This document provides an example of constructing an activity on arrow (AOA) network and activity on node (AON) network for a project with multiple activities. It shows the steps to calculate early start, early finish, late start, late finish, total float, and critical path for identifying the longest duration of project completion. The critical path is identified as A → C → G → J, with an overall project completion time of 27 days.