipment Issues #1
48
 Hydraulic Jack (Ram)
 Grippers
 Leaking
 Electric Pump
 Tripping breakers
 Gauge
 Needle jumps/stalls
 Hoses (10,000 psi)
 Pressure buildup
Copyright © 2010 AMSYSCO, Inc.
8.2 Equipment Issues #2
49
 Tips for Jack (Ram)
 Tighten screws for tendon-gripper.
 Remove concrete, etc. in nose-piece and grippers.
 Tips for Electric Pump / Gauge / Hoses
 Check rating and length of electric cord / generator.
 Check whether gauge starts at 0 psi.
 Tighten hose fittings and check for cuts in hoses.
 Check oil reservoir.
 DO NOT stress in rain/snow.
 Tie equipment off for fall-safety.
 DO NOT kick or drag equipment.
Copyright © 2010 AMSYSCO, Inc.
8.3 Field Issues #1
 Concrete Issues:
 Blowouts
 Honeycombing
 Voids
 How to repair???
 Installation Issues:
 Excessive tendon
curves (w/o hairpins)
can cause issues.
 Jobsite damage to
material.
50
Copyright © 2010 AMSYSCO, Inc.
8.3 Field Issues #2
 Elongations (± 7%)
 Over-elongation
means more force
provided than
anticipated.
 Under-elongation is
means less force
provided than
anticipated.
 Check mill certs, EL
range, tendon length,
equipment, anchor
cavity
 Strand Breakage or
Drilled Tendons
 PT Supplier can run
force calc to find out
remaining force.
 Replace or
Abandon.
 Approval by
Engineer of Record.
 Contact PT Supplier
51
Copyright © 2010 AMSYSCO, Inc.
AMSYSCO, INC.
THANK YOU !
AMSYSCO’s Online Network
Website: www.amsyscoinc.com
Blog: www.amsyscoinc.com/blog
Facebook: www.facebook.com/amsysco
LinkedIN: www.linkedin.com/company/amsysco-inc.
Twitter: www.twitter.com/amsyscoinc
YouTube: www.youtube.com/amsysco
52
Copyright © 2010 AMSYSCO, Inc.

Mais conteúdo relacionado

Mais procurados

Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wallHarsh Bothra
 
Prestressed Concrete Structures
Prestressed Concrete Structures Prestressed Concrete Structures
Prestressed Concrete Structures ABHISHEK SHARMA
 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete jaiveer singh
 
Raft foundations
Raft foundationsRaft foundations
Raft foundationshatim ahmed
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slabArvind Vishwakarma
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresHariyali Pujara
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajat Nainwal
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structuresLuan Truong Van
 
Composite structures of steel and concrete
Composite structures of steel and concreteComposite structures of steel and concrete
Composite structures of steel and concretePashtoon Khan
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girdersMD.Yeasin Mostafiz
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920INTEZAAR ALAM
 

Mais procurados (20)

Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Prestressed Concrete Structures
Prestressed Concrete Structures Prestressed Concrete Structures
Prestressed Concrete Structures
 
Pt slabs
Pt slabsPt slabs
Pt slabs
 
Prestress concrete
Prestress concretePrestress concrete
Prestress concrete
 
Prestresses concrete
Prestresses concrete Prestresses concrete
Prestresses concrete
 
Post tensioning
Post tensioningPost tensioning
Post tensioning
 
Raft foundations
Raft foundationsRaft foundations
Raft foundations
 
Column design.ppt
Column design.pptColumn design.ppt
Column design.ppt
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slab
 
Post Tension
Post TensionPost Tension
Post Tension
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
Prestressed
PrestressedPrestressed
Prestressed
 
Post tensioning in building structures
Post tensioning in building structuresPost tensioning in building structures
Post tensioning in building structures
 
Composite structures of steel and concrete
Composite structures of steel and concreteComposite structures of steel and concrete
Composite structures of steel and concrete
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
 

Destaque (6)

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Gyproc
GyprocGyproc
Gyproc
 
Final Construction Documents
Final Construction DocumentsFinal Construction Documents
Final Construction Documents
 
Partitions
PartitionsPartitions
Partitions
 
Partition wall
Partition wallPartition wall
Partition wall
 
Partition walls
Partition wallsPartition walls
Partition walls
 

Semelhante a Post-Tension Concrete - Info session for Contractors

CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment ReportWan Nee
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementBekaert
 
2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic PresentationQipei Mei
 
prestressing_manual.pdf
prestressing_manual.pdfprestressing_manual.pdf
prestressing_manual.pdfRiturajR
 
18CE71L SEMINAR (2).ppt
18CE71L SEMINAR (2).ppt18CE71L SEMINAR (2).ppt
18CE71L SEMINAR (2).pptssuser23ab30
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESIRJET Journal
 
Post formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsPost formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsCCL Concrete
 
Design of Metal Deck Sheet and Composite I-Section as secondary member
Design of Metal Deck Sheet and Composite I-Section as secondary memberDesign of Metal Deck Sheet and Composite I-Section as secondary member
Design of Metal Deck Sheet and Composite I-Section as secondary memberIRJET Journal
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+Est
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concreteARULPANDIAN8
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdfRijuDasgupta
 

Semelhante a Post-Tension Concrete - Info session for Contractors (20)

CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment Report
 
Difogfufl l
Difogfufl lDifogfufl l
Difogfufl l
 
Pre stress concrete
Pre stress concretePre stress concrete
Pre stress concrete
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Steel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcementSteel fibers vs steel mesh in concrete reinforcement
Steel fibers vs steel mesh in concrete reinforcement
 
2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation
 
Long Span Structures
Long Span StructuresLong Span Structures
Long Span Structures
 
prestress Register (1).pdf
prestress Register (1).pdfprestress Register (1).pdf
prestress Register (1).pdf
 
prestressing_manual.pdf
prestressing_manual.pdfprestressing_manual.pdf
prestressing_manual.pdf
 
18CE71L SEMINAR (2).ppt
18CE71L SEMINAR (2).ppt18CE71L SEMINAR (2).ppt
18CE71L SEMINAR (2).ppt
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Psc notes
Psc notesPsc notes
Psc notes
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURESREVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
REVIEW OF THE ROLE OF JOINTS USAGE IN BRIDGE STRUCTURES
 
Post formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabsPost formed holes-in_post-tensioned_slabs
Post formed holes-in_post-tensioned_slabs
 
Design of Metal Deck Sheet and Composite I-Section as secondary member
Design of Metal Deck Sheet and Composite I-Section as secondary memberDesign of Metal Deck Sheet and Composite I-Section as secondary member
Design of Metal Deck Sheet and Composite I-Section as secondary member
 
CT 3 +5 prestressing b+
CT 3 +5 prestressing b+CT 3 +5 prestressing b+
CT 3 +5 prestressing b+
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 

Mais de AMSYSCO Inc.

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningAMSYSCO Inc.
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldAMSYSCO Inc.
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven TowerAMSYSCO Inc.
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckAMSYSCO Inc.
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureAMSYSCO Inc.
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionAMSYSCO Inc.
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO Inc.
 
PTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementPTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementAMSYSCO Inc.
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)AMSYSCO Inc.
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersAMSYSCO Inc.
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningAMSYSCO Inc.
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationAMSYSCO Inc.
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningAMSYSCO Inc.
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small BusinessAMSYSCO Inc.
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow AwardsAMSYSCO Inc.
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards BookletAMSYSCO Inc.
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned ConcreteAMSYSCO Inc.
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post TensioningAMSYSCO Inc.
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville ArenaAMSYSCO Inc.
 

Mais de AMSYSCO Inc. (20)

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and Field
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven Tower
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deck
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay Infrastructure
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 Trillion
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall Buildings
 
PTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavementPTI Journal : Buford Ave post-tensioned pavement
PTI Journal : Buford Ave post-tensioned pavement
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for Installers
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post Tensioning
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field Certification
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post Tensioning
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small Business
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards Booklet
 
Build for You
Build for YouBuild for You
Build for You
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville Arena
 

Último

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524najka9823
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 

Último (20)

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 

Post-Tension Concrete - Info session for Contractors

  • 2. OUTLINE of INFO SESSION PART ONE 1. Introduction to Post-Tension 2. Components of Post-Tension 3. Construction Team 4. Submittals PART TWO 5. Pre-Installation 6. Installation Management 7. Post-Concrete Placement PART THREE 8. Troubleshooting 2 Copyright © 2010 AMSYSCO, Inc. Click this icon to view video in presentation
  • 3. 1. INTRO to POST-TENSIONING 3 Copyright © 2010 AMSYSCO, Inc.
  • 4. 1.1 History of Post-Tensioning  Post-Tensioning is a method of prestressing. Concrete is weak in tension. PT increases concrete’s ability to perform under tensile stresses. Tendons are tensioned after the concrete is poured.  1928 : Modern Prestressed Concrete “invented.”  1946 : Post- Tensioning gained momentum in Europe due to steel shortage.  1951 : 1st PT bridge constructed in U.S.  1963 : Prestressed Concrete incorporated into ACI Code.  1976 : Post- Tensioning Institute (PTI) founded. 4 Copyright © 2010 AMSYSCO, Inc.
  • 5. 1.2 AMSYSCO, Inc. 5  1981 : AMSYSCO, Inc. founded by Rattan Khosa  1984 : Joined PTI  1985 : Installed extrusion line equipment  1989 : Became PTI Plant Certified  1990 : Rattan Khosa elected to PTI Executive Committee  1999 : Rattan Khosa became President of PTI (2yrs)  2000 : Completed 400th unbonded PT project  2003 : Neel Khosa joined AMSYSCO  2007 : Moved headquarters to Romeoville, IL  2008 : Awarded PTI Project of the Year (Guthrie)  2009 : Completed Target Field (MN Twins) Copyright © 2010 AMSYSCO, Inc. AMSYSCO, Inc. P: 630-296-8383 1200 Windham Parkway F: 630-296-8380 Romeoville, IL 60446 www.amsyscoinc.com
  • 6. 1.3.1 Types of Post-Tensioning 6 PRESTRESSING STEEL TENDONS  Mono-Strand = One single strand per tendon.  Multi-Strand = Multiple strands per tendon.  Unbonded: Tendon encased in plastic sheathing. Does not bond to concrete. Force transferred by the anchorage only.  Bonded: Tendon installed in ducts that are pumped with grout after stressing. Bonds to concrete. Copyright © 2010 AMSYSCO, Inc.
  • 7.  Commercial High-Rise  Multi-Family Housing  Residential Housing (SOG)  Parking Structures  Stadiums / Theaters 1.3.2 Uses of Post-Tensioning  Bridges  Stadiums  Tennis Courts  Water Tanks / Silos  Nuclear Plants  Repair & Restoration 7 Copyright © 2010 AMSYSCO, Inc.
  • 8. 1.4 Benefits of Unbonded Post- Tension8 Copyright © 2010 AMSYSCO, Inc.
  • 9. 2. COMPONENTS of Post-Tension 9 Copyright © 2010 AMSYSCO, Inc.
  • 10. 2.1.1 Strand – Bare 10  Strand: Hig h-stre ng th ste e lwire . 6 -wire s twist aro und 7 th ce ntral“king ”-wire . Typicaldiam e te rs are 0 . 5” and 0 . 6 ”.  Tendon: Strand that is e ncase d with a laye r o f co rro sive -inhibito r (g re ase ) and plastic she athing .Strand 0.5” 0.6” Units Weight 0.525 0.740 lbs per ft Ultimate Stress 270 270 ksi Cross-sectional area 0.153 0.217 sq.in. MUTS = ksi x sq.in. 41.3 58.6 kips Jacking Force = 80% MUTS 33 46.8 kips Avg. Final Effective Force ~27.5 ~38.0 kips Elongation = approx. 8” per 100’-0 tendon length inches Copyright © 2010 AMSYSCO, Inc.
  • 11. 2.1.2 Strand – Coated 11  PT Coating or Tendon Grease  Reduces friction during stressing  Le ss frictio n m e ans m o re fo rce pe r te ndo n.  Eliminates rifling in plastic sheathing  Protects Strand from corrosion  PT Sheathing or Plastic Sheathing  Extruded HDPE  Acts as bond breaker to enable stressing  Contains PT Coating  Acts as additional corrosion barrier Copyright © 2010 AMSYSCO, Inc.
  • 12. 2.2 Anchor, Wedges, Pocket Former12  Anchor: Casting which houses wedges used to transfer prestressing force to concrete.  Fixed Anchor – installed in supplier’s plant  Intermediate Stressing – located at construction joints  Stressing Anchor – where jacking force is applied  Wedges : Tapered high-strength steel with teeth.  Pocket Former: Temporary device that creates opening/pocket in concrete to allow for stressing.Copyright © 2010 AMSYSCO, Inc.
  • 13. 2.3 Encapsulated vs. Regular 13 Component ENCAPSULATED REGULAR Plastic Sheathing 50 ML 40 or 50 ML Anchors Plastic-Coated Metal Uncoated Metal Pocket Formers YES YES Snap Caps YES NO Wedges YES YES Translucent Sleeves YES NO - filled with grease YES N/A Positive Mechanical Connection YES NO Seal Plugs YES NO Protection during shipping YES De pe nds o n spe c. Copyright © 2010 AMSYSCO, Inc.
  • 14. 2.4.1 Supports – Definitions 14  C.G.S. = Center of Gravity of Steel  C.G.C. = Center of Gravity of Concrete  AT ANCHORAGES: C.G.S. = C.G.C. ______________________________________ _____  Profile /Drape: Te ndo n e le vatio n inside co ncre te .  Slab-On-Ground has no drape in slab (not in beams).  High Point: Co ntro lpo int at co lum n suppo rts . Copyright © 2010 AMSYSCO, Inc.
  • 15. 2.4.2 Supports – Function 15  Maintains tendon drape & Reduces tendon wobble.  Stabilizes tendon during concrete placement.  Support Chair: Plastic supports used in slabs.  Support Bar: #4 Bar.  Slab Bolster: Used at slab midspans. No bar required.  BeamSupports: Attach U-bars to stirrups.  Maximum 48” spacing (U.N.O.) Copyright © 2010 AMSYSCO, Inc.
  • 16. 2.5 Stressing Equipment 16  Hydraulic Jack/Ram and Electric Pump with Gauge.  Needs 110V, 30 amps power with cords that are 3-wire, 12-gauge and less than 100 feet long. Copyright © 2010 AMSYSCO, Inc.
  • 17.  Used for pedestrian and/or vehicular restraint.  Same as 0.5” Post-Tensioning strand.  Except for galvanization or epoxy coating.  Anchorage devices may be different also. 2.6 Barrier Cable 17 Copyright © 2010 AMSYSCO, Inc.
  • 18. 3. CONSTRUCTION TEAM 18 Copyright © 2010 AMSYSCO, Inc.
  • 19. 3.1 Architect & Structural Engineer19  ARCHITECT  Provides building dimensions and layout.  Provides barrier cable design.  STRUCTURAL ENGINEER  Provides structural design for post-tensioning, etc.  Provides concrete mix design requirements.  Adherence to building and seismic codes (IBC, etc.)  General and special requirements. Copyright © 2010 AMSYSCO, Inc.
  • 20. 3.2 General Contractor 20  Provides latest design documents to PT Supplier.  Approves pour sequence.  Coordinates post-tensioning with other trades (embeds, stairs, openings etc.) that may affect the access to stressing tendons.  Manages post-tensioning process. Copyright © 2010 AMSYSCO, Inc. Should obtain from PT Supplier: • Bare and Gross weight of PT • # of Holes in bulkhead to stress • # Pockets to grout • Support/Backup bar tonnage (epoxy) • Pour Sequence
  • 21. 3.3 Post-Tension Supplier 21  Must ship material from a PTI Certified Plant.  Responsibilities include:  Provide installation shop drawings and calcs that meet requirement in structural design drawings.  Furnish post-tensioning tendons and accessories to meet structural specifications.  Certify calibrated stressing equipment.  Assist in solving preconstruction and field issues related to post-tensioning.  Provide theoretical elongation ranges. Copyright © 2010 AMSYSCO, Inc.
  • 22. 3.4 Post-Tension Installer  Should be PTI Certified – Level 2 Ironworker (o r e q ual).  For safety reasons, individuals operating stressing equipment must have experience in stressing and basic maintenance.  Should keep a copy of the PTI ‘Fie ld Manual’ onsite. 22 Copyright © 2010 AMSYSCO, Inc.
  • 23. 3.5 Post-Tension Inspector 23  Should be PTI Certified – Level 2 Inspector.  Independent party from PT Supplier and Installer.  Responsibilities include:  Check tendon profiles.  Monitor stressing operations.  Measure elongations after stressing.  Compare measured to theoretical elongations.  Make elongation report for Str. Engineer’s approval.Copyright © 2010 AMSYSCO, Inc.
  • 24. 3.6 Other Subcontractors 24  RebarSupplier– needs bar list for support steel.  Forming Contractor– needs pour sequence.  Concrete Supplier– mix design to ensure adequate concrete strength at time of stressing.  MEPTrades – coordinate openings for office/residential.  Trades with Embeds – architectural precast, Copyright © 2010 AMSYSCO, Inc.
  • 25. 4. SUBMITTALS 25 Copyright © 2010 AMSYSCO, Inc.
  • 26. 4.1 Construction Documents 26  Drawings  Structural  Architectural  Specifications  Post-Tensioning (Division 3)  Barrier Cable (Division 5)  Construction Schedule  Forming, Delivery, Installation and Stressing dates Copyright © 2010 AMSYSCO, Inc.
  • 27. 4.2 Pre-Detailing 27  CAD Files  Pour Sequence  Construction Joints  Pour Strips  Stressing Restrictions  Scope review  Special requirements  Coordination with other trades  Openings (MEP, crane) & Embeds (precast, curtainwall) Copyright © 2010 AMSYSCO, Inc.
  • 28. 4.3 Post-Tensioning Submittals 28  Installation Drawings  Tendon Plan  Support Plan  Beam End View Details  Friction Calculations  Product / Test Data  Bar List (support/backup)  Mill Certificates  Samples Copyright © 2010 AMSYSCO, Inc.
  • 30. 5.1 PTI Certified Plant  Fabrication  Raw Materials  PT Coating/Grease  Plastic Sheathing  Corrosion Protection  Delivery  Mill Certs  Bill of Lading  Cutting Lists  Jack Calibration 30 Copyright © 2010 AMSYSCO, Inc.
  • 31. 5.2 Jobsite  Unloading & Handling without damaging PT  Storage to protect from corrosion.  Organization of post-tension inventory.  Safety during installation and stressing. 31 Copyright © 2010 AMSYSCO, Inc.
  • 32. 6. JOBSITE INSTALLATION 32 Copyright © 2010 AMSYSCO, Inc.
  • 33. 6.1 PTI Field Procedures Manual  Published by Post- Tensioning Institute  Provides procedures and details for post- tensioned concrete installation.  Introduction  Document Control  Delivery, Acceptance, Handling and Storage  Installation Concrete Placement  Tendon Stressing  Elongation  Tendon Finishing  Encapsulation  Jobsite Troubleshooting  Appendix 33 Copyright © 2010 AMSYSCO, Inc.
  • 34. 6.2 Anchor Types 34 A. Fixed /Dead End – Anchor attached on one end of tendon. Installed by PT supplier. B. Intermediate Anchor– Anchor placed on tendon by PT supplier. Moves freely until it is installed at construction joint by PT installer. C. Stressing /Live End – Anchor attached on one or two end(s) of tendon. Installed by PT installer. Stressing occurs after concrete reaches specified strength. Copyright © 2010 AMSYSCO, Inc. C B A
  • 35. 6.3 One-Way Slab  BeamTendon – Group of tendons placed inside a beam. Supported by rebar. (similar to girders, joists).  Slab Tendon – Tendons or Bundles of Tendons placed in the slab that run perpendicular to the beam. Supported by chair and/or rebar.  Temperature Tendon – Tendons placed in the slab that run parallel to the beam. Installed for crack- control. Supported by chair/rebar and/or on main tendons. 35 Copyright © 2010 AMSYSCO, Inc.
  • 36. 6.4 Two-Way Slab 36  Banded Tendon – Group of tendons placed together in a narrow strip along the column line.  Uniform/Distributed Tendon – Tendons or Bundles of Tendons spaced uniformly that run perpendicular to the banded tendons.Copyright © 2010 AMSYSCO, Inc.
  • 37. 6.5 Slab-On-Ground 37  Used mainly in residential housing foundation, industrial floors or grade-level parking areas.  Distributed tendons supported by chairs at each intersection. Profile at mid-depth of slab (unless there is a grade-beam).  Tendons equally spaced, each way. Copyright © 2010 AMSYSCO, Inc.
  • 38. 6.6 Concrete Placement 38  Important to have proper strength before stressing.  Stressing should occur within 3-4 days of pour.  Dependant on 28 day strength and project specs. Copyright © 2010 AMSYSCO, Inc.
  • 40. 7.1 Safety 40  Proper installation and storage affects safety  Equipment O&M Manuals  Stressing by qualified personnel  Controlled Access Area: No one allowed along entire length of tendon.  Recommend placing sand bags on top of Fixed End and Stressing End in case of blowouts.  Listen and watch equipment and concrete. Copyright © 2010 AMSYSCO, Inc.
  • 41. 7.2 Stressing 41  Before stressing:  Concrete reach proper strength (typically 3000 psi)  Clean anchor cavity with WD-40  Install wedges, check alignment.  Cross-Check equipment (automatic-seater)  Stressing Video on AMSYSCO website Copyright © 2010 AMSYSCO, Inc.
  • 42. 7.3 Elongations  Paint Markings  Proper Measuring  Use metal object  Stressing Record  Approved by Structural Engineer  “Negative” elongation is slippage 42 Copyright © 2010 AMSYSCO, Inc.
  • 43. 7.4 Cutting 43  Different methods of cutting tendon tails:  Oxyacetylene Torch (recommend fire- watch/welder)  Hydraulic Shear  Plasma Cutter  Abrasive Wheel  Enough tail has to be cut to install snap cap.  Abrasive wheel not recommended for this reason. Copyright © 2010 AMSYSCO, Inc.
  • 44. 7.5 Grouting  Non-shrink, Non- chloride, Non- corrosive.  Reach required strength.  Clean anchor cavity prior to grouting.  Spray resin in pocket to produce better grout cap.  Grout within 1-2 days of approved stressing. 44 Copyright © 2010 AMSYSCO, Inc.
  • 46. 8.1 Pre-Installation Issues #1  Missing Tendons  Check packing slips  Check color coding  Check other bundles  Short Length Tendons  Splice Coupler and piece of tendon  Or Replace tendon  Damaged Tendons  Anchor damage (replace anchor)  Kink in strand (replace tendon) 46 Copyright © 2010 AMSYSCO, Inc.
  • 47. 8.1 Pre-Installation Issues #2  Missing Accessories  Support Chairs  Anchors  Wedges  Pocket Formers  Snap Caps, etc.  Which Pours were shipped? Compare to packing slips.  Plastic Sheathing Issues  Cuts (use repair tape)  Shrinkage at anchors (use repair tape/split-tubing or replace tendon).  Rebar congestion  Beam anchor detail  Allow for concrete consolidation. 47 Copyright © 2010 AMSYSCO, Inc.
  • 48. 8.2 Equipment Issues #1 48  Hydraulic Jack (Ram)  Grippers  Leaking  Electric Pump  Tripping breakers  Gauge  Needle jumps/stalls  Hoses (10,000 psi)  Pressure buildup Copyright © 2010 AMSYSCO, Inc.
  • 49. 8.2 Equipment Issues #2 49  Tips for Jack (Ram)  Tighten screws for tendon-gripper.  Remove concrete, etc. in nose-piece and grippers.  Tips for Electric Pump / Gauge / Hoses  Check rating and length of electric cord / generator.  Check whether gauge starts at 0 psi.  Tighten hose fittings and check for cuts in hoses.  Check oil reservoir.  DO NOT stress in rain/snow.  Tie equipment off for fall-safety.  DO NOT kick or drag equipment. Copyright © 2010 AMSYSCO, Inc.
  • 50. 8.3 Field Issues #1  Concrete Issues:  Blowouts  Honeycombing  Voids  How to repair???  Installation Issues:  Excessive tendon curves (w/o hairpins) can cause issues.  Jobsite damage to material. 50 Copyright © 2010 AMSYSCO, Inc.
  • 51. 8.3 Field Issues #2  Elongations (± 7%)  Over-elongation means more force provided than anticipated.  Under-elongation is means less force provided than anticipated.  Check mill certs, EL range, tendon length, equipment, anchor cavity  Strand Breakage or Drilled Tendons  PT Supplier can run force calc to find out remaining force.  Replace or Abandon.  Approval by Engineer of Record.  Contact PT Supplier 51 Copyright © 2010 AMSYSCO, Inc.
  • 52. AMSYSCO, INC. THANK YOU ! AMSYSCO’s Online Network Website: www.amsyscoinc.com Blog: www.amsyscoinc.com/blog Facebook: www.facebook.com/amsysco LinkedIN: www.linkedin.com/company/amsysco-inc. Twitter: www.twitter.com/amsyscoinc YouTube: www.youtube.com/amsysco 52 Copyright © 2010 AMSYSCO, Inc.