SlideShare uma empresa Scribd logo
1 de 8
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
0
Project Management
Resource Allocation and Smoothing
Dr. Mahmoud Abbas Mahmoud
Assistant Professor
2017
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
1
Resource Allocation and Smoothing
1. Resource Planning
A resource may be defined as the machine or person who will perform the scope
of work. Resource planning is forecasting the resources required to perform the
scope of work within the time plan.
The resource constraint should be considered after the network diagram, schedule
bar chart and procurement schedule have been developed. But before the crash-
flow statement.
2. Resource Estimating
The resource estimates is linked directly to the scope of work and bill of materials
(BOM). The scope of work may be expressed as so many tons of steel, or so many
square meters of wall paint etc. From this description estimator can convert the
scope of work into manhours per unit ‘X’.
Consider the following, if the scope of work is to erect (assemble) 12 tons of steel
and the estimator knows from past experience that the work can be done in 150
manhours per ton and the men work 10 hour shifts, then the equation is:
( 12 tons × 150 manhours per ton )
10 hrs per day
= 180 mandays
Resource / Duration Trade-Off
3. Resource Forecasting
Resource forecasting is to forecast the total resource requirement by discipline or
interchangeable resource. An interchangeable resource is when you have a pool
(group) of workers and any one of them could perform the work. This is done by
compiling all the resource estimates and presenting them in a structured resource
table.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
2
Resource Table
Resource Forecast - Bar Chart
Resource Forecast – Histogram
Note: The bar chart shows the number of resources per activity per day, and the
histogram shows the total recourse required per day.
4. Resource Availability
In establishing the resource availability, the following points should be
considered:
a- Other resource commitments - if your company is involved in a number of
projects which all draw from a common labor pool, the other projects'
requirements must also be considered (also called multi-project resource
scheduling).
b- The anticipated sickness and absenteeism rate. For example: allow for a
25% absentee rate based on experience.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
3
Planning for a 25% Absenteeism
Keeping the above points in mind, the resource availability table will be
developed. Consider the following example:
5. Resource Histogram
The resource histogram is a popular planning tool because it gives a good visual
presentation which is easy to assimilate and understand. The prerequisites for
drawing the resource histogram are:
a- Early start bar chart (after considering the procurement requirements which
ensure the materials and equipment are available)
b- Resource forecast per activity.
Consider the following example:
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
4
Resource Table
Resource Bar chart and Histogram
6. Resource Loading
The resource forecast is now compared with the resources available. The ideal
situation is achieved when the resource requirement equals the resources
available. Unfortunately, in project management this seldom happens, because it
is not always possible to adjust supply with demand, so some form of compromise
is essential.
A resource overload is when the resource forecast exceeds the available
resources, while a resource under-load is when resource forecast is lower than the
available resource.
A resource overload will lead to some activities being delayed which could delay
the completion of the project.
A resource under-load will under-utilize the company's resources which could
have a detrimental effect on the company's profitability.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
5
Resource Loading (overloading and under-loading)
The overloads and under-loads can now be identified and addressed as follows:
a- Resource Smoothing: assign resources to critical activities first, then try
moving the other activities to ease any overload and under-utilization.
b- Time-Limited Resource Scheduling: the end date of the project is fixed,
so resources must be increased to address any overloads.
c- Resource-Limited Resource Scheduling: the maximum number of
resources is fixed, so the end date may need to be extended to address any
overload.
d- Increase Resources: to address an overload.
e- Reduce Resources: to address an under-load (under-utilized).
7. Resource Smoothing
Resource smoothing is the process of moving activities to improve the resource
loading profile.
The first step is to select the resource to be smoothed. To decide which resource
to smooth consider:
a- The resource that is most overloaded.
b- The resource that is most used on the project.
c- The least flexible resource - this could be the resource that comes from
overseas, is difficult to get hold of or is least available.
d- The most expensive resource to hire.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
6
Example:
Resource Bar chart and Histogram
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
7
Smoothed Bar chart and Histogram

Mais conteúdo relacionado

Mais procurados

Resource Planning
Resource PlanningResource Planning
Resource PlanningWajahat Ali
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Project Resource Allocation
Project Resource AllocationProject Resource Allocation
Project Resource Allocationmohsin iqbal
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)Mayur Rahangdale
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management A Makwana
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPMMunaf Dayee
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationAnand Bobade
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 

Mais procurados (20)

Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
crashing of project
crashing of project crashing of project
crashing of project
 
Project Resource Allocation
Project Resource AllocationProject Resource Allocation
Project Resource Allocation
 
RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)RESOURCE LEVELLING (MS PROJECT)
RESOURCE LEVELLING (MS PROJECT)
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management Project scheduling and resource levelling_Construction Management
Project scheduling and resource levelling_Construction Management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Pert
PertPert
Pert
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 

Destaque

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsian jones
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementBob Zoller
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation Riadh Mohammed Arif
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017Carol Smith
 

Destaque (13)

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Resource management
Resource managementResource management
Resource management
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tips
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_Management
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Semelhante a Resource allocation and smoothing

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...HIMADRI BANERJI
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementOrangescrum
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxaryan532920
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxIftikhar1985
 
Project management teaching
Project management   teachingProject management   teaching
Project management teachingCHIRANJAN SAHA
 

Semelhante a Resource allocation and smoothing (20)

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
B012440511
B012440511B012440511
B012440511
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources Management
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptx
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptxCE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
 
Resource management
Resource managementResource management
Resource management
 
Project management teaching
Project management   teachingProject management   teaching
Project management teaching
 
CAPM Study Session 3
CAPM Study Session 3CAPM Study Session 3
CAPM Study Session 3
 

Mais de Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsDr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Dr. Mahmoud Al-Naimi
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 

Mais de Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 

Último

Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 

Último (20)

Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 

Resource allocation and smoothing

  • 1. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 0 Project Management Resource Allocation and Smoothing Dr. Mahmoud Abbas Mahmoud Assistant Professor 2017
  • 2. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 1 Resource Allocation and Smoothing 1. Resource Planning A resource may be defined as the machine or person who will perform the scope of work. Resource planning is forecasting the resources required to perform the scope of work within the time plan. The resource constraint should be considered after the network diagram, schedule bar chart and procurement schedule have been developed. But before the crash- flow statement. 2. Resource Estimating The resource estimates is linked directly to the scope of work and bill of materials (BOM). The scope of work may be expressed as so many tons of steel, or so many square meters of wall paint etc. From this description estimator can convert the scope of work into manhours per unit ‘X’. Consider the following, if the scope of work is to erect (assemble) 12 tons of steel and the estimator knows from past experience that the work can be done in 150 manhours per ton and the men work 10 hour shifts, then the equation is: ( 12 tons × 150 manhours per ton ) 10 hrs per day = 180 mandays Resource / Duration Trade-Off 3. Resource Forecasting Resource forecasting is to forecast the total resource requirement by discipline or interchangeable resource. An interchangeable resource is when you have a pool (group) of workers and any one of them could perform the work. This is done by compiling all the resource estimates and presenting them in a structured resource table.
  • 3. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 2 Resource Table Resource Forecast - Bar Chart Resource Forecast – Histogram Note: The bar chart shows the number of resources per activity per day, and the histogram shows the total recourse required per day. 4. Resource Availability In establishing the resource availability, the following points should be considered: a- Other resource commitments - if your company is involved in a number of projects which all draw from a common labor pool, the other projects' requirements must also be considered (also called multi-project resource scheduling). b- The anticipated sickness and absenteeism rate. For example: allow for a 25% absentee rate based on experience.
  • 4. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 3 Planning for a 25% Absenteeism Keeping the above points in mind, the resource availability table will be developed. Consider the following example: 5. Resource Histogram The resource histogram is a popular planning tool because it gives a good visual presentation which is easy to assimilate and understand. The prerequisites for drawing the resource histogram are: a- Early start bar chart (after considering the procurement requirements which ensure the materials and equipment are available) b- Resource forecast per activity. Consider the following example:
  • 5. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 4 Resource Table Resource Bar chart and Histogram 6. Resource Loading The resource forecast is now compared with the resources available. The ideal situation is achieved when the resource requirement equals the resources available. Unfortunately, in project management this seldom happens, because it is not always possible to adjust supply with demand, so some form of compromise is essential. A resource overload is when the resource forecast exceeds the available resources, while a resource under-load is when resource forecast is lower than the available resource. A resource overload will lead to some activities being delayed which could delay the completion of the project. A resource under-load will under-utilize the company's resources which could have a detrimental effect on the company's profitability.
  • 6. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 5 Resource Loading (overloading and under-loading) The overloads and under-loads can now be identified and addressed as follows: a- Resource Smoothing: assign resources to critical activities first, then try moving the other activities to ease any overload and under-utilization. b- Time-Limited Resource Scheduling: the end date of the project is fixed, so resources must be increased to address any overloads. c- Resource-Limited Resource Scheduling: the maximum number of resources is fixed, so the end date may need to be extended to address any overload. d- Increase Resources: to address an overload. e- Reduce Resources: to address an under-load (under-utilized). 7. Resource Smoothing Resource smoothing is the process of moving activities to improve the resource loading profile. The first step is to select the resource to be smoothed. To decide which resource to smooth consider: a- The resource that is most overloaded. b- The resource that is most used on the project. c- The least flexible resource - this could be the resource that comes from overseas, is difficult to get hold of or is least available. d- The most expensive resource to hire.
  • 7. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 6 Example: Resource Bar chart and Histogram
  • 8. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 7 Smoothed Bar chart and Histogram