Easy Steps to Critical Path
Determination and Floats Calculations
for Projects
Project Management
Dr. Mahmoud Abbas Mahmoud
Asst. Prof.
2016
Easy Steps to Critical Path
Determination and Floats Calculations
for Projects
We will illustrate these
steps with the following
Example:
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
Example:
For the project given in the following (AOA) network diagram:
i) Find the critical activities.
ii) Find the critical path (CP).
iii) Find project completion time.
iv) Find the free float (FF) for each activity.
v) Summarize the results in a table.
Note: all times are in (weeks)
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
Critical Path Calculations
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
Forward Pass:
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
Forward Pass:
Calculating the Earliest Start Time (ES):
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
Forward Pass:
Calculating the Earliest Start Time (ES):
Earliest Start Time (ES)j=Max [ (ES)i + Dij ]
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
Earliest Start Time (ES) for Start Event = (0)
NOTE: (ES) for any Start Event = (0)
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
10[0+10]= 10
0
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15 Max [(0+7) , (10+5)] = Max [7,15]= 15
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
[10+ 6]= 16
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
Max [(15+9) , (16+0)] =
Max [24,16]= 24
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
Max [(16+8) , (24+12)]
= Max [24,36]= 36
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
Project completion time is: 36 weeks
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
Backward Pass:
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
36
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
36
Calculating the Latest Completion Time (LC):
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
36
36
Calculating the Latest Completion Time (LC):
Latest Completion Time (LC)i=Min [ (LC)j - Dij ]
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
16
24
24
36
36
36 – 12 = 24
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
24
16
24
24
36
36
Min [(36-8),(24-0)=
Min[28,24] = 24
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
15
15
24
16
24
24
36
36
24 – 9 = 15
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
10
10
15
15
24
16
24
24
36
36
Min [(24-6),(15-5)=
Min[18,10] = 10
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Min [(15-7),(10-10)=
Min[8, 0] = 0
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
Dr. Mahmoud Abbas Mahmoud
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
How to find the Critical Activities and
the Critical Path ???
Dr. Mahmoud Abbas Mahmoud
Remember that only a critical
activity can have a Zero Total
Float (TF)
Dr. Mahmoud Abbas Mahmoud
Therefore, we will calculate
the total floats for all
activities and each activity
has a ZERO total float (TF) will
be a critical activity.
Total Float (TF) calculations
Dr. Mahmoud Abbas Mahmoud
TFij = (LC)j – (ES)i – Dij
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
A
B
C
D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
B
C
D
E
F
G
Dummy
For activity A (1, 2)
TF = 10 – 0 – 10 = 0*
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
B
C
D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
C
D
E
F
G
Dummy
For activity B (1, 3)
TF = 15 – 0 – 7 = 8
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
C
D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
D
E
F
G
Dummy
For activity C (2, 3)
TF = 15 – 10 – 5 = 0*
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
E
F
G
Dummy
For activity D (3, 4)
TF = 24 – 10 – 6 = 8
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
F
G
Dummy
For activity E (3, 5)
TF = 24 – 15 – 9 = 0*
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
G
Dummy
For activity F (4, 6)
TF = 36 – 16 – 8 = 12
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
Yes0G
Dummy
For activity G (5, 6)
TF = 36 – 24 – 12 = 0*
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
Yes0G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
Yes0G
No8Dummy
For Dummy activity (4, 5)
TF = 24 – 16 – 0 = 8
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
Yes0G
No8Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
CriticalTotal FloatActivity
Yes0A
No8B
Yes0C
No8D
Yes0E
No12F
Yes0G
No8Dummy
The Critical Activities are: (A, C, E, G)
Critical Path is: (A C E G)
Project completion time is: 36 weeks
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free Float (FF) Calculations
FFij = (ES)j – (ES)i – Dij
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
A
B
C
D
E
F
G
Dummy
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
B
C
D
E
F
G
Dummy
For activity A (1, 2)
FF = 10 – 0 – 10 = 0
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
C
D
E
F
G
Dummy
For activity B (1, 3)
FF = 15 – 0 – 7 = 8
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
D
E
F
G
Dummy
For activity C (2, 3)
FF = 15 – 10 – 5 = 0
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
0D
E
F
G
Dummy
For activity D (3, 4)
FF = 16 – 10 – 6 = 0
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
0D
0E
F
G
Dummy
For activity E (3, 5)
FF = 24 – 15 – 9 = 0
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
0D
0E
12F
G
Dummy
For activity F (4, 6)
FF = 36 – 16 – 8 = 12
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
0D
0E
12F
0G
Dummy
For activity G (5, 6)
FF = 36 – 24 – 12 = 0
Dr. Mahmoud Abbas Mahmoud
A= 10
B= 7
1
2
3
C= 5
D= 6
E= 9
4
5
6Dummy
F= 8
G= 12
0
0
0
10
10
15
15
24
16
24
24
36
36
Free FloatActivity
0A
8B
0C
0D
0E
12F
0G
8Dummy
For Dummy activity (4, 5)
FF = 24 – 16 – 0 = 8
Dr. Mahmoud Abbas Mahmoud
Free FloatActivity
0A
8B
0C
0D
0E
12F
0G
8Dummy
Think !!!!
Dr. Mahmoud Abbas Mahmoud
We can notice from these
results that all critical activities
must have zero free floats but
not each activity that has zero
free float must be critical.
For example, activity (D) has
zero Free Float but it is not
critical.
Free FloatActivity
0A
8B
0C
0D
0E
12F
0G
8Dummy
Summary
Activity
Symbol
Activity
(i, j)
Duration
Dij
ESi LCj TFij FFij
A (1, 2) 10 0 10 0* 0
B (1, 3) 7 0 15 8 8
C (2, 3) 5 10 15 0* 0
D (2, 4) 6 10 24 8 0
E (3, 5) 9 15 24 0* 0
Dummy (4, 5) 0 16 24 8 8
F (4, 6) 8 16 36 12 12
G (5, 6) 12 24 36 0* 0
Notice that total float (TF) values marked with (*) mark
are for critical activities.
Dr. Mahmoud Abbas Mahmoud
Dr. Mahmoud Al-Naimi

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)Construction report (boq, wbs, reports, evm)
Construction report (boq, wbs, reports, evm)
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Quantity Surveying & Cost Planning
Quantity Surveying & Cost PlanningQuantity Surveying & Cost Planning
Quantity Surveying & Cost Planning
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project controls
Project controlsProject controls
Project controls
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear project
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Volume
VolumeVolume
Volume
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 

Destaque

What is Job Follow-Up letter
What is Job Follow-Up letterWhat is Job Follow-Up letter
What is Job Follow-Up letterNavdeep Kumar
 
Cv & covering letter
Cv & covering letterCv & covering letter
Cv & covering lettertorrepacheco
 
PM Session 8
PM Session 8PM Session 8
PM Session 8dmdk12
 
Project Termination
Project TerminationProject Termination
Project TerminationSajjad Sayed
 
Writing a Covering Letter
Writing a Covering LetterWriting a Covering Letter
Writing a Covering LetterSanthy Subbarau
 
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...Jack Morton Worldwide
 
Termination.project management
Termination.project managementTermination.project management
Termination.project managementMarius Miron
 
How to write a CV and a Covering Letter
How to write a CV and a Covering LetterHow to write a CV and a Covering Letter
How to write a CV and a Covering Lettermaochoa35
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
Effective Resume Writing
Effective Resume WritingEffective Resume Writing
Effective Resume WritingArsalan Ahmad
 
Sample resume ppt
Sample resume pptSample resume ppt
Sample resume pptlissarray
 
Resume writing ppt presentation
Resume writing ppt presentationResume writing ppt presentation
Resume writing ppt presentationctccareer
 

Destaque (16)

Covering Letter
Covering LetterCovering Letter
Covering Letter
 
What is Job Follow-Up letter
What is Job Follow-Up letterWhat is Job Follow-Up letter
What is Job Follow-Up letter
 
Cv & covering letter
Cv & covering letterCv & covering letter
Cv & covering letter
 
PM Session 8
PM Session 8PM Session 8
PM Session 8
 
Project Termination
Project TerminationProject Termination
Project Termination
 
Writing a Covering Letter
Writing a Covering LetterWriting a Covering Letter
Writing a Covering Letter
 
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...
Marketer's guide to Facebook timeline: Tips for brands and marketers for the ...
 
Project Termination
Project TerminationProject Termination
Project Termination
 
Termination.project management
Termination.project managementTermination.project management
Termination.project management
 
Project termination
Project terminationProject termination
Project termination
 
How to write a CV and a Covering Letter
How to write a CV and a Covering LetterHow to write a CV and a Covering Letter
How to write a CV and a Covering Letter
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Effective Resume Writing
Effective Resume WritingEffective Resume Writing
Effective Resume Writing
 
Sample resume ppt
Sample resume pptSample resume ppt
Sample resume ppt
 
Resume writing ppt presentation
Resume writing ppt presentationResume writing ppt presentation
Resume writing ppt presentation
 

Semelhante a Easy steps to critical path determination and floats calculations for projects

Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
Aminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah Assagaf
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)Nikka Lopez
 
Aminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah Assagaf
 
Arts job solution [www.onlinebcs.com]
Arts job solution [www.onlinebcs.com]Arts job solution [www.onlinebcs.com]
Arts job solution [www.onlinebcs.com]Itmona
 

Semelhante a Easy steps to critical path determination and floats calculations for projects (10)

Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
Aminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyek
 
Critical path method (cpm)
Critical path method (cpm)Critical path method (cpm)
Critical path method (cpm)
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Aminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyekAminullah assagaf mp9 manajemen proyek
Aminullah assagaf mp9 manajemen proyek
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
Arts job solution [www.onlinebcs.com]
Arts job solution [www.onlinebcs.com]Arts job solution [www.onlinebcs.com]
Arts job solution [www.onlinebcs.com]
 
Lecture 5.pdf
Lecture 5.pdfLecture 5.pdf
Lecture 5.pdf
 

Mais de Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2Dr. Mahmoud Al-Naimi
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1Dr. Mahmoud Al-Naimi
 

Mais de Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
 

Último

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniquesugginaramesh
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 

Último (20)

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Comparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization TechniquesComparative Analysis of Text Summarization Techniques
Comparative Analysis of Text Summarization Techniques
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 

Easy steps to critical path determination and floats calculations for projects

  • 1. Easy Steps to Critical Path Determination and Floats Calculations for Projects Project Management Dr. Mahmoud Abbas Mahmoud Asst. Prof. 2016
  • 2. Easy Steps to Critical Path Determination and Floats Calculations for Projects We will illustrate these steps with the following Example: Dr. Mahmoud Abbas Mahmoud
  • 3. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 Example: For the project given in the following (AOA) network diagram: i) Find the critical activities. ii) Find the critical path (CP). iii) Find project completion time. iv) Find the free float (FF) for each activity. v) Summarize the results in a table. Note: all times are in (weeks)
  • 4. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 Critical Path Calculations
  • 5. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 Forward Pass:
  • 6. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 Forward Pass: Calculating the Earliest Start Time (ES):
  • 7. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 Forward Pass: Calculating the Earliest Start Time (ES): Earliest Start Time (ES)j=Max [ (ES)i + Dij ]
  • 8. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 Earliest Start Time (ES) for Start Event = (0) NOTE: (ES) for any Start Event = (0)
  • 9. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0
  • 10. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 10[0+10]= 10 0
  • 11. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 Max [(0+7) , (10+5)] = Max [7,15]= 15
  • 12. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 [10+ 6]= 16
  • 13. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 Max [(15+9) , (16+0)] = Max [24,16]= 24
  • 14. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 Max [(16+8) , (24+12)] = Max [24,36]= 36
  • 15. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 Project completion time is: 36 weeks
  • 16. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 Backward Pass:
  • 17. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36
  • 18. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 36
  • 19. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC):
  • 20. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC): Latest Completion Time (LC)i=Min [ (LC)j - Dij ]
  • 21. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 16 24 24 36 36 36 – 12 = 24
  • 22. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 24 16 24 24 36 36 Min [(36-8),(24-0)= Min[28,24] = 24
  • 23. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 15 15 24 16 24 24 36 36 24 – 9 = 15
  • 24. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 10 10 15 15 24 16 24 24 36 36 Min [(24-6),(15-5)= Min[18,10] = 10
  • 25. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Min [(15-7),(10-10)= Min[8, 0] = 0
  • 26. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  • 27. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 How to find the Critical Activities and the Critical Path ???
  • 28. Dr. Mahmoud Abbas Mahmoud Remember that only a critical activity can have a Zero Total Float (TF)
  • 29. Dr. Mahmoud Abbas Mahmoud Therefore, we will calculate the total floats for all activities and each activity has a ZERO total float (TF) will be a critical activity.
  • 30. Total Float (TF) calculations Dr. Mahmoud Abbas Mahmoud TFij = (LC)j – (ES)i – Dij A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  • 31. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity A B C D E F G Dummy
  • 32. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy For activity A (1, 2) TF = 10 – 0 – 10 = 0*
  • 33. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy
  • 34. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy For activity B (1, 3) TF = 15 – 0 – 7 = 8
  • 35. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy
  • 36. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy For activity C (2, 3) TF = 15 – 10 – 5 = 0*
  • 37. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy
  • 38. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy For activity D (3, 4) TF = 24 – 10 – 6 = 8
  • 39. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy
  • 40. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy For activity E (3, 5) TF = 24 – 15 – 9 = 0*
  • 41. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy
  • 42. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy For activity F (4, 6) TF = 36 – 16 – 8 = 12
  • 43. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy
  • 44. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy For activity G (5, 6) TF = 36 – 24 – 12 = 0*
  • 45. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy
  • 46. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy For Dummy activity (4, 5) TF = 24 – 16 – 0 = 8
  • 47. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy
  • 48. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy The Critical Activities are: (A, C, E, G) Critical Path is: (A C E G) Project completion time is: 36 weeks
  • 49. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  • 50. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free Float (FF) Calculations FFij = (ES)j – (ES)i – Dij
  • 51. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity A B C D E F G Dummy
  • 52. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A B C D E F G Dummy For activity A (1, 2) FF = 10 – 0 – 10 = 0
  • 53. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B C D E F G Dummy For activity B (1, 3) FF = 15 – 0 – 7 = 8
  • 54. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C D E F G Dummy For activity C (2, 3) FF = 15 – 10 – 5 = 0
  • 55. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C 0D E F G Dummy For activity D (3, 4) FF = 16 – 10 – 6 = 0
  • 56. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C 0D 0E F G Dummy For activity E (3, 5) FF = 24 – 15 – 9 = 0
  • 57. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C 0D 0E 12F G Dummy For activity F (4, 6) FF = 36 – 16 – 8 = 12
  • 58. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C 0D 0E 12F 0G Dummy For activity G (5, 6) FF = 36 – 24 – 12 = 0
  • 59. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 Free FloatActivity 0A 8B 0C 0D 0E 12F 0G 8Dummy For Dummy activity (4, 5) FF = 24 – 16 – 0 = 8
  • 60. Dr. Mahmoud Abbas Mahmoud Free FloatActivity 0A 8B 0C 0D 0E 12F 0G 8Dummy Think !!!!
  • 61. Dr. Mahmoud Abbas Mahmoud We can notice from these results that all critical activities must have zero free floats but not each activity that has zero free float must be critical. For example, activity (D) has zero Free Float but it is not critical. Free FloatActivity 0A 8B 0C 0D 0E 12F 0G 8Dummy
  • 62. Summary Activity Symbol Activity (i, j) Duration Dij ESi LCj TFij FFij A (1, 2) 10 0 10 0* 0 B (1, 3) 7 0 15 8 8 C (2, 3) 5 10 15 0* 0 D (2, 4) 6 10 24 8 0 E (3, 5) 9 15 24 0* 0 Dummy (4, 5) 0 16 24 8 8 F (4, 6) 8 16 36 12 12 G (5, 6) 12 24 36 0* 0 Notice that total float (TF) values marked with (*) mark are for critical activities. Dr. Mahmoud Abbas Mahmoud